Shilottar Raichur, Raigarh

Deedo IDDL-RAI-SHILOTTARRAICHUR

10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1
Registrations3some projects hold several
Completion still due12 past their date
Median extension8 months67% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

3 MahaRERA registrations in Shilottar Raichur

1 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 8 months.

Projects in Shilottar Raichur

1 project registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Balaji SymphonyVinay AgrawalCompleted, extended 4 mo—69%
Shilottar Raichur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Vinay Agrawal1 project
  2. Vinay Agrawal1 project

Shilottar Raichur, in questions

How many projects in Shilottar Raichur run late?

10 in 10 MahaRERA registrations (3 of 3): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shilottar Raichur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology