MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 52% of its units are booked.

Rodpali, Raigarh 410206 · by Hareshkumar Rasiklal Shah · 50% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales52% booked30 of 58 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 17 Jan 2020, completion promised 28 Aug 2023, revised to 27 Aug 2024.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000024057
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002405717 Jan 202028 Aug 202327 Aug 2024Hareshkumar Rasiklal ShahProject page
Documents91

3 documents held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN Cardpan.pdf · uploaded 23 Dec 2019Source

Legal

  • Legal Title reporttitle report search report new.pdf · uploaded 23 Dec 2019Source
  • Declaration Form BFORM B.pdf · uploaded 6 Jan 2020Source

Migrated

  • 1 PAN Cardpan.pdf · uploaded 23 Dec 2019Source
  • 1 Copy of the legal title reporttitle report search report new.pdf · uploaded 23 Dec 2019Source
Show all 91 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesShivam 01 No emcumberance.pdf · uploaded 23 Dec 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERT.pdf · uploaded 23 Dec 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng cert new.pdf · uploaded 23 Dec 2019Source
  • 1 Proforma of Allotment letterShivam agnt to sale.pdf · uploaded 23 Dec 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 2 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERT.pdf · uploaded 2 Jan 2020Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 6 Jan 2020Source
  • 2 Proforma of Allotment letterShivam Allotment Letter 01 (3 files merged).pdf · uploaded 9 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20200102_0001.pdf · uploaded 13 Jan 2020Source
  • 2 Copy of Layout Approval (in case of layout)MYSCAN_20200102_0002.pdf · uploaded 13 Jan 2020Source
  • 3 Copy of Layout Approval (in case of layout)MYSCAN_20200102_0003.pdf · uploaded 13 Jan 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentMYSCAN_20200102_0001.pdf · uploaded 13 Jan 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentMYSCAN_20200102_0002.pdf · uploaded 13 Jan 2020Source
  • 3 Building Plan Approval / NA Order for plotted developmentMYSCAN_20200102_0003.pdf · uploaded 13 Jan 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 11 Sep 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERING CERTIFICATE (1).pdf · uploaded 11 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 11 Sep 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certficate.pdf · uploaded 31 Mar 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate -70_compressed (1).pdf · uploaded 31 Mar 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 19 Jul 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 ARCHITECT CERTIFICATE.pdf · uploaded 19 Jul 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 ARCHITECT CERTIFICATE 2.pdf · uploaded 19 Jul 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 ENGINEER CERTIFICATE 2.pdf · uploaded 19 Jul 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 ENGINEER CERTIFICATE.pdf · uploaded 19 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 19 Jul 2023Source
  • 1 Disclosure of sold/ booked inventoryBHIKHI DISCLOSURE OF SOLD.pdf · uploaded 19 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_compressed.pdf · uploaded 5 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 24 Nov 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 24 Nov 2023Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold.pdf · uploaded 24 Nov 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)self declaration june.pdf · uploaded 24 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)self declaration sept.pdf · uploaded 24 Nov 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan for change_compressed.pdf · uploaded 30 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC for Change.pdf · uploaded 30 Nov 2023Source
  • 2 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 30 Nov 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan for Change_compressed.pdf · uploaded 8 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Final Form 5.pdf · uploaded 9 Dec 2023Source
  • 3 Disclosure of sold/ booked inventoryDisclosure.pdf · uploaded 17 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration Edited.pdf · uploaded 17 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 24 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2A Shivam mar 2020.pdf · uploaded 31 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2A Shivam mar 2021.pdf · uploaded 31 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form 2A Shivam Mar 2022.pdf · uploaded 31 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5 Shivam.pdf · uploaded 11 Mar 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentnew plan 1.pdf · uploaded 1 Apr 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentnew plan 2.pdf · uploaded 1 Apr 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentnew plan 3.pdf · uploaded 1 Apr 2024Source
  • 9 Building Plan Approval / NA Order for plotted developmentnew plan 4.pdf · uploaded 1 Apr 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentNew CC_compressed.pdf · uploaded 1 Apr 2024Source
  • 3 Declaration about Commencement CertificateNew CC_compressed.pdf · uploaded 1 Apr 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)DocScanner 06-May-2024 1.pdf · uploaded 6 May 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_compressed.pdf · uploaded 6 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A.pdf · uploaded 6 May 2024Source
  • 4 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 6 May 2024View
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Bhikhi dev Shivam Form 3.pdf · uploaded 31 May 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Bhikhi Shivam Form 3 final.pdf · uploaded 31 May 2024Source
  • 4 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 25 Jun 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 25 Jun 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC PRINTS.pdf · uploaded 27 Jun 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrances to Legal.pdf · uploaded 6 Jul 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances to Legal.pdf · uploaded 6 Jul 2024Source
  • 1 CERSAI detailscersai.pdf · uploaded 6 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 6 Jul 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Seperate bank account- FORMAT CHANGED.pdf · uploaded 6 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation from Allotment Letter.pdf · uploaded 6 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementNo deviation from agreement for sale.pdf · uploaded 6 Jul 2024Source
  • 10 Building Plan Approval / NA Order for plotted developmentHighlighted one.pdf · uploaded 8 Aug 2024Source

Technical

  • DocumentMYSCAN_20200102_0001.pdf · uploaded 13 Jan 2020Source
  • DocumentMYSCAN_20200102_0002.pdf · uploaded 13 Jan 2020Source
  • DocumentMYSCAN_20200102_0003.pdf · uploaded 13 Jan 2020Source
  • DocumentMYSCAN_20200102_0001.pdf · uploaded 13 Jan 2020Source
  • DocumentMYSCAN_20200102_0002.pdf · uploaded 13 Jan 2020Source
  • DocumentMYSCAN_20200102_0003.pdf · uploaded 13 Jan 2020Source
  • DocumentPlan for change_compressed.pdf · uploaded 30 Nov 2023Source
  • DocumentPlan for Change_compressed.pdf · uploaded 8 Dec 2023Source
  • Documentnew plan 1.pdf · uploaded 1 Apr 2024Source
  • Documentnew plan 2.pdf · uploaded 1 Apr 2024Source
  • Documentnew plan 3.pdf · uploaded 1 Apr 2024Source
  • Documentnew plan 4.pdf · uploaded 1 Apr 2024Source
  • DocumentHighlighted one.pdf · uploaded 8 Aug 2024Source

Technical (Architect)

  • DocumentDocScanner 06-May-2024 1.pdf · uploaded 6 May 2024Source

Technical (Engineer)

  • Documentform 2_compressed.pdf · uploaded 6 May 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 53 SECTOR 16

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop58 units in all
Address
Plot No 53 Sector 16, Roadpali, Sector 16PIN 410206
Village
Rodpali, Panvel taluka
Land area for this project
800 sq m (8,606 sq ft)
Permissible built-up area
1,199 sq m (12,905 sq ft)
Sanctioned built-up area
1,199 sq m (12,905 sq ft)
Designated bank account
196
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 53 SECTOR 16

Land as published on MahaRERA's project page

PLOT NO 53 SECTOR 16

Boundaries

North
9 Mtr Wide To The North
South
Plot No 33 And 34 To The South
East
Plot No 52 To The East
West
11 Mtr Wide Road To The West

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking58 units

30 of 58 units booked (52%), as the promoter reported to MahaRERA

1BHK · 49 unitsShop · 9 units
TypeCarpet areaUnitsBooked
1BHK21.75 sq m · 234 sq ft52
1BHK23.16 sq m · 249 sq ft32
1BHK24.33 sq m · 262 sq ft21
1BHK24.45 sq m · 263 sq ft21
1BHK24.85 sq m · 267 sq ft11
1BHK24.96 sq m · 269 sq ft52
1BHK25.07 sq m · 270 sq ft52
1BHK25.11 sq m · 270 sq ft53
Show all 22 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK25.16 sq m · 271 sq ft11
1BHK25.17 sq m · 271 sq ft11
1BHK25.28 sq m · 272 sq ft52
1BHK25.43 sq m · 274 sq ft107
1BHK25.46 sq m · 274 sq ft11
1BHK25.85 sq m · 278 sq ft33
Shop9.16 sq m · 99 sq ft10
Shop9.3 sq m · 100 sq ft10
Shop9.55 sq m · 103 sq ft10
Shop9.57 sq m · 103 sq ft10
Shop9.64 sq m · 104 sq ft10
Shop9.73 sq m · 105 sq ft21
Shop15.31 sq m · 165 sq ft10
Shop19.03 sq m · 205 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSheetal Architect—
Chartered accountantJayesh Patel—
EngineerVilas Agharkar—
OtherVijaykumar Manilal Patel—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Rodpali

All 12 projects in Rodpali · Compare Shivam with another project

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology