Hareshkumar Rasiklal Shah
Deedo IDDD-1RVNOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 16 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| RamdootP52000016188 | Karanjade | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| RudraP52000016669 | Karanjade | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| ShivamP52000024057 | Rodpali | Certificate Signed | 28 Aug 2023 | 27 Aug 2024 | +12 mo |
| RudrakshaP52000048151 | Karanjade | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | +20 mo* |
Hareshkumar Rasiklal Shah, in questions
Does Hareshkumar Rasiklal Shah finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 16 mo late. Across Maharashtra, 73% kept their date.
How many projects has Hareshkumar Rasiklal Shah registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Hareshkumar Rasiklal Shah have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.