Extended 12 mo9 floorsRERA P52000006617
C1 and C2, Cluster C
Deedo IDDP-RAI-CN6E-C2MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked33%19 of 58 · MahaRERA
Completion21 Nov 202022 Nov 2019 · revised
Units & parking in C1 and C2
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK A | 39 m² (420 sq.ft) | 34 | 7 |
| 1 BHK B | 39.9 m² (430 sq.ft) | 24 | 12 |
As registered with MahaRERA
- RERA registration
- P52000006617 · registered 14 Aug 2017
- Promised completion
- 22 Nov 2019
- Revised completion
- 21 Nov 2020
- Sanctioned habitable floors
- 9
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-RAI-CN6E-C2
Questions about C1 and C2
When is C1 and C2 due for completion?
The MahaRERA registration promises 22 Nov 2019, revised to 21 Nov 2020.
How many floors does C1 and C2 have?
9 sanctioned habitable floors, as registered with MahaRERA.
Data through12 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology