RERA projects in Navi Mumbai Panvel Rigardh (Ct)
26 projects under 27 MahaRERA registrations, registered 2017–2025. 30% have a completion date extended beyond the one promised.
26RERA projects
27Registrationssome projects hold several
6Completion still due21 past their completion date
15 monthsMedian extension beyond promised date30% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 3 |
| 2019 | 8 |
| 2020 | 1 |
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 5 |
| 2024 | 1 |
| 2025 | 1 |
Projects in Navi Mumbai Panvel Rigardh (Ct)
26 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Soverien HillFullspace Realty LLP | PR1270002501066 | 1 Oct 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Shiv ElitePremji Dosha Vaviya | P52000077070 | 23 Jul 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Ashtavinayak CornerAshtavinayak Builders | P52000052730 | 22 Sep 2023 | 30 Jun 2027 | — | Not yet due | 0 |
| Yasho Nandanvan Co-Operative Housing Society Ltd.Kedar Buildcon Private Limited | P52000051284 | 8 Jun 2023 | 30 Sep 2026 | — | Promised date passed | 0 |
| Navankur Co-Operative Housing Society Ltd.Kedar Buildcon Private Limited | P52000051169 | 1 Jun 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Nandai ApartmentJeevan Life Spaces | P52000050358 | 5 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| GeeCee EmeraldGeeCee Ventures Limited | P52000050116 | 15 Mar 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Tukaram PalacePremji Dosha Vaviya | P52000046051 | 15 Jun 2022 | 31 Mar 2023 | 31 Mar 2024 | Extended 12 mo | 0 |
| Sai Deep ResidencyPavan Mahatma Devalkar | P52000034601 | 11 Apr 2022 | 31 Aug 2026 | — | Promised date passed | 0 |
| A 1 RishikeshDhriti Builders & Developers LLP | P52000029934 | 15 Jul 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Yash PrathamYash Builders And Developers | P52000026729 | 21 Oct 2020 | 30 Jun 2022 | — | Promised date passed | 0 |
| Apex HomeLalji Nathalal Devda | P52000022696 | 12 Oct 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| MetropolisMetro Infra | P52000022444 | 24 Sep 2019 | 30 Dec 2022 | 30 Dec 2023 | Extended 12 mo | 0 |
| CalistaBluescape Infra | P52000022210 | 5 Sep 2019 | 15 Nov 2026 | — | Not yet due | 0 |
| Yashwant ParkNeelkanth Enterprises | P52000021765 | 23 Jul 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| Surya DeepPillars India Constructions | P52000021435 | 28 Jun 2019 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| Regency PalmsRegency Inc | P52000021191, P52000021209 | 14 Jun 2019 | 1 Jun 2024 | 1 Jun 2025 | Extended 12 mo | 0 |
| Future VisionFuture Homes Developers | P52000020171 | 29 Mar 2019 | 30 Mar 2022 | — | Promised date passed | 0 |
| Shree Gauri KrupaShree Ganesh Builders & Developers | P52000018981 | 28 Dec 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Shree Ganesh KrupaYjnj Construction Pvt Ltd | P52000018800 | 5 Dec 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Mahalaxmi KrupaSurmanj Construction | P52000017551 | 28 Aug 2018 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| Jay GaneshG N Group Builders And Developers | P52000012834 | 7 Sep 2017 | 30 Nov 2018 | 30 Jun 2022 | Extended 43 mo | 0 |
| Shivshankar KalashSuresh Shivshankar Sharma | P52000010959 | 31 Aug 2017 | 1 Jun 2018 | — | Promised date passed | 0 |
| Krishna DhamLandmark Construction | P52000009937 | 22 Aug 2017 | 31 Mar 2018 | 31 Mar 2019 | Extended 12 mo | 0 |
| Prime VillaLeera Ramji Arethiya | P52000004578 | 9 Aug 2017 | 26 Dec 2019 | — | Promised date passed | 0 |
| Kvk Keshar Baug IM/S. Kvk Homes | P52000002105 | 31 Jul 2017 | 8 Nov 2021 | — | Promised date passed | 0 |
Other localities in Panvel
- Ulawe678 projects
- Vadghar (Ct)421 projects
- Panvel301 projects
- Wahal299 projects
- Karanjade250 projects
- Taloje Panchnad151 projects
- Dapoli142 projects
- Kharghar137 projects
- Kamothe86 projects
- New Panvel74 projects
- Kalamboli58 projects
- Taloje Majkur43 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Kedar Buildcon Private Limited2 projects
- Premji Dosha Vaviya2 projects
- Ashtavinayak Builders1 project
- Bluescape Infra1 project
- Dhriti Builders & Developers LLP1 project
- Fullspace Realty LLP1 project
- Future Homes Developers1 project
- GeeCee Ventures Limited1 project
- G N Group Builders And Developers1 project
- Jeevan Life Spaces1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology