Deedo IDDP-RAI-PWQDCompletion was pushed back 4 months, to Mar 2027; no MahaRERA orders on record; 40% of its units are booked.
Kevale, Raigarh 410206 · by Priyal Buildcon LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2027
- This projectRegistered 8 Jul 2021, completion promised 30 Nov 2026, revised to 30 Mar 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Wing A4 floors · 16 units44% booked
- Wing B4 floors · 16 units63% booked
- Wing C5 floors · 20 units20% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000029833
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000029833 | 8 Jul 2021 | 30 Nov 2026 | 30 Mar 2027 | Priyal Buildcon LLP | Project page |
Documents137
2 documents held by Deedo, 135 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card - Priyal Buildcon LLP.pdf · uploaded 10 Jun 2021Source
Legal
Migrated
- 1 PAN CardPan Card - Priyal Buildcon LLP.pdf · uploaded 10 Jun 2021Source
Show all 137 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout Plan_compressed.pdf · uploaded 10 Jun 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentCIDCO_NAINA_BP 517_CC Signed dwgs-compressed_compressed-compressed (1) (1).pdf · uploaded 10 Jun 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCIDCO_NAINA_BP-00517_2020_CCLetter.pdf · uploaded 10 Jun 2021Source
- 1 Details of encumbrancesEncumbrances certificate Govind Greens.pdf · uploaded 23 Jun 2021Source
- 1 Declaration in FORM BForm B-Jayesh Gandhi.pdf · uploaded 23 Jun 2021Source
- 1 Proforma of Allotment letterAgreement for Sale draft.pdf · uploaded 23 Jun 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentZone approval by CIDCO_compressed.pdf · uploaded 28 Jun 2021Source
- 3 Commencement Certificates / NA Order for plotted developmentCIDCO_NAINA_BP-00517_2020_CCLetter.pdf · uploaded 28 Jun 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate - Govind Greens-compressed.pdf · uploaded 28 Jun 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Govind Greens FORM3.pdf · uploaded 28 Jun 2021Source
- 2 Proforma of Allotment letterAllotment Letter_Govind Greens.pdf · uploaded 28 Jun 2021Source
- 1 Copy of the legal title reportTitle Search report Kewale.pdf · uploaded 29 Jun 2021Source
- 1 Declaration about Commencement CertificateDeclaration for commencement certificate.pdf · uploaded 29 Jun 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Rera Certificate.pdf · uploaded 2 Jul 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Rera Certificate.pdf · uploaded 30 Oct 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers CertifICATE.pdf · uploaded 30 Oct 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Govind Greens Form-3-CA Certificate.pdf · uploaded 30 Oct 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architect Rera Certificate.pdf · uploaded 19 Jan 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Engineers Certificate.pdf · uploaded 19 Jan 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Priyal Form-3 10-01-2022_11zon.pdf · uploaded 19 Jan 2022Source
- 1 Disclosure of sold/ booked inventoryGovind Greens _ Sales inventory disclosure.pdf · uploaded 25 Jan 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certifcate 31 03 2022_compressed.pdf · uploaded 27 May 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Govind Greens enginer certifcate 31 03 2022.pdf · uploaded 27 May 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)GOVIND GREENS CA CERTIFICATE-compressed.pdf · uploaded 27 May 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA ARCHITECT CERTIFICATE 13-07-2022_compressed.pdf · uploaded 18 Jul 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certifcate Govind Greens_compressed.pdf · uploaded 18 Jul 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 Govind Greens Form-3-CA Certificate 30-06-2022.pdf · uploaded 18 Jul 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate_compressed.pdf · uploaded 27 Oct 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng certificate_compressed.pdf · uploaded 27 Oct 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA C A Certificate_compressed.pdf · uploaded 27 Oct 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate-compressed.pdf · uploaded 2 Jan 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 31 12 2022.pdf · uploaded 7 Jan 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A certificate FORM 3.pdf · uploaded 18 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2021-22.pdf · uploaded 6 Feb 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT RERA CERTIFICATE 31-03-2023 Compressed.pdf · uploaded 20 Apr 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Grovid Greens compressed.pdf · uploaded 20 Apr 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificage FORM 3 31 03 2023.pdf · uploaded 27 Apr 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)1Architect certificage 30 06 23.pdf · uploaded 27 Jul 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Enginerring Certificate 30 06 2023.pdf · uploaded 27 Jul 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 C A Certificate from no 3 signed.pdf · uploaded 27 Jul 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)5 CA Certificate Form 5 F Y 2022 2023.pdf · uploaded 27 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)5 CA Certificate Form 5 F Y 2022 2023.pdf · uploaded 27 Jul 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 ARCHITECT CERTIFICATE 30-09-2023.pdf · uploaded 3 May 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Achitect Certificate 27 12 2023.pdf · uploaded 3 May 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 ARCHITECT CERTIFICATE 31-03-2024.pdf · uploaded 3 May 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-1 ARCHITECT CERTIFICATE 30-09-2023.pdf · uploaded 3 May 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form No 2 Engineer certificate 31 03 2024.pdf · uploaded 3 May 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 ENGINEER CERTIFCATE DEC 2023.pdf · uploaded 3 May 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 CA Certificate - 31-12-2023.pdf · uploaded 3 May 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form No 3 C A Certifcate 31 03 2024.pdf · uploaded 3 May 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM No 2 Engineer Certificate 31 03 2024.pdf · uploaded 24 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2 A Quality certificate from Eng.pdf · uploaded 24 May 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM No 3 C A Certificate 23 05 2024.pdf · uploaded 24 May 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbance Legal.pdf · uploaded 5 Jun 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbance Legal.pdf · uploaded 5 Jun 2024Source
- 2 Disclosure of sold/ booked inventoryBook Inventory.pdf · uploaded 5 Jun 2024Source
- 1 CERSAI detailsCersai declaration.pdf · uploaded 5 Jun 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsForm a Jayshri Jethwa.pdf · uploaded 5 Jun 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 5 Jun 2024Source
- 1 Proforma of Agreement for saleAgreement for Sale draft.pdf · uploaded 5 Jun 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 5 Jun 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Quality Assurance Govind Greens.pdf · uploaded 18 Jun 2024Source
- 2 Proforma of Agreement for saleModel Sale Agreement RERA Govind Greens.pdf · uploaded 18 Jun 2024Source
- 3 Proforma of Allotment letterModel form of allotment letter Govind Greens.pdf · uploaded 18 Jun 2024Source
- 1 Deviation Report with respect to Allotment letterGovind Greens Allotment letter deviation.pdf · uploaded 18 Jun 2024Source
- 1 Deviation Report with respect to model copy of AgreementGovind Greens AFS deviation.pdf · uploaded 18 Jun 2024Source
- 2 Declaration in FORM BForm B Jayesh Gandhi 24052025.pdf · uploaded 20 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 16 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30062024.pdf · uploaded 28 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Achitect Certificate 27 12 2023.pdf · uploaded 28 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 19102024.pdf · uploaded 28 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form No 3 C A Certifcate 30 06 2024.pdf · uploaded 28 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 From 3 C A certificate 31 12 2023.pdf · uploaded 28 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Engineer Certificate 30092024.pdf · uploaded 28 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no 2 30 06 2024.pdf · uploaded 28 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 30092024.pdf · uploaded 28 Jan 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate 31122024 compressed.pdf · uploaded 29 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate From No 2 dt 31 12 2024.pdf · uploaded 29 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate form 1.pdf · uploaded 8 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 8 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form No 2 (Engineer's Certiifcate).pdf · uploaded 8 May 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure sold inventory.pdf · uploaded 8 May 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Annexure -C (form 2A).pdf · uploaded 8 May 2025Source
- 1 Declaration in FORM BAffidavit.pdf · uploaded 16 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate 20102024.pdf · uploaded 20 Jun 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 C A Certifcate 31 12 2024.pdf · uploaded 20 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 Jul 2025Source
- Withdrawal Update Form 1Form No 1 30 09 2025 (Architect Certificate).pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 1Form No 1 30 09 2025 (Architect Certificate).pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 2Form no 2 Engineers certificate.pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 2Form no 2 Engineers certificate.pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 3From No 3 G G 30 09 2025.pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 3From No 3 G G 30 09 2025.pdf · uploaded 23 Dec 2025Source
- Form 5 (FY 2024-2025)Form No 5 Govind Greens AY 2025 26.pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 11 Form No 1 Arichtect Certificate_compressed.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1Form No 1 30 09 2025 (Architect Certificate).pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 22 Engineer Cerificaqte Form 2 30 06 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 22 Engineer Cerificaqte Form 2 30 06 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 33 Form No 3 C A Certificate 30 06 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 33 Form No 3 C A Certificate 30 06 2025.pdf · uploaded 4 Feb 2026Source
- Form 2A (FY 2024-2025)Annexure A 2024 2025.pdf · uploaded 4 Feb 2026Source
- Withdrawal Update Form 1From No 1 Govind Greens 31 12 2025.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 2From No 2 Govind Greens 31 12 2025.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 3From No 3 Govind Greens 31 12 2025.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 1From No 1 Govind Greens 31 03 2026_compressed.pdf · uploaded 8 May 2026Source
- Withdrawal Update Form 1From No 1 Govind Greens 31 03 2026_compressed.pdf · uploaded 8 May 2026Source
- Withdrawal Update Form 2From No 2 Govind Greens 31 03 2026.pdf · uploaded 8 May 2026Source
- Withdrawal Update Form 2From No 2 Govind Greens 31 03 2026.pdf · uploaded 8 May 2026Source
- Withdrawal Update Form 3From No 3 Govind Greens 31 12 2025.pdf · uploaded 8 May 2026Source
- Withdrawal Update Form 3Form No 3 Govind Greens 31 03 2026_260508_174553.pdf · uploaded 8 May 2026Source
- Form 2A (FY 2025-2026)Form 2A_05-05-2026.pdf · uploaded 8 May 2026Source
Technical
- DocumentLayout Plan_compressed.pdf · uploaded 10 Jun 2021Source
- DocumentCIDCO_NAINA_BP 517_CC Signed dwgs-compressed_compressed-compressed (1) (1).pdf · uploaded 10 Jun 2021Source
- DocumentAmended CC Approved Plan Sheet 1.pdf · uploaded 21 May 2026Source
- DocumentAmended CC Approved Plan Sheet 2.pdf · uploaded 21 May 2026Source
- DocumentAmended CC Approved Plan Sheet 3.pdf · uploaded 21 May 2026Source
- DocumentAmended CC Approved Plan Sheet 4.pdf · uploaded 21 May 2026Source
- DocumentAmended CC Approved Plan Sheet 5.pdf · uploaded 21 May 2026Source
Technical (Architect)
- DocumentForm 1 30062024.pdf · uploaded 28 Jan 2025Source
- Document1 Achitect Certificate 27 12 2023.pdf · uploaded 28 Jan 2025Source
- DocumentArchitect Certificate 19102024.pdf · uploaded 28 Jan 2025Source
- DocumentForm 1 Architect Certificate 31122024 compressed.pdf · uploaded 29 Jan 2025Source
- DocumentArchitect Certificate form 1.pdf · uploaded 8 May 2025Source
- DocumentFrom No 1 Govind Greens 31 03 2026_compressed.pdf · uploaded 6 May 2026Source
Technical (Engineer)
- DocumentForm no 2 30 06 2024.pdf · uploaded 28 Jan 2025Source
- DocumentEngineer Certificate 30092024.pdf · uploaded 28 Jan 2025Source
- DocumentEngineer Certificate From No 2 dt 31 12 2024.pdf · uploaded 29 Jan 2025Source
- DocumentForm No 2 (Engineer's Certiifcate).pdf · uploaded 8 May 2025Source
- DocumentFrom No 2 Govind Greens 31 03 2026.pdf · uploaded 6 May 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO 71/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —52 units in all
- Address
- SURVEY NO 71/2, AT VILLAGE KEWALE, TALUKA PANVEL, swapnanagari, morbe dam road, VILLAGE KEWALEPIN 410206
- Village
- Kevale, Panvel taluka
- Location
- 19.02174, 73.15732
- Land area for this project
- 1,536 sq m (16,528 sq ft)
- Permissible built-up area
- 2,457 sq m (26,445 sq ft)
- Sanctioned built-up area
- 2,415 sq m (25,990 sq ft)
- Recreational open space
- 254 sq m (2,739 sq ft)
- Designated bank account
- 82
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 71/2,AT VILLAGE KEWALE, TALUKA PANVEL
Boundaries
- North
- Survey No 72
- South
- Survey No 71-1
- East
- Road
- West
- Survey No 71-1
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking52 units
52 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing A | — | — | 16 |
| Wing B | — | — | 16 |
| Wing C | — | — | 20 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | An Arch | — |
| Chartered accountant | Dipika Patel | — |
| Chartered accountant | Manish Kumar Gupta | — |
| Chartered accountant | Pooja Patwari | — |
| Engineer | Jayesh Gandhi | — |
| Engineer | Rahul Sashte & Associates | — |
| Other | Shakti Constructions | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kevale
- Rising SunRERA PM1270002600457
- Arham OneRERA P52000055460
- Panvel Pride Phase 2RERA P52000030827
- Praradi PearlRERA P52000027439
- Abhinandan ClorisRERA P52000022977
- Panvel PrideRERA P52000021424
All 7 projects in Kevale · Compare Govind Greens with another project