Others · 1 building · 50 unitsRERA P52000021318

Shreepati Solitaire

Deedo IDDP-RAI-SN3V

MahaRERA shows it completed; no MahaRERA orders on record; 20% of its units are booked.

Karanjade, Raigarh 410206 · by Rudra Supertech Llp

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales20% booked10 of 50 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 21 Jun 2019, completion promised 30 Dec 2023.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000021318
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002131821 Jun 201930 Dec 202330 Dec 2023Rudra Supertech LLPProject page
Documents41

1 document held by Deedo, 40 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN- Rudra LLP.pdf · uploaded 12 Jun 2019Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 12 Jun 2019Source
  • Declaration Form BForm B.pdf · uploaded 13 Jun 2019Source

Migrated

  • 1 PAN CardPAN- Rudra LLP.pdf · uploaded 12 Jun 2019Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 12 Jun 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout 1.pdf · uploaded 12 Jun 2019Source
  • 2 Copy of Layout Approval (in case of layout)Layout 2.pdf · uploaded 12 Jun 2019Source
Show all 41 documentsShow fewer documents

Migrated

  • 3 Copy of Layout Approval (in case of layout)Layout 3.pdf · uploaded 12 Jun 2019Source
  • 4 Copy of Layout Approval (in case of layout)Layout 4.pdf · uploaded 12 Jun 2019Source
  • 1 Building Plan Approval (IOD)Layout 1.pdf · uploaded 12 Jun 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 12 Jun 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2- Engg Cert.pdf · uploaded 12 Jun 2019Source
  • 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 12 Jun 2019Source
  • 2 Proforma of Allotment letterDraft Agreement for Sale.pdf · uploaded 12 Jun 2019Source
  • 1 Details of encumbrancesNo Encumbrances Cert.pdf · uploaded 13 Jun 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 13 Jun 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1- Arch Cert.pdf · uploaded 13 Jun 2019Source
  • 1 Certificates of CA (Form 3)Form 3- CA cert.pdf · uploaded 13 Jun 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1- Arch Cert.pdf · uploaded 16 Jul 2019Source
  • 1 Form 2AForm 2A-RSLLP.pdf · uploaded 16 Jul 2019Source
  • 3 Proforma of Allotment letterDraft Agreement-Rudra Supertech LLP.pdf · uploaded 6 Nov 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form- 1.pdf · uploaded 13 Nov 2019Source
  • 2 Form 2AForm2A.pdf · uploaded 13 Nov 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 15 Feb 2020Source
  • 3 Form 2AForm 2A.pdf · uploaded 15 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 FY 19-20 RSLLP.pdf · uploaded 27 Apr 2021Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)170-3-KAR RERA.pdf · uploaded 26 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)UPLOAD FORM 5.pdf · uploaded 16 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)1 Form 5-2020-21 RSLLP-For Upload.pdf · uploaded 21 Feb 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development170-OC (1).pdf · uploaded 4 Apr 2023Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)170-3 Form 4.pdf · uploaded 5 Apr 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation Letter Rudra Supertech LLP.pdf · uploaded 21 Apr 2023Source
  • 1 Status of ConveyanceConveyance Letter Rudra Supertech LLP-.pdf · uploaded 21 Apr 2023Source

Technical

  • DocumentLayout 1.pdf · uploaded 12 Jun 2019Source
  • DocumentLayout 1.pdf · uploaded 12 Jun 2019Source
  • DocumentLayout 2.pdf · uploaded 12 Jun 2019Source
  • DocumentLayout 3.pdf · uploaded 12 Jun 2019Source
  • DocumentLayout 4.pdf · uploaded 12 Jun 2019Source

Technical (Architect)

  • Document170-3-KAR RERA.pdf · uploaded 26 Feb 2022Source

Technical (Engineer)

  • DocumentForm 2- Engg Cert.pdf · uploaded 12 Jun 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO. 170, SECTOR3

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1 RK, 2 BHK, Shop50 units in all
Address
Plot No. 170, Sector-3, Karanjade, Panvel, Karanjade, Sector-3PIN 410206
Village
Karanjade, Panvel taluka
Land area for this project
950 sq m (10,225 sq ft)
Permissible built-up area
1,419 sq m (15,278 sq ft)
Sanctioned built-up area
1,419 sq m (15,278 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO. 170SECTOR3

Land as published on MahaRERA's project page

PLOT NO. 170, SECTOR-3, KARANJADE, PANVEL

Boundaries

North
Open Space
South
20 Mtr Wide Road
East
Plot No 170a
West
20 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking50 units

10 of 50 units booked (20%), as the promoter reported to MahaRERA

1 BHK · 28 units1 RK · 4 units2 BHK · 8 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1 BHK19.38 sq m · 209 sq ft10
1 BHK22.72 sq m · 245 sq ft10
1 BHK25.13 sq m · 270 sq ft10
1 BHK25.17 sq m · 271 sq ft10
1 BHK25.71 sq m · 277 sq ft20
1 BHK25.74 sq m · 277 sq ft10
1 BHK25.76 sq m · 277 sq ft21
1 BHK26.28 sq m · 283 sq ft42
Show all 35 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1 BHK26.29 sq m · 283 sq ft10
1 BHK26.55 sq m · 286 sq ft10
1 BHK26.57 sq m · 286 sq ft11
1 BHK26.69 sq m · 287 sq ft51
1 BHK26.73 sq m · 288 sq ft31
1 BHK27 sq m · 291 sq ft10
1 BHK27.2 sq m · 293 sq ft10
1 BHK27.38 sq m · 295 sq ft11
1 BHK27.95 sq m · 301 sq ft10
1 RK13.77 sq m · 148 sq ft10
1 RK16.3 sq m · 175 sq ft10
1 RK16.55 sq m · 178 sq ft11
1 RK16.91 sq m · 182 sq ft10
2 BHK28.09 sq m · 302 sq ft11
2 BHK29.2 sq m · 314 sq ft10
2 BHK37.02 sq m · 399 sq ft10
2 BHK39.71 sq m · 427 sq ft30
2 BHK39.93 sq m · 430 sq ft10
2 BHK40.22 sq m · 433 sq ft11
Shop13.77 sq m · 148 sq ft10
Shop15.16 sq m · 163 sq ft10
Shop15.41 sq m · 166 sq ft10
Shop18.57 sq m · 200 sq ft10
Shop20.41 sq m · 220 sq ft20
Shop22.15 sq m · 238 sq ft20
Shop24.22 sq m · 261 sq ft10
Shop30.38 sq m · 327 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architects—
Chartered accountantA. T. Upadhye & Co.—
Chartered accountantDSSM & Co. LLP—
EngineerS R Consultants—
OtherArvind M Rudani—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Karanjade

All 265 projects in Karanjade · Compare Shreepati Solitaire with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology