Completion was pushed back 4 months, to Jul 2029; no MahaRERA orders on record; 3% of its units are booked.

Karanjade, Raigarh 410206 · by Bipin Chandrakant Munoth, Riddhi Developers

DeliveryExtended 4 moPromised Mar 2029 · now due Jul 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales3% booked3 of 99 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2029

  • This projectRegistered 5 Mar 2026, completion promised 31 Mar 2029, revised to 31 Jul 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1270002502609
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12700025026095 Mar 202631 Mar 202931 Jul 2029Riddhi DevelopersProject page
Documents33

1 document held by Deedo, 32 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN-BCM.pdf · uploaded 19 Dec 2025Source

Legal

  • Declaration Form BLegal Title Report.pdf · uploaded 19 Dec 2025Source
  • Declaration Form BForm B.pdf · uploaded 19 Dec 2025Source
  • Declaration Form BTripartite Agreement-CIDCO-28-04-2008.pdf · uploaded 19 Dec 2025Source
  • OthersTripartite Agreement-CIDCO-28-04-2008.pdf · uploaded 14 Feb 2026Source
  • OthersAnn-A-Discl-Interest-Bipin.pdf · uploaded 14 Feb 2026Source
  • OthersAgreement to Lease dt-15-04-2008.pdf · uploaded 24 Feb 2026Source
Show all 33 documentsShow fewer documents

Legal

  • OthersAffidavit-Riddhi-Past Experience.pdf · uploaded 26 Feb 2026Source
  • Declaration Form BAgreement to Lease dt-15-04-2008.pdf · uploaded 26 Feb 2026Source

Migrated

  • Withdrawal Update Form 1Form-1-Primark-March-2026.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form-1-Primark-March-2026.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2Withdrawal Update Form 2 · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2Form-2-Primark-March-2026.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3Form-3-Primark-March-2026.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3Form-3-Primark-March-2026.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form-1-Primark-March-2026.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 2Form-2-Primark-March-2026.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 3Form-3-Primark-March-2026.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 1Form-1-Primark-June-2026.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2Form-2-Primark-June-2026.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3Form-3-Primark-June-2026.pdf · uploaded 17 Jul 2026Source
  • Form 2A (FY 2025-2026)Fom-2A-Primark-2025-26.pdf · uploaded 17 Jul 2026Source

Technical

  • DocumentPlan-1.pdf · uploaded 19 Dec 2025Source
  • DocumentPlan-2.pdf · uploaded 19 Dec 2025Source
  • DocumentPlan-3.pdf · uploaded 19 Dec 2025Source
  • DocumentPlan-4.pdf · uploaded 19 Dec 2025Source
  • DocumentPlan-5.pdf · uploaded 19 Dec 2025Source
  • DocumentAnnexure A Declaration.pdf · uploaded 19 Dec 2025Source
  • OthersForm-1-Primark.pdf · uploaded 19 Dec 2025Source
  • OthersCIDCO Email dt 31 03 2025.pdf · uploaded 30 Jan 2026Source

Technical (Architect)

  • DocumentForm-1-Primark-June-2026.pdf · uploaded 17 Jul 2026Source

Technical (Engineer)

  • DocumentForm-2-Primark-June-2026.pdf · uploaded 17 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No. 14, Sector 2A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—104 units in all
Address
Plot No. 14, Sector 2APIN 410206
Village
Karanjade, Panvel taluka
Land area for this project
1,949 sq m (20,984 sq ft)
Permissible built-up area
9,426 sq m (1,01,465 sq ft)
Sanctioned built-up area
9,426 sq m (1,01,465 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
171
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 14Sector 2A

Land as published on MahaRERA's project page

Plot No. 14, Sector 2A, Karanjade, Tal. Panvel, Distt. Raigad

Boundaries

North
Plot No. 1
South
15 Mtrs. wide Road
East
Plot No. 14/A and 14/2
West
Plot No. 13 and Plot No. 2+3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking104 units

104 units registered

— · 104 units
TypeCarpet areaUnits
——104

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeepak Pandurang Thakare—
EngineerSamarth Agarwal—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Karanjade

All 265 projects in Karanjade · Compare Munoth Primark with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology