Florence Landmark
Deedo IDDP-RAI-GZGQCompletion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.
Damat, Raigarh 410101 · by Palak Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- P52000052599Registered 11 Sep 2023, completion promised 31 Dec 2030, revised to 30 Apr 2031.
- P52000052774Registered 22 Sep 2023, completion promised 31 Dec 2030, revised to 30 Apr 2031.
No extension certificate on record.
2 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Wing D6 floors · 49 units0% booked
- Wing E6 floors · 44 units0% booked
- Wing F3 floors · 11 units0% booked
- Wing G3 floors · 11 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations2
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000052599 | 11 Sep 2023 | 31 Dec 2030 | 30 Apr 2031 | Palak Developers | Project page |
| P52000052774 | 22 Sep 2023 | 31 Dec 2030 | 30 Apr 2031 | Palak Developers | Project page |
Documents159
2 documents held by Deedo, 157 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
Legal
- Other – LegalP52000052774 · OTHER LEGAL 1.pdf · uploaded 21 Jun 2023Source
- Declaration Form BP52000052774 · PALAK P3 Affidavit palak developer PROMOTER FORM B.pdf · uploaded 21 Jun 2023Source
- Other – LegalP52000052599 · OTHER LEGAL 1.pdf · uploaded 21 Jun 2023Source
- Legal Title reportP52000052599 · 1 Copy of the legal title report.pdf · uploaded 21 Jun 2023Source
Show all 159 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardP52000052774 · 1 PAN Card.pdf · uploaded 21 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP52000052774 · PHASE 3.pdf · uploaded 21 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP52000052774 · 1 Commencement Certificates _ NA Order for plotted development (1).pdf · uploaded 21 Jun 2023Source
- 1 Declaration in FORM BP52000052774 · PALAK P3 Affidavit palak developer PROMOTER FORM B.pdf · uploaded 21 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · RERA PHASE 3 CA CERTIFICATE.pdf · uploaded 21 Jun 2023Source
- 1 Proforma of Agreement for saleP52000052774 · AGREEMENT OF SALE FINAL 1.pdf · uploaded 21 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52000052774 · palak P3 declaration farmat A.pdf · uploaded 21 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementP52000052774 · PALAK P3 No deviation in agreement for sale.pdf · uploaded 21 Jun 2023Source
- 1 Other – LegalP52000052774 · OTHER LEGAL 1.pdf · uploaded 21 Jun 2023Source
- 1 PAN CardP52000052599 · 1 PAN Card (1).pdf · uploaded 21 Jun 2023Source
- 1 Copy of the legal title reportP52000052599 · 1 Copy of the legal title report.pdf · uploaded 21 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP52000052599 · PHASE 2.pdf · uploaded 21 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP52000052599 · 1 Commencement Certificates _ NA Order for plotted development.pdf · uploaded 21 Jun 2023Source
- 1 Declaration about Commencement CertificateP52000052599 · PALAK P2 Declaration.pdf · uploaded 21 Jun 2023Source
- 1 Declaration in FORM BP52000052599 · Affidavit Palak developers PROMOTER FORM B.pdf · uploaded 21 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP52000052599 · PALAK P2 Annexure A Deepak shah.pdf · uploaded 21 Jun 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsP52000052599 · PALAK P2 Annexure A SAHIL PANCHALA.pdf · uploaded 21 Jun 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsP52000052599 · PALAK P2 Annexure A Dixit shah.pdf · uploaded 21 Jun 2023Source
- 1 Proforma of Agreement for saleP52000052599 · AGREEMENT OF SALE FINAL (1).pdf · uploaded 21 Jun 2023Source
- 1 Proforma of Allotment letterP52000052599 · ALLOTMENT LETTER FINAL.pdf · uploaded 21 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52000052599 · PALAK P2 FORMAT A Account.pdf · uploaded 21 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterP52000052599 · PALAK P2 No deviation in allotment letter.pdf · uploaded 21 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementP52000052599 · PALAK P2 No deviation in agreement sale.pdf · uploaded 21 Jun 2023Source
- 1 Other – LegalP52000052599 · OTHER LEGAL 1.pdf · uploaded 21 Jun 2023Source
- 1 a Details of encumbrances concerned to FinanceP52000052599 · 2 b Details of encumbrances concerned to Legal_compressed.pdf · uploaded 26 Jun 2023Source
- 1 b Details of encumbrances concerned to LegalP52000052599 · 2 b Details of encumbrances concerned to Legal_compressed.pdf · uploaded 26 Jun 2023Source
- 1 CERSAI detailsP52000052774 · 1 CERSAI details (3)_compressed.pdf · uploaded 27 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP52000052774 · 1 Disclosure of Interest in Other Real Estate Organizations (1) sahil panchala_compressed.pdf · uploaded 27 Jun 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsP52000052774 · 1 Disclosure of Interest in Other Real Estate Organizations (2) deepak shah_compressed (1).pdf · uploaded 27 Jun 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsP52000052774 · 1 Disclosure of Interest in Other Real Estate Organizations (2) dixit shah_compressed (1).pdf · uploaded 27 Jun 2023Source
- 1 Proforma of Allotment letterP52000052774 · allotment letter new.pdf · uploaded 27 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterP52000052774 · 1 Deviation Report with respect to Allotment letter_compressed.pdf · uploaded 27 Jun 2023Source
- 1 Copy of Layout Approval (in case of layout)P52000052599 · PALAK DEV PHASE 02 (1) FINAL.pdf · uploaded 27 Jun 2023Source
- 2 Copy of Layout Approval (in case of layout)P52000052599 · PALAK DEV PHASE 02 - COPY 2_compressed (1).pdf · uploaded 27 Jun 2023Source
- 3 Copy of Layout Approval (in case of layout)P52000052599 · built up area.pdf · uploaded 3 Jul 2023Source
- 2 a Details of encumbrances concerned to FinanceP52000052599 · PALAK P2 No Encumbrance Concern to Finance (1)_compressed.pdf · uploaded 6 Jul 2023Source
- 2 b Details of encumbrances concerned to LegalP52000052599 · PALAK P2 No Encumbrance Concern to Finance (1)_compressed.pdf · uploaded 6 Jul 2023Source
- 1 CERSAI detailsP52000052599 · PALAK P2 REPORT CERSAI_compressed.pdf · uploaded 6 Jul 2023Source
- 1 Copy of Layout Approval (in case of layout)P52000052774 · PALAK DEV PHASE 03 COPY_compressed.pdf · uploaded 8 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · CA PALAK.pdf · uploaded 11 Jul 2023Source
- 1 Copy of the legal title reportP52000052774 · LEGAL SEARCH TITLE FINAL FINAL_compressed.pdf · uploaded 3 Aug 2023Source
- 2 Copy of Layout Approval (in case of layout)P52000052774 · BUILDING LAYOUT.pdf · uploaded 3 Aug 2023Source
- 3 Copy of Layout Approval (in case of layout)P52000052774 · BUILT UP AREA STATEMENT.pdf · uploaded 3 Aug 2023Source
- 1 a Details of encumbrances concerned to FinanceP52000052774 · ENCUMBRANCES CONCERN TO FINANCE FINAL.pdf · uploaded 4 Aug 2023Source
- 2 a Details of encumbrances concerned to FinanceP52000052774 · ENCUMBRANCES CONCERN TO LEGAL FINAL.pdf · uploaded 4 Aug 2023Source
- 1 b Details of encumbrances concerned to LegalP52000052774 · ENCUMBRANCES CONCERN TO FINANCE FINAL.pdf · uploaded 4 Aug 2023Source
- 2 b Details of encumbrances concerned to LegalP52000052774 · ENCUMBRANCES CONCERN TO LEGAL FINAL.pdf · uploaded 4 Aug 2023Source
- 1 Declaration about Commencement CertificateP52000052774 · COMMENCEMENT CERTIFICATE FORMAT D_compressed.pdf · uploaded 4 Aug 2023Source
- 3 a Details of encumbrances concerned to FinanceP52000052774 · palak partnershipdeed new_compressed.pdf · uploaded 11 Sep 2023Source
- 3 b Details of encumbrances concerned to LegalP52000052774 · palak partnershipdeed new_compressed.pdf · uploaded 11 Sep 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsP52000052774 · palak partnershipdeed new_compressed.pdf · uploaded 11 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052774 · ARCHITECT CERTIFICATE 31 MARCH 2024.pdf · uploaded 1 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052774 · ENGINEER CERTIFICATE 31 MARCH 2024.pdf · uploaded 1 Jun 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · Florence Landmark Phase 3 Jan Mar 24 Form 03 (1).pdf · uploaded 1 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052599 · ARCHITECT CERTIFICATE PHASE 2 - 31 MARCH 2024.pdf · uploaded 1 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052599 · ENGINEER CERTIFICATE PHASE 2 - 31MARCH 2024.pdf · uploaded 1 Jun 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · Florence Landmark Phase 02 jan mar 2024 form 03.pdf · uploaded 1 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052774 · ARCHITECT CERTIFICATE PHASE 3 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052774 · architect certificate phase 3 SEP 2024.pdf · uploaded 7 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · Florence Landmark ph 03 FY 2024-25 q1-signed01_compressed.pdf · uploaded 7 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · Florence Landmark Ph 03 Form 03 FY 24-25 Q2 signed A_compressed.pdf · uploaded 7 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052774 · ENGINEER CERTIFICATE PHAASE 3 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052774 · engineer certificate phase 3 SEP 2024.pdf · uploaded 7 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052599 · ARCHITECT CERTIFICATE PHASE 2 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052599 · architect certificate phase 2 SEP 2024.pdf · uploaded 7 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · Florence Landmark Ph 02 FY 2024-25 q1-signed01_compressed.pdf · uploaded 7 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · Florence Landmark Ph 02 FY 24-25 q2 signed a.pdf · uploaded 7 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052599 · ENGINEER CERTIFICATE PHASE 2 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052599 · engineer certificate phase 2 SEP 2024.pdf · uploaded 7 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052774 · phase III architect certificate.pdf · uploaded 24 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · Florence Landmark Ph 03 Q3 FY 24-25 signed.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052774 · phase III engineer certificate.pdf · uploaded 24 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052599 · phase II architect certificate.pdf · uploaded 24 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · Florence Landmark Ph 02 Q3 FY 24-25 signed.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052599 · phase II engineer certificate.pdf · uploaded 24 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052774 · form 1 phase III Q4.pdf · uploaded 23 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052774 · Phase 03 Florence Form 03 Jan Mar 2025 - signed_compressed.pdf · uploaded 23 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052774 · form 2 phase III Q4.pdf · uploaded 23 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52000052599 · form 1 Phase II Q4.pdf · uploaded 23 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52000052599 · Phase 02 Florence Form 03 Jan Mar 2025 - signed_compressed.pdf · uploaded 23 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52000052599 · form 2 phase II Q4.pdf · uploaded 23 Apr 2025Source
- Form 1P52000052774 · form 1 phase 3 Q1 2025.pdf · uploaded 21 Jul 2025Source
- Form 2P52000052774 · form 2 phase 3 Q1 2025.pdf · uploaded 21 Jul 2025Source
- Form 3P52000052774 · palak florence ph 03 - SIGNED FORM 03 APR JUN 25.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryP52000052774 · PHASE III unsold sold inventory 2025.pdf · uploaded 21 Jul 2025Source
- Form 1P52000052599 · form 1 phase 2 Q1 2025.pdf · uploaded 21 Jul 2025Source
- Form 2P52000052599 · form 2 phase 2 Q1 2025.pdf · uploaded 21 Jul 2025Source
- Form 3P52000052599 · palak florence ph 02 - SIGNED form 03 apr jun 25.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryP52000052599 · PHASE II unsold sold inventory 2025.pdf · uploaded 21 Jul 2025Source
- Form 1P52000052774 · FORM 1 PHASE 3 Q2 2025-26.pdf · uploaded 7 Feb 2026Source
- Form 2P52000052774 · FORM 2 PHASE 3 Q2 2025-26.pdf · uploaded 7 Feb 2026Source
- Form 3P52000052774 · Palak Phase 03 form 03.pdf · uploaded 7 Feb 2026Source
- Disclosure of Sold and Booked InventoryP52000052774 · Disclosure of sold booked and unsold inventory.pdf · uploaded 7 Feb 2026Source
- Form 1P52000052774 · palak developers phase 3 architect certificate.pdf · uploaded 7 Feb 2026Source
- Form 2P52000052774 · palak developers phase 3 form2 Engineer Certificate.pdf · uploaded 7 Feb 2026Source
- Form 3P52000052774 · Florence Phase 03 Form 03 Oct Dec 25 - signed.pdf · uploaded 7 Feb 2026Source
- Disclosure of Sold and Booked InventoryP52000052774 · Disclosure of sold booked and unsold inventory.pdf · uploaded 7 Feb 2026Source
- Form 1P52000052599 · Palak developers Phase 2 form 1 Q2.pdf · uploaded 7 Feb 2026Source
- Form 2P52000052599 · Palak developers Phase 2 form 2 Q2.pdf · uploaded 7 Feb 2026Source
- Form 3P52000052599 · Palak developers Phase 2 form 03 Q 2.pdf · uploaded 7 Feb 2026Source
- Disclosure of Sold and Booked InventoryP52000052599 · disclosure of sold booked and unsold inventory.pdf · uploaded 7 Feb 2026Source
- Form 1P52000052599 · florence land mark phase 2 form1.pdf · uploaded 7 Feb 2026Source
- Form 2P52000052599 · florence land mark phase 2 form2.pdf · uploaded 7 Feb 2026Source
- Form 3P52000052599 · Florence Phase 02 Form 03 Oct Dec 25 - signed.pdf · uploaded 7 Feb 2026Source
- Disclosure of Sold and Booked InventoryP52000052599 · Disclosure of sold booked and unsold inventory.pdf · uploaded 7 Feb 2026Source
- Form 1P52000052774 · FORM 1 Q4 2025-26 PHASE 3.pdf · uploaded 29 Apr 2026Source
- Form 2P52000052774 · FORM 2 Q4 2025-26 PHASE 3.pdf · uploaded 29 Apr 2026Source
- Form 3P52000052774 · Palak Dev Ph3 Form 3 Jan-mar26.pdf · uploaded 29 Apr 2026Source
- Disclosure of Sold and Booked InventoryP52000052774 · PHASE III Q4 2025-26.pdf · uploaded 29 Apr 2026Source
- Form 1P52000052599 · PHASE 2 FORM 1 Q4.pdf · uploaded 30 Apr 2026Source
- Form 2P52000052599 · phase 2 form 2 Q4.pdf · uploaded 30 Apr 2026Source
- Form 3P52000052599 · Palak dev Ph2 Form 3 Jan-mar26.pdf · uploaded 30 Apr 2026Source
- Disclosure of Sold and Booked InventoryP52000052599 · PHASE II Q4 2025-26 (1).pdf · uploaded 30 Apr 2026Source
- Withdrawal Update Form 1P52000052774 · ph 3 form 1 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 2P52000052774 · ph 3 form 2 Q 1 2026-27.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 3P52000052774 · Florence landmark Phase 3 Form 03 Apr Jun 2026.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 1P52000052599 · ph 2 form 1 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 2P52000052599 · ph 2 form 2 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 3P52000052599 · Palak developers Phase 2 Form 03 Apr Jun 2026.pdf · uploaded 21 Jul 2026Source
- Form 5 (FY 2025-2026)P52000052774 · FORM 5 FY 2025-26 PALAK FLORENCE PH 3.pdf · uploaded 30 Sep 2026Source
- Form 5 (FY 2025-2026)P52000052599 · FORM 5 FY 2025-26 PALAK FLORENCE PH 2.pdf · uploaded 30 Sep 2026Source
Technical
- DocumentP52000052774 · PHASE 3.pdf · uploaded 21 Jun 2023Source
- DocumentP52000052599 · PHASE 2.pdf · uploaded 21 Jun 2023Source
- DocumentP52000052599 · PALAK DEV PHASE 02 (1) FINAL.pdf · uploaded 27 Jun 2023Source
- DocumentP52000052599 · PALAK DEV PHASE 02 - COPY 2_compressed (1).pdf · uploaded 27 Jun 2023Source
- DocumentP52000052599 · built up area.pdf · uploaded 3 Jul 2023Source
- DocumentP52000052774 · PALAK DEV PHASE 03 COPY_compressed.pdf · uploaded 8 Jul 2023Source
- DocumentP52000052774 · BUILDING LAYOUT.pdf · uploaded 3 Aug 2023Source
- DocumentP52000052774 · BUILT UP AREA STATEMENT.pdf · uploaded 3 Aug 2023Source
Technical (Architect)
- DocumentP52000052774 · ARCHITECT CERTIFICATE PHASE 3 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052774 · architect certificate phase 3 SEP 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052599 · ARCHITECT CERTIFICATE PHASE 2 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052599 · architect certificate phase 2 SEP 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052774 · phase III architect certificate.pdf · uploaded 24 Jan 2025Source
- DocumentP52000052599 · phase II architect certificate.pdf · uploaded 24 Jan 2025Source
- DocumentP52000052774 · form 1 phase III Q4.pdf · uploaded 23 Apr 2025Source
- DocumentP52000052599 · form 1 Phase II Q4.pdf · uploaded 23 Apr 2025Source
- DocumentP52000052774 · ph 3 form 1 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
- DocumentP52000052599 · ph 2 form 1 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
Technical (Engineer)
- DocumentP52000052774 · ENGINEER CERTIFICATE PHAASE 3 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052774 · engineer certificate phase 3 SEP 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052599 · ENGINEER CERTIFICATE PHASE 2 JUNE 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052599 · engineer certificate phase 2 SEP 2024.pdf · uploaded 7 Nov 2024Source
- DocumentP52000052774 · phase III engineer certificate.pdf · uploaded 24 Jan 2025Source
- DocumentP52000052599 · phase II engineer certificate.pdf · uploaded 24 Jan 2025Source
- DocumentP52000052774 · form 2 phase III Q4.pdf · uploaded 23 Apr 2025Source
- DocumentP52000052599 · form 2 phase II Q4.pdf · uploaded 23 Apr 2025Source
- DocumentP52000052774 · ph 3 form 2 Q 1 2026-27.pdf · uploaded 21 Jul 2026Source
- DocumentP52000052599 · ph 2 form 2 Q1 2026-27.pdf · uploaded 21 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 71/1/B/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Phases
- 2
- Unit types
- 1BHK, 1RK, 2BHK115 units in all
- Address
- 71/1/B/1, Survey No 71/1/B/1, Neral Karjat Highway, Near Sunrise Residency, Damat, DamatPIN 410101
- Village
- Damat, Karjat taluka
- Location
- 19.04701, 73.31378
- Land area for this project
- 4,967 sq m (53,460 sq ft)
- Permissible built-up area
- 15,136 sq m (1,62,918 sq ft)
- Sanctioned built-up area
- 4,413 sq m (47,501 sq ft)
- Recreational open space
- 1,355 sq m (14,585 sq ft)
- Designated bank account
- 51
- Developed in phases
- Yes
- Also registered as
- Florence Landmark Phase 2, Florence Landmark Phase - 3
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
71/1/B/1
Boundaries
- North
- Survey No 70
- South
- Survey No 71 1 B 2 And 71 1 A
- East
- Survey No 71 And 72
- West
- State Highway No 76
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking115 units
0 of 115 units booked (0%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52000052599 | Wing D | 1BHK | 27.6 sq m · 297 sq ft | 4 | 0 |
| P52000052599 | Wing D | 1BHK | 27.61 sq m · 297 sq ft | 19 | 0 |
| P52000052599 | Wing D | 1BHK | 27.93 sq m · 301 sq ft | 14 | 0 |
| P52000052599 | Wing D | 1BHK | 32.02 sq m · 345 sq ft | 4 | 0 |
| P52000052599 | Wing D | 1RK | 20.03 sq m · 216 sq ft | 4 | 0 |
| P52000052599 | Wing D | 2BHK | 40.6 sq m · 437 sq ft | 4 | 0 |
| P52000052599 | Wing E | 1BHK | 27.61 sq m · 297 sq ft | 20 | 0 |
| P52000052599 | Wing E | 1BHK | 27.93 sq m · 301 sq ft | 12 | 0 |
Show all 20 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52000052599 | Wing E | 1BHK | 32.02 sq m · 345 sq ft | 4 | 0 |
| P52000052599 | Wing E | 1RK | 20.8 sq m · 224 sq ft | 4 | 0 |
| P52000052599 | Wing E | 2BHK | 40.6 sq m · 437 sq ft | 4 | 0 |
| P52000052774 | Wing F | 1BHK | 27.99 sq m · 301 sq ft | 1 | 0 |
| P52000052774 | Wing F | 1BHK | 28.09 sq m · 302 sq ft | 4 | 0 |
| P52000052774 | Wing F | 1BHK | 28.71 sq m · 309 sq ft | 2 | 0 |
| P52000052774 | Wing F | 1BHK | 28.98 sq m · 312 sq ft | 1 | 0 |
| P52000052774 | Wing F | 1BHK | 29.98 sq m · 323 sq ft | 1 | 0 |
| P52000052774 | Wing F | 2BHK | 43.2 sq m · 465 sq ft | 2 | 0 |
| P52000052774 | Wing G | 1BHK | 28.09 sq m · 302 sq ft | 7 | 0 |
| P52000052774 | Wing G | 1BHK | 28.1 sq m · 302 sq ft | 2 | 0 |
| P52000052774 | Wing G | 2BHK | 43.2 sq m · 465 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals11
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Architect | The Design India Group | — | P52000052599 |
| Architect | The Design India Group | — | P52000052774 |
| Chartered accountant | Jagdish Bhagat & Co | — | P52000052774 |
| Chartered accountant | Jagdish Bhagat & Co | — | P52000052599 |
| Chartered accountant | Jagdish Chetanlal Bhagat | — | P52000052774 |
| Chartered accountant | Jagdish Chetanlal Bhagat | — | P52000052599 |
| Chartered accountant | Pratik Kothawale | — | P52000052774 |
| Chartered accountant | Pratik Kothawale | — | P52000052599 |
Show all 11 professionalsShow fewer professionals
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Chartered accountant | Tanveer Bhagat | — | P52000052599 |
| Engineer | the design india group | — | P52000052599 |
| Engineer | The Design India Group | — | P52000052774 |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Damat
- Diamond HeightsRERA PM1270002602291
- Mecca AvenueRERA PM1270002601824
- Mount CityRERA PR1271012601253
- Baug-E-ZainabRERA PM1270002502279
- Maryam ComplexRERA PM1270002500135
- Madina ComplexRERA P52000053474
- Florence Landmark Phase 1RERA P52000051375
- Sun CityRERA P52000017041
All 11 projects in Damat · Compare Florence Landmark with another project