RERA projects in Boriwali
3 projects under 4 MahaRERA registrations, registered 2017–2025. 75% have a completion date extended beyond the one promised.
Locality
3RERA projects
4Registrationssome projects hold several
2Completion still due2 past their completion date
4 monthsMedian extension beyond promised date75% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 2 |
| 2025 | 1 |
Projects in Boriwali
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aurum VistaIndu Developers | P52000078699 | 7 Jan 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Olympeo RetreatParadiso Realty Solutions LLP | P52000055126, P52000056416 | 4 Mar 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| nest 1 phase 2Rajesh Virendra Gupta | P52000010177 | 24 Aug 2017 | 30 Sep 2018 | 30 Sep 2019 | Extended 12 mo | 0 |
Other localities in Karjat
Most active promoters
By projects registered here, as named on MahaRERA.
- Indu Developers1 project
- Paradiso Realty Solutions LLP1 project
- Rajesh Virendra Gupta1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology