2 projects under 3 MahaRERA registrations, registered 2017–2022. 67% have a completion date extended beyond the one promised.
Locality
2RERA projects
3Registrationssome projects hold several
3Completion still due0 past their completion date
32 monthsMedian extension beyond promised date67% of registrations extended
0Regulatory casesnone on MahaRERA's lists
11Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 1 |
Projects in Bardi
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Riva RythmSahabhagi Infra Pvt Ltd. | P52000014541, P52000034946 | 8 Dec 2017 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Swapnpurti ResidencyShankar Balu Khopade | P52000010739 | 31 Aug 2017 | 12 Dec 2022 | 31 Dec 2027 | Extended 60 mo | 0 |
Other localities in Karjat
Most active promoters
By projects registered here, as named on MahaRERA.
- Sahabhagi Infra Pvt Ltd.1 project
- Shankar Balu Khopade1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology