Akurli, Raigarh
Deedo IDDL-RAI-AKURLI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects23
Registrations24some projects hold several
Completion still due1113 past their date
Median extension4 months46% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
24 MahaRERA registrations in Akurli
3 not yet due8 extended, not yet due13 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Akurli
23 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| TattvamB And B Properties | Due Mar 2032 | — | — |
| Kasturi AnvayaPanache Realty | Due Dec 2030 | — | — |
| Kasturi AureliaPanache Realty | Due Apr 2029, extended 4 mo | — | — |
| Olive BoulevardOlive Infra & Lifestyle LLP | Due Apr 2030, extended 4 mo | — | — |
| Balaji EvergreenVishesh Supreme Projects LLP | Due Apr 2030, extended 4 mo | — | — |
Nearby: other villages in Panvel
Most active promoters
- Supreme Holdings & Hospitality (India) Limited3 projects
- Future Infra2 projects
- Panache Realty2 projects
- Simran Enterprises2 projects
- B And B Properties1 project
- Future Buildcon1 project
- Future Homes Constructions1 project
- Jindal Builders And Developers1 project
- Kanakia Spaces Realty Private Limited1 project
- Konkan Shrusti Infra Developers LLP1 project
Akurli, in questions
How many projects in Akurli run late?
9 in 10 MahaRERA registrations (21 of 24): their completion date was extended or has passed, data through 29 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Akurli by Deedo. Medians on fewer than 3 deeds are not shown.
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology