Deedo IDDP-PUN-QPHJMahaRERA shows it completed, after its date was pushed back 2 years; no MahaRERA orders on record; 87% of its units are booked.
Warje, Pune 411058 · Property rates in Warje · by L M Bafna
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 2 years
- This projectRegistered 29 Jul 2017, completion promised 31 Dec 2019, revised to 30 Dec 2021.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Rental · Oct 2026
- Rental · Aug 2026
- Title transfer · Jul 2026
- Rental · 24 mo · Jul 2026
- Mortgage · May 2026No amount
- Rental · 22 mo · May 2026
- Rental · Apr 2026
- Resale · Apr 2026
- Resale · Mar 2026
- Mortgage · Mar 2026
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Oct 2026 | Not on record | Rental | — | View Rental, Oct 2026 | |
| Aug 2026 | Suvan Forett · 1 | Rental | — | View Rental, Aug 2026 | |
| Jul 2026 | Not on record | Title transfer | — | View Title transfer, Jul 2026 | |
| Jul 2026 | Unit F/702 | Rental | — | View Rental, Jul 2026 | |
| May 2026 | Suvan Forett · 403 | Mortgage | — | View Mortgage, May 2026 | |
| May 2026 | Suvan Forett · 802 | Rental | — | View Rental, May 2026 | |
| Apr 2026 | Not on record | Rental | — | View Rental, Apr 2026 | |
| Apr 2026 | Suvan Forett · 6 | Resale | 637 sq ft | View Resale, Apr 2026 | |
| Mar 2026 | Suvan Forett · 2 | Resale | 718 sq ft | View Resale, Mar 2026 | |
| Mar 2026 | Not on record | Mortgage | — | View Mortgage, Mar 2026 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100001907
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100001907 | 29 Jul 2017 | 31 Dec 2019 | 30 Dec 2021 | L M Bafna | Project page |
Documents54
2 documents held by Deedo, 52 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.pdf · uploaded 11 Apr 2023Source
Legal
Show all 54 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)1.pdf · uploaded 17 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Warje (2).pdf · uploaded 17 Jul 2017Source
- 1 Declaration in FORM BForm B.pdf · uploaded 17 Jul 2017Source
- 1 Proforma of Allotment letterAllotment Letter and Agreement to Sale.pdf · uploaded 17 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 21 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 21 Jul 2017Source
- 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 21 Jul 2017Source
- 2 Building Plan Approval (IOD)1.pdf · uploaded 24 Jan 2018Source
- 3 Building Plan Approval (IOD)2.pdf · uploaded 24 Jan 2018Source
- 4 Building Plan Approval (IOD)3.pdf · uploaded 24 Jan 2018Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Jan 2018Source
- 1 Certificates of CA (Form 5)Form V - CA - RERA Audit Certificate Suvan Forett, Warje.pdf · uploaded 22 Nov 2018Source
- 2 Certificates of CA (Form 5)Form V - CA - 2019 RERA Audit Certificate Suvan Forett, Warje.pdf · uploaded 14 Oct 2019Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Suvan Forett Warje.pdf · uploaded 3 Jun 2021Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)1.pdf · uploaded 5 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2.pdf · uploaded 27 Jan 2023Source
- 7 Architect’s Certificate on Completion of Project (Form 4)Form 4 - New - Warje.pdf · uploaded 27 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORETT Form 5 F Y 18-19.pdf · uploaded 16 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Forett 19-20.pdf · uploaded 10 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Forett 20-21.pdf · uploaded 10 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Forett 21-22.pdf · uploaded 10 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 FY 19-20.pdf · uploaded 10 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 20-21.pdf · uploaded 10 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 21-22.pdf · uploaded 10 Apr 2023Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development1.pdf · uploaded 10 Apr 2023Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2.pdf · uploaded 10 Apr 2023Source
- 8 Architect’s Certificate on Completion of Project (Form 4)FORM 4 - FORETT.pdf · uploaded 10 Apr 2023Source
- 1 PAN CardPAN CARD.pdf · uploaded 11 Apr 2023Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 ARCHITECT'S CERTIFICATE - WARJE.pdf · uploaded 11 Apr 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 F Y 2018-19.pdf · uploaded 11 Apr 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate F Y 2017-18.pdf · uploaded 11 Apr 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate F Y 2018-19.pdf · uploaded 11 Apr 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate F Y 2019-20.pdf · uploaded 11 Apr 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate F Y 2020-21.pdf · uploaded 11 Apr 2023Source
- 2 Certificates of CA (Form 3)Form 3 F Y 2017-18.pdf · uploaded 11 Apr 2023Source
- 3 Certificates of CA (Form 3)Form 3 F Y 2018-19.pdf · uploaded 11 Apr 2023Source
- 4 Certificates of CA (Form 3)Form 3 F Y 2019-20.pdf · uploaded 11 Apr 2023Source
- 5 Certificates of CA (Form 3)Form 3 F Y 2020-21.pdf · uploaded 11 Apr 2023Source
- 1 Status of ConveyanceConveyance Deed Index.pdf · uploaded 11 Apr 2023Source
Technical
Technical (Architect)
- DocumentForm 1 F Y 2018-19.pdf · uploaded 11 Apr 2023Source
Technical (Engineer)
- DocumentEngineer Certificate F Y 2020-21.pdf · uploaded 11 Apr 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No. 2, S. No. 114/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2rlk39 units in all
- Address
- S. No. 114/1, Plot No. 2, WARJE, URIT NAGARPIN 411058
- Village
- Warje, Haveli taluka
- Location
- 18.49100, 73.79453
- Land area for this project
- 1,591 sq m (17,125 sq ft)
- Permissible built-up area
- 2,543 sq m (27,369 sq ft)
- Sanctioned built-up area
- 1,570 sq m (16,896 sq ft)
- Designated bank account
- 21
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S. No. 114/1, Plot No. 2
Boundaries
- North
- S No 120 and portion of S No 114-1
- South
- 24 m Road
- East
- Portion of S No 114-1 and Amenity Space
- West
- S No 113
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking39 units
34 of 39 units booked (87%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2rlk | 58.47 sq m · 629 sq ft | 5 | 4 |
| 2rlk | 58.59 sq m · 631 sq ft | 5 | 4 |
| 2rlk | 59.28 sq m · 638 sq ft | 4 | 3 |
| 2rlk | 59.3 sq m · 638 sq ft | 5 | 5 |
| 2rlk | 59.72 sq m · 643 sq ft | 5 | 4 |
| 2rlk | 59.72 sq m · 643 sq ft | 5 | 5 |
| 2rlk | 59.8 sq m · 644 sq ft | 5 | 5 |
| 2rlk | 59.8 sq m · 644 sq ft | 5 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shinde Joshi and Associates | — |
| Registered real estate agent | Amit Arun Kapade | — |
Source: MahaRERA project page. Contact details are not shown.
Suvan Forett in numbers
Registered deals, summarised
Deedo has 75 registered documents at Suvan Forett, from Sep 2018 to Oct 2026: 35 sales, 13 leave and licence agreements, 26 mortgages. The median registered sale since Sep 2018 works out to about ₹11,500 per sq ft, at a median of ₹74 L a deal; 9% of sales were resales.
- What is the price per sq ft at Suvan Forett?
- The median registered sale since Sep 2018 works out to about ₹11,500 per sq ft, at a median of ₹74 L a deal; 9% of sales were resales.
- How many properties have been sold at Suvan Forett?
- 35 sales are registered at Suvan Forett, 3 of them resales.
- Are properties at Suvan Forett rented out?
- Yes: 13 leave and licence agreements are registered at Suvan Forett, at a median rent since Sep 2018 of about ₹26,000 a month with a deposit of about ₹60,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Suvan Forett by Deedo, last updated with deals registered in Oct 2026.
Latest deal · Rental · Oct 2026