Residential / Group Housing · 1 building · 30 unitsRERA P52100050115

Varad Residency

Deedo IDDP-PUN-R9HB

Its promised completion date, Sep 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 57% of its units are booked.

Wakad, Pune 411057 · Property rates in Wakad · by Vilas Bhagaji Arekar

Delivery2 mo past duePromised Sep 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales57% booked17 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Sep 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 15 Mar 2023, completion promised 16 Sep 2026, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100050115
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005011515 Mar 202316 Sep 202616 Sep 2026Vilas Bhagaji ArekarProject page
Documents156

2 documents held by Deedo, 154 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 13 Oct 2022Source

Legal

  • Legal Title reportCircular 28 Search Report.pdf · uploaded 13 Oct 2022Source
  • Declaration Form BForm B Aff.pdf · uploaded 13 Oct 2022Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 13 Oct 2022Source
  • 1 Copy of the legal title reportCircular 28 Search Report.pdf · uploaded 13 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceDecl Non Encumberance.pdf · uploaded 13 Oct 2022Source
Show all 156 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalDecl Leagal Enc.pdf · uploaded 13 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 13 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction plan.pdf · uploaded 13 Oct 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentElevation.pdf · uploaded 13 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement_compressed.pdf · uploaded 13 Oct 2022Source
  • 1 Declaration about Commencement CertificateDecl CC.pdf · uploaded 13 Oct 2022Source
  • 1 Declaration in FORM BForm B Aff.pdf · uploaded 13 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect cert.pdf · uploaded 13 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng Cert.pdf · uploaded 13 Oct 2022Source
  • 1 CERSAI detailsCersai Undertaking.pdf · uploaded 13 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDecl Bank Acc.pdf · uploaded 13 Oct 2022Source
  • 1 Proforma of Allotment letterDraft Allotment letter.pdf · uploaded 16 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterDecl Deviation allotment letter dec 2022.pdf · uploaded 16 Dec 2022Source
  • 1 Proforma of Agreement for saleDraft Agreement Varad Residency 2022.pdf · uploaded 8 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation in draft Agreement Varad Resi.pdf · uploaded 8 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Annexure A.pdf · uploaded 15 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 5 Mar 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_compressed.pdf · uploaded 26 Jun 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3_compressed.pdf · uploaded 26 Jun 2023Source
  • 2 Proforma of Agreement for saleVarad Residency Raw Agreement Draft.pdf · uploaded 7 Jul 2023Source
  • 3 Proforma of Agreement for saleVarad Residency Raw Agreement Draft-NEW.pdf · uploaded 21 Aug 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 21 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate.pdf · uploaded 24 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3_compressed.pdf · uploaded 24 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryDiscloser Of Sold Unsold Inventory.pdf · uploaded 27 Oct 2023Source
  • 2 Disclosure of sold/ booked inventoryDsclosure of Sold -Unsold Inventory.pdf · uploaded 31 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form No 5.pdf · uploaded 31 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Form 1.pdf · uploaded 10 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 10 Jan 2024Source
  • 3 Disclosure of sold/ booked inventorySOLD-UNSOLD.pdf · uploaded 10 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 10 Jan 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentHPSC0085_compressed.pdf · uploaded 6 Mar 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentHPSC0084_compressed.pdf · uploaded 6 Mar 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentHPSC0086_compressed.pdf · uploaded 6 Mar 2024Source
  • 2 Declaration about Commencement CertificateSKM_C284e27030804030.pdf · uploaded 6 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Apr 2024Source
  • 4 Disclosure of sold/ booked inventorySU.pdf · uploaded 14 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 SCAN_compressed.pdf · uploaded 14 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 18 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2.pdf · uploaded 18 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A-22-23.pdf · uploaded 18 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A-23-24.pdf · uploaded 18 Jul 2024Source
  • 5 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 18 Jul 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 18 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 17 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2.pdf · uploaded 17 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 17 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 17 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)F5.pdf · uploaded 17 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 17 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 17 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2.pdf · uploaded 17 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 17 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)F5.pdf · uploaded 17 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F2.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySU.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)F1.pdf · uploaded 20 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 20 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySU.pdf · uploaded 20 Apr 2025Source
  • Form 1F1-final.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Self-declaration of Quarterly ProgressSU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-SEPT-24.pdf · uploaded 26 May 2025Source
  • Form 2F2-SEPT-24.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Self-declaration of Quarterly ProgressSU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 1F1-FINAL.pdf · uploaded 26 May 2025Source
  • Form 2F2-FINAL.pdf · uploaded 26 May 2025Source
  • Form 3F3-FINAL.pdf · uploaded 26 May 2025Source
  • Disclosure of Sold and Booked InventorySU-FINAL.pdf · uploaded 26 May 2025Source
  • Form 5 (FY 2022-2023)F5-22-23.pdf · uploaded 26 May 2025Source
  • Form 5 (FY 2023-2024)F5-23-24.pdf · uploaded 26 May 2025Source
  • Withdrawal Update Form 1f1.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 1f1.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2F2-FINAL.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 2F2-FINAL.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3F3-FINAL.pdf · uploaded 17 Jul 2025Source
  • Withdrawal Update Form 3F3-FINAL.pdf · uploaded 17 Jul 2025Source
  • Form 5 (FY 2024-2025)F5-VARAD RESIDENCY (1).pdf · uploaded 29 Sep 2025Source
  • Withdrawal Update Form 1F1-FINAL.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2F2-FINAL.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3F3-FINAL.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1F1-Q3.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2F2-Q3.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3F3-Q3.pdf · uploaded 20 Jan 2026Source
  • Form 2A (FY 2022-2023)Form 2A-FY 22-23.pdf · uploaded 16 Jun 2026Source
  • Form 2A (FY 2023-2024)Form 2A-FY 23-24.pdf · uploaded 16 Jun 2026Source
  • Form 2A (FY 2024-2025)Form 2A-FY 24-25.pdf · uploaded 16 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A-FY 25-26.pdf · uploaded 16 Jun 2026Source
  • Form 5 (FY 2025-2026)F5-FY 25-26.pdf · uploaded 16 Jun 2026Source
  • Withdrawal Update Form 1F1-Q4.pdf · uploaded 11 Jul 2026Source
  • Withdrawal Update Form 2F2-Q4.pdf · uploaded 11 Jul 2026Source
  • Withdrawal Update Form 3F3-Q4.pdf · uploaded 11 Jul 2026Source
  • Withdrawal Update Form 1F1-JUNE-26.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2FORM-2-JUNE-26.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3F3-JUNE -26.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1F1-JUNE-26.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2FORM-2-JUNE-26.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3F 3 - VARAD RESIDENCY (1).pdf · uploaded 12 Aug 2026Source

Technical

  • DocumentLayout.pdf · uploaded 13 Oct 2022Source
  • DocumentSanction plan.pdf · uploaded 13 Oct 2022Source
  • DocumentElevation.pdf · uploaded 13 Oct 2022Source
  • DocumentHPSC0085_compressed.pdf · uploaded 6 Mar 2024Source
  • DocumentHPSC0084_compressed.pdf · uploaded 6 Mar 2024Source
  • DocumentHPSC0086_compressed.pdf · uploaded 6 Mar 2024Source
  • DocumentPLAN-01.pdf · uploaded 21 Aug 2026Source
  • DocumentPLAN-02.pdf · uploaded 21 Aug 2026Source
  • DocumentPLAN-03.pdf · uploaded 21 Aug 2026Source

Technical (Architect)

  • DocumentFORM-1.pdf · uploaded 17 Nov 2024Source
  • DocumentFORM-1.pdf · uploaded 17 Nov 2024Source
  • DocumentFORM-1.pdf · uploaded 20 Jan 2025Source
  • DocumentF1.pdf · uploaded 20 Apr 2025Source
  • DocumentF1-JUNE-26.pdf · uploaded 18 Jul 2026Source

Technical (Engineer)

  • DocumentF2.pdf · uploaded 17 Nov 2024Source
  • DocumentF2.pdf · uploaded 17 Nov 2024Source
  • DocumentF2.pdf · uploaded 20 Jan 2025Source
  • DocumentFORM-2.pdf · uploaded 20 Apr 2025Source
  • DocumentFORM-2-JUNE-26.pdf · uploaded 18 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 73/1A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Office space, Shop30 units in all
Address
73/1A, Hinjewadi Road, Near bhumkar VastiPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
1,000 sq m (10,764 sq ft)
Permissible built-up area
2,694 sq m (29,000 sq ft)
Sanctioned built-up area
2,694 sq m (29,000 sq ft)
Designated bank account
89
Developed in phases
No

Survey, CTS, gat or plot numbers

73/1A

Land as published on MahaRERA's project page

73/1A

Boundaries

North
Chinchwad Hinjewadi DP Road
South
Survey No 73part
East
Property of Mr Eknath Bhumkar
West
20 fits wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking30 units

17 of 30 units booked (57%), as the promoter reported to MahaRERA

2BHK · 14 units3BHK · 12 unitsOffice space · 2 unitsShop · 2 units
TypeCarpet areaUnitsBooked
2BHK54.79 sq m · 590 sq ft1411
3BHK63.33 sq m · 682 sq ft126
Office space26.95 sq m · 290 sq ft10
Office space60.68 sq m · 653 sq ft10
Shop113.4 sq m · 1,221 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKimaya Associates Mr Manik Buchade—
Chartered accountantPravin Pise & Associates—
Chartered accountantVaibhav Bhise—
EngineerDhananjay Deshmukh—
EngineerVishwajeet Bhegade—

Source: MahaRERA project page. Contact details are not shown.