Residential / Group Housing · 4 buildings · 193 unitsRERA PR1260002501760

The Embercrest

Deedo IDDP-PUN-HW93

Completion was pushed back 4 months, to Apr 2032; no MahaRERA orders on record; 26% of its units are booked.

Wakad, Pune 411057 · Property rates in Wakad · by Chandrarang Developer & Builders Pvt. Ltd

DeliveryExtended 4 moPromised Dec 2031 · now due Apr 2032RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales26% booked50 of 193 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2032

  • This projectRegistered 12 Dec 2025, completion promised 31 Dec 2031, revised to 30 Apr 2032.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1260002501760
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR126000250176012 Dec 202531 Dec 203130 Apr 2032Chandrarang Developer and Builders Pvt LtdProject page
Documents100

2 documents held by Deedo, 98 filings listed on MahaRERA's project page

Registration certificate (2)

Finance

  • PAN CardCDBPL_PAN Card.pdf · uploaded 31 Oct 2025Source
  • Othersilovepdf_merged (60).pdf · uploaded 1 Dec 2025Source
  • Others6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-2.pdf · uploaded 1 Dec 2025Source
  • OthersDeclaration- Finance.pdf · uploaded 5 Dec 2025Source

Legal

  • Declaration Form BRERA TITLE- 251 and 253 WAKAD_compressed.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-1-15.pdf · uploaded 28 Oct 2025Source
Show all 100 documentsShow fewer documents

Legal

  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-16-30.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-31-46.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-47-58-1-6.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-47-58-7-12.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-59-71-1-7.pdf · uploaded 28 Oct 2025Source
  • Declaration Form B6 Sale Deed 251-1A-1 - OSC-CDBPL 7924-2020 - 35 R_compressed-59-71-8-13.pdf · uploaded 28 Oct 2025Source
  • OthersAnexture - A ALJ (1).pdf · uploaded 31 Oct 2025Source
  • OthersJayashree Jagtap.pdf · uploaded 31 Oct 2025Source
  • OthersVijay Jagtap.pdf · uploaded 31 Oct 2025Source
  • OthersShubhangi S Jagtap.pdf · uploaded 31 Oct 2025Source
  • Declaration Form BForm B Declaration (1).pdf · uploaded 31 Oct 2025Source
  • Declaration Form B7-12 Extract, 251 Wakad.pdf · uploaded 31 Oct 2025Source
  • Declaration Form BShankar Sir Resignation Board Resolution.pdf · uploaded 31 Oct 2025Source
  • OthersEmail SS-Embercrest.pdf · uploaded 1 Dec 2025Source

Migrated

  • Withdrawal Update Form 1form 1_compressed.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3form 3_compressed (5).pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 17 Apr 2026Source
  • Withdrawal Update Form 2CDBPL-The Embercrest FORM 2 Q4 (1).pdf · uploaded 17 Apr 2026Source
  • Withdrawal Update Form 3CDBPL-The Embercrest FORM 3 Q4.pdf · uploaded 17 Apr 2026Source
  • Withdrawal Update Form 1form 1_11zon.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 3form 3_11zon (1).pdf · uploaded 10 Jul 2026Source
  • Form 2A (FY 2025-2026)FORM 2A.pdf · uploaded 11 Jul 2026Source
  • Form 5 (FY 2025-2026)embercrest final.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentHPSC0450.pdf · uploaded 30 Oct 2025Source
  • DocumentHPSC0451.pdf · uploaded 30 Oct 2025Source
  • DocumentNew Doc 10-07-2025 (1).pdf · uploaded 30 Oct 2025Source
  • DocumentHPSC0452.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0454.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0455.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0456.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0457.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0458.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0459.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0460.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0461.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0462.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0463.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0446_compressed.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0453_compressed.pdf · uploaded 31 Oct 2025Source
  • DocumentHPSC0466_compressed.pdf · uploaded 31 Oct 2025Source
  • OthersAnexture - A ALJ (1).pdf · uploaded 31 Oct 2025Source
  • OthersVijay Jagtap.pdf · uploaded 31 Oct 2025Source
  • OthersJayashree Jagtap.pdf · uploaded 31 Oct 2025Source
  • OthersShubhangi S Jagtap.pdf · uploaded 31 Oct 2025Source
  • OthersEmail-Embarcrast.pdf · uploaded 21 Nov 2025Source
  • Documentcommencement.pdf · uploaded 17 Apr 2026Source
  • Documentscan (1).pdf · uploaded 17 Apr 2026Source
  • Documentscan (2) (1).pdf · uploaded 17 Apr 2026Source
  • Documentscan (3).pdf · uploaded 17 Apr 2026Source
  • Documentscan (4).pdf · uploaded 17 Apr 2026Source
  • Documentscan (5).pdf · uploaded 17 Apr 2026Source
  • Documentscan (6).pdf · uploaded 17 Apr 2026Source
  • Documentscan (7).pdf · uploaded 17 Apr 2026Source
  • Documentscan (8).pdf · uploaded 17 Apr 2026Source
  • Documentscan (9).pdf · uploaded 17 Apr 2026Source
  • Documentscan (10).pdf · uploaded 17 Apr 2026Source
  • Documentscan (11).pdf · uploaded 17 Apr 2026Source
  • Documentscan (12).pdf · uploaded 17 Apr 2026Source
  • Documentscan (13).pdf · uploaded 17 Apr 2026Source
  • Documentscan (14).pdf · uploaded 17 Apr 2026Source
  • Documentscan (15).pdf · uploaded 17 Apr 2026Source
  • Documentscan (16).pdf · uploaded 17 Apr 2026Source
  • Documentscan (17).pdf · uploaded 17 Apr 2026Source
  • Documentscan (18).pdf · uploaded 17 Apr 2026Source
  • Documentscan (19).pdf · uploaded 17 Apr 2026Source
  • Documentscan (20).pdf · uploaded 17 Apr 2026Source
  • Documentscan (21).pdf · uploaded 17 Apr 2026Source
  • DocumentWAKAD 251 - 01 LAYOUT.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - 02 LAYOUT_11zon.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - 03 LAYOUT_11zon.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - 04 LAYOUT.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - A WING 05.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 06.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 07.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 08.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 09.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 10.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 11.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 13.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - B WING 12.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 14.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 15.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 16.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 17.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - C WING 18.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - D WING 19.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - D WING 21.pdf · uploaded 7 Aug 2026Source
  • DocumentWAKAD 251 - D WING 20.pdf · uploaded 7 Aug 2026Source

Technical (Architect)

  • Documentform 1_11zon.pdf · uploaded 10 Jul 2026Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 10 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1B, 1C

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—193 units in all
Address
WakadPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
13,050 sq m (1,40,470 sq ft)
Permissible built-up area
30,393 sq m (3,27,147 sq ft)
Sanctioned built-up area
30,393 sq m (3,27,147 sq ft)
Recreational open space
1,489 sq m (16,024 sq ft)
Designated bank account
220
Developed in phases
Yes

Survey, CTS, gat or plot numbers

1B1C253/4 CTS No 948949950Sr No 251/1A

Land as published on MahaRERA's project page

Sr No 251/1A, 1B, 1C, 253/4 CTS No 948, 949, 950

Boundaries

North
By land owned by Namdeo Kaspate
South
By land owned by Nathu Kaspate and 24 M Wide Road
East
By part of Sr no 251/1A
West
By land owned by Jaywant D Kaspate

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking193 units

193 units registered

— · 193 units
BuildingTypeCarpet areaUnits
B Building——44
C Building——82
D Building (with Mhada)——67

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVikas Achalkar—
Chartered accountantSumeet Kate—
EngineerAvinash Gaikwad—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Wakad

All 314 projects in Wakad · Compare The Embercrest with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology