Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 69% of its units are booked.

Wakad, Pune 411057 · by Shiv Developers

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales69% booked147 of 213 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 26 Feb 2020, completion promised 29 Dec 2027, revised to 29 Apr 2028.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100024649
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002464926 Feb 202029 Dec 202729 Apr 2028Shiv DevelopersProject page
Documents303

2 documents held by Deedo, 301 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN Cardcompany pan.pdf · uploaded 6 Dec 2019Source
  • Other – FinanceSBI Realse Deed pdf.pdf · uploaded 5 Mar 2025Source

Legal

  • Legal Title reportsearch title_compressed-1-10.pdf · uploaded 6 Dec 2019Source
  • Legal Title reportsearch title_compressed-11-20.pdf · uploaded 6 Dec 2019Source
  • Legal Title reportsearch title_compressed-21-27.pdf · uploaded 6 Dec 2019Source
  • Legal Title reportilovepdf_merged.pdf · uploaded 14 Feb 2020Source
Show all 303 documentsShow fewer documents

Legal

  • Legal Title reportilovepdf_merged (1).pdf · uploaded 14 Feb 2020Source
  • Declaration Form BFORM B PARK 59.pdf · uploaded 17 Feb 2020Source
  • Declaration Form BFORM B REVISED.pdf · uploaded 10 Dec 2020Source
  • Declaration Form Blegal title Report - Park 59.pdf · uploaded 14 Apr 2026Source

Migrated

  • 1 PAN Cardcompany pan.pdf · uploaded 6 Dec 2019Source
  • 1 Copy of the legal title reportsearch title_compressed-1-10.pdf · uploaded 6 Dec 2019Source
  • 2 Copy of the legal title reportsearch title_compressed-11-20.pdf · uploaded 6 Dec 2019Source
  • 3 Copy of the legal title reportsearch title_compressed-21-27.pdf · uploaded 6 Dec 2019Source
  • 4 Copy of the legal title reportilovepdf_merged.pdf · uploaded 14 Feb 2020Source
  • 5 Copy of the legal title reportilovepdf_merged (1).pdf · uploaded 14 Feb 2020Source
  • 1 Details of encumbrancesENCUMBRAMCES PARK 59.pdf · uploaded 14 Feb 2020Source
  • 1 Copy of Layout Approval (in case of layout)02.pdf · uploaded 14 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted development02.pdf · uploaded 14 Feb 2020Source
  • 2 Building Plan Approval / NA Order for plotted development02.pdf · uploaded 14 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMICEMENT PARK 59.pdf · uploaded 14 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 AR CER 14-02-20_compressed.pdf · uploaded 14 Feb 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2A SITE ENGG_compressed.pdf · uploaded 14 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA CERTIFICATE_compressed.pdf · uploaded 14 Feb 2020Source
  • 1 Proforma of Allotment letterAgreement to sale park 59.pdf · uploaded 14 Feb 2020Source
  • 1 Declaration in FORM BFORM B PARK 59.pdf · uploaded 17 Feb 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PARK 59 15 FEB 20.pdf · uploaded 17 Feb 2020Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER OF PARK 59.pdf · uploaded 17 Feb 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR form 1 30 06 2020 compressed.pdf · uploaded 24 Sep 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PARK 59 30 06 2020.pdf · uploaded 24 Sep 2020Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Rera compressed.pdf · uploaded 24 Sep 2020Source
  • 2 Declaration in FORM BFORM B REVISED.pdf · uploaded 10 Dec 2020Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Scan Dec 05, 2020_compressed.pdf · uploaded 11 Dec 2020Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 11 Dec 2020Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate (1)_compressed.pdf · uploaded 11 Dec 2020Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)PARK 59 DEC 2020 FORM 1.pdf · uploaded 9 Feb 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2PARK 59 DEC 20.pdf · uploaded 9 Feb 2021Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed (1).pdf · uploaded 9 Feb 2021Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA MARCH FINAL_compressed (1).pdf · uploaded 17 May 2021Source
  • 2 Copy of Layout Approval (in case of layout)Layout plan (1).pdf · uploaded 18 May 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentNEW COMMENCEMENT.pdf · uploaded 18 May 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Revised Form 1_compressed.pdf · uploaded 18 May 2021Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 compressed.pdf · uploaded 18 May 2021Source
  • 1 Declaration about Commencement CertificateDeclaration.pdf · uploaded 28 Jun 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2A SITE ENGG_compressed.pdf · uploaded 13 Jul 2021Source
  • 1 Disclosure of sold/ booked inventorysold-unsold.pdf · uploaded 13 Jul 2021Source
  • 2 Declaration about Commencement CertificateDeclaration new.pdf · uploaded 16 Jul 2021Source
  • 2 Details of encumbrancesEncumbrance certificate.pdf · uploaded 4 Oct 2021Source
  • 3 Details of encumbrancesNew Encumberance certificate.pdf · uploaded 12 Oct 2021Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed.pdf · uploaded 13 Dec 2021Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_compressed.pdf · uploaded 13 Dec 2021Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A certificate_compressed.pdf · uploaded 13 Dec 2021Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)shiv devloper new form 1 compressed.pdf · uploaded 8 Apr 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Park 59.pdf · uploaded 8 Apr 2022Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed (2).pdf · uploaded 4 May 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Park 59 30-06-2022_compressed.pdf · uploaded 15 Jul 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Park 59 _compressed.pdf · uploaded 15 Jul 2022Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed.pdf · uploaded 15 Jul 2022Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera updated Certificate-09-12-2022 (2).pdf · uploaded 4 Jan 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Park 59.pdf · uploaded 4 Jan 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)rera certificate shiv.pdf · uploaded 4 Jan 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentscan0141_compressed.pdf · uploaded 20 Jan 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentscan0142_compressed.pdf · uploaded 20 Jan 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentscan0143_compressed.pdf · uploaded 20 Jan 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentscan0144_compressed.pdf · uploaded 20 Jan 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 20 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)F 5-2021-22.pdf · uploaded 6 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20-21.pdf · uploaded 13 Feb 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold RERA compressed.pdf · uploaded 18 Feb 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Apr 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA CA CERTIFICATE.pdf · uploaded 24 May 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECTURE CERTIFICATE park 59.pdf · uploaded 19 Jun 2023Source
  • 3 Disclosure of sold/ booked inventorySOLD UNSOLD DETAILS (1)_compressed.pdf · uploaded 19 Jun 2023Source
  • 1 Proforma of Agreement for saleRevise Customer Agreement.pdf · uploaded 19 Jun 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Park 59 F2_compressed (1).pdf · uploaded 20 Jun 2023Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final_compressed.pdf · uploaded 21 Jul 2023Source
  • 3 Copy of Layout Approval (in case of layout)HPSC0524 (1).pdf · uploaded 1 Sep 2023Source
  • 4 Copy of Layout Approval (in case of layout)HPSC0524.pdf · uploaded 1 Sep 2023Source
  • 5 Copy of Layout Approval (in case of layout)59 layout 1.pdf · uploaded 1 Sep 2023Source
  • 6 Copy of Layout Approval (in case of layout)59 layout.pdf · uploaded 1 Sep 2023Source
  • 3 Declaration about Commencement Certificate20230830061644.pdf · uploaded 1 Sep 2023Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD DETAIL.pdf · uploaded 30 Sep 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Oct 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Park 59.pdf · uploaded 6 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)GetUserDocumentFileContent (6) (1) (1).pdf · uploaded 11 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)GetUserDocumentFileContent (6) (1).pdf · uploaded 11 Oct 2023Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE RERA.pdf · uploaded 13 Oct 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentplinth inwd A,B,C,D bldg (1) Sep Quarter (2).pdf · uploaded 17 Oct 2023Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 P59.pdf · uploaded 20 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form No 5.pdf · uploaded 20 Oct 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 7 Dec 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2.pdf · uploaded 7 Dec 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)park 59 Engineer Certificate.pdf · uploaded 7 Dec 2023Source
  • 5 Disclosure of sold/ booked inventorySold unsold.pdf · uploaded 9 Dec 2023Source
  • 7 Copy of Layout Approval (in case of layout)HPSC0187.pdf · uploaded 29 Mar 2024Source
  • 8 Copy of Layout Approval (in case of layout)HPSC0187.pdf · uploaded 29 Mar 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentHPSC0188.pdf · uploaded 29 Mar 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentHPSC0189.pdf · uploaded 29 Mar 2024Source
  • 9 Building Plan Approval / NA Order for plotted developmentHPSC0190.pdf · uploaded 29 Mar 2024Source
  • 10 Building Plan Approval / NA Order for plotted developmentHPSC0191.pdf · uploaded 29 Mar 2024Source
  • 11 Building Plan Approval / NA Order for plotted developmentHPSC0192.pdf · uploaded 29 Mar 2024Source
  • 12 Building Plan Approval / NA Order for plotted developmentHPSC0193.pdf · uploaded 29 Mar 2024Source
  • 13 Building Plan Approval / NA Order for plotted developmentHPSC0194.pdf · uploaded 29 Mar 2024Source
  • 14 Building Plan Approval / NA Order for plotted developmentHPSC0195 (1).pdf · uploaded 29 Mar 2024Source
  • 15 Building Plan Approval / NA Order for plotted developmentHPSC0196.pdf · uploaded 29 Mar 2024Source
  • 16 Building Plan Approval / NA Order for plotted developmentHPSC0197.pdf · uploaded 29 Mar 2024Source
  • 17 Building Plan Approval / NA Order for plotted developmentHPSC0198.pdf · uploaded 29 Mar 2024Source
  • 18 Building Plan Approval / NA Order for plotted developmentHPSC0199.pdf · uploaded 29 Mar 2024Source
  • 19 Building Plan Approval / NA Order for plotted developmentHPSC0201.pdf · uploaded 29 Mar 2024Source
  • 20 Building Plan Approval / NA Order for plotted developmentHPSC0202.pdf · uploaded 29 Mar 2024Source
  • 21 Building Plan Approval / NA Order for plotted developmentHPSC0203.pdf · uploaded 29 Mar 2024Source
  • 22 Building Plan Approval / NA Order for plotted developmentHPSC0204.pdf · uploaded 29 Mar 2024Source
  • 23 Building Plan Approval / NA Order for plotted developmentHPSC0205.pdf · uploaded 29 Mar 2024Source
  • 5 Commencement Certificates / NA Order for plotted developmentSsekar24032612580.pdf · uploaded 29 Mar 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Update Certificate-05-12-2023 (1).pdf · uploaded 29 Mar 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 29 Mar 2024Source
  • 6 Disclosure of sold/ booked inventorymarch 2024.pdf · uploaded 23 Apr 2024Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)SOLD Unsold updated 24 04 2024.pdf · uploaded 24 Apr 2024Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 (5).pdf · uploaded 3 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 23 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Update Certificate-21-06-2024 - Copy.pdf · uploaded 25 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 25 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM No 3_11zon.pdf · uploaded 25 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sep Quarter RERA_11zon.pdf · uploaded 25 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Park 59 June form 2 (1).pdf · uploaded 25 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Park 59 form 2.pdf · uploaded 25 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 22 Jan 2025Source
  • 1 Other – FinanceSBI Realse Deed pdf.pdf · uploaded 5 Mar 2025Source
  • Form 1F1.pdf · uploaded 30 Jul 2025Source
  • Form 1F1.pdf · uploaded 30 Jul 2025Source
  • Form 1F1.pdf · uploaded 30 Jul 2025Source
  • Form 1F1.pdf · uploaded 30 Jul 2025Source
  • Form 1F1.pdf · uploaded 30 Jul 2025Source
  • Form 2F2.pdf · uploaded 30 Jul 2025Source
  • Form 2F2.pdf · uploaded 30 Jul 2025Source
  • Form 2F2.pdf · uploaded 30 Jul 2025Source
  • Form 2F2.pdf · uploaded 30 Jul 2025Source
  • Form 2F2.pdf · uploaded 30 Jul 2025Source
  • Form 3F3.pdf · uploaded 30 Jul 2025Source
  • Form 3F3.pdf · uploaded 30 Jul 2025Source
  • Form 3F3.pdf · uploaded 30 Jul 2025Source
  • Form 3F3.pdf · uploaded 30 Jul 2025Source
  • Form 3F3.pdf · uploaded 30 Jul 2025Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 30 Jul 2025Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 30 Jul 2025Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 30 Jul 2025Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 30 Jul 2025Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 30 Jul 2025Source
  • Form 1Form 1.pdf · uploaded 28 Oct 2025Source
  • Form 1Form 1.pdf · uploaded 28 Oct 2025Source
  • Form 1Form 1.pdf · uploaded 28 Oct 2025Source
  • Form 2Form 2.pdf · uploaded 28 Oct 2025Source
  • Form 2Form 2.pdf · uploaded 28 Oct 2025Source
  • Form 2Form 2.pdf · uploaded 28 Oct 2025Source
  • Form 3form 3.pdf · uploaded 28 Oct 2025Source
  • Form 3form 3.pdf · uploaded 28 Oct 2025Source
  • Form 3form 3.pdf · uploaded 28 Oct 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUNE 2020.pdf · uploaded 28 Oct 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUNE 2020.pdf · uploaded 28 Oct 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUNE 2020.pdf · uploaded 28 Oct 2025Source
  • Form 1Form 1 s.pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1.pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (1).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1.pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (1).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (2).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (3).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (1).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (3).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (3).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 (3).pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1.pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1 s.pdf · uploaded 12 Nov 2025Source
  • Form 1FORM 1 S.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2FORM 2PARK 59 DEC 20.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2park 59 june 21 Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Park 59 sep 21 Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Park 59 March 23 Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2park 59 March 25 Form 2.pdf · uploaded 12 Nov 2025Source
  • Form 2Park 59 Form 2 (1).pdf · uploaded 12 Nov 2025Source
  • Form 3form 3 (s.pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3.pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (1).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (1).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (2)_compressed (2).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3.pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (42).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (2).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (3).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3 (3).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3_compressed (18).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3_compressed (19).pdf · uploaded 12 Nov 2025Source
  • Form 3Form 3.pdf · uploaded 12 Nov 2025Source
  • Form 3FORM 3 s_compressed (3).pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold And Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold And Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD DEC 21.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD MARCH 22.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUNE 22.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD SEPT 22.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold And Unsold.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold unsold sep 2024.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD & UNSOLD UP TO MARCH 2025.pdf · uploaded 12 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD JUNE 25.pdf · uploaded 12 Nov 2025Source
  • Form 1Form 1.pdf · uploaded 30 Dec 2025Source
  • Form 2park 59 sep 25.pdf · uploaded 30 Dec 2025Source
  • Form 3Form 3_compressed (27).pdf · uploaded 30 Dec 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold_compressed (4).pdf · uploaded 30 Dec 2025Source
  • Form 1FORM 1 WITH SIGN.pdf · uploaded 4 Feb 2026Source
  • Form 2FORM 2 WITH SIGN.pdf · uploaded 4 Feb 2026Source
  • Form 3FORM 3 WITH SIGN_compressed.pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD_compressed (6).pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 1Form1.pdf · uploaded 2 Mar 2026Source
  • Withdrawal Update Form 2Form2 (5).pdf · uploaded 2 Mar 2026Source
  • Withdrawal Update Form 3FORM 3_SHIV DEVELOPER_FINAL (1) (1)_compressed.pdf · uploaded 2 Mar 2026Source
  • Form 1Rera Update Certificate-21-06-2024 - Copy.pdf · uploaded 6 Mar 2026Source
  • Form 1F1.pdf · uploaded 6 Mar 2026Source
  • Form 2Form 2.pdf · uploaded 6 Mar 2026Source
  • Form 2F2.pdf · uploaded 6 Mar 2026Source
  • Form 3FORM 3.pdf · uploaded 6 Mar 2026Source
  • Form 3F3.pdf · uploaded 6 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold And Unsold.pdf · uploaded 6 Mar 2026Source
  • Disclosure of Sold and Booked InventorySU.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2019-2020)park 59 form 2A 19-20.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2020-2021)park 59 form 2A 20-21.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2021-2022)park 49 from 2A 21-22.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2022-2023)Park form 59 form 2A 22-23.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2023-2024)park 59 from 2A 23-24.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2024-2025)park 59 form 2A 24-25.pdf · uploaded 6 Mar 2026Source
  • Form 2A (FY 2025-2026)park 59 form 2A 25-26.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2020-2021)form 5 2020-21_compressed.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2021-2022)form 5 2021-22_compressed.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2022-2023)form 5 2022-23_compressed.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2023-2024)form 5 2023-24_compressed.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2024-2025)form 5 2024-25_compressed.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 1Updated formate form1 with sign ss.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 2form 2 with sign.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 3System Generated FORM 3 s_compressed.pdf · uploaded 8 May 2026Source
  • Withdrawal Update Form 1Form 1 dt.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2form 2 (14).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3SIGNED FORM 3 (1).pdf · uploaded 20 Jul 2026Source

Technical

  • Document02.pdf · uploaded 14 Feb 2020Source
  • Document02.pdf · uploaded 14 Feb 2020Source
  • Document02.pdf · uploaded 14 Feb 2020Source
  • DocumentLayout plan (1).pdf · uploaded 18 May 2021Source
  • Documentscan0141_compressed.pdf · uploaded 20 Jan 2023Source
  • Documentscan0142_compressed.pdf · uploaded 20 Jan 2023Source
  • Documentscan0143_compressed.pdf · uploaded 20 Jan 2023Source
  • Documentscan0144_compressed.pdf · uploaded 20 Jan 2023Source
  • DocumentHPSC0524 (1).pdf · uploaded 1 Sep 2023Source
  • DocumentHPSC0524.pdf · uploaded 1 Sep 2023Source
  • Document59 layout 1.pdf · uploaded 1 Sep 2023Source
  • Document59 layout.pdf · uploaded 1 Sep 2023Source
  • DocumentHPSC0187.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0187.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0188.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0189.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0190.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0191.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0192.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0193.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0194.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0195 (1).pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0196.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0197.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0198.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0199.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0201.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0202.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0203.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0204.pdf · uploaded 29 Mar 2024Source
  • DocumentHPSC0205.pdf · uploaded 29 Mar 2024Source
  • DocumentP2.pdf · uploaded 5 Mar 2026Source
  • DocumentP3.pdf · uploaded 5 Mar 2026Source
  • DocumentP4.pdf · uploaded 5 Mar 2026Source
  • DocumentP5.pdf · uploaded 5 Mar 2026Source
  • DocumentP6.pdf · uploaded 5 Mar 2026Source
  • DocumentP7.pdf · uploaded 5 Mar 2026Source
  • DocumentP8.pdf · uploaded 5 Mar 2026Source
  • DocumentP17.pdf · uploaded 5 Mar 2026Source
  • DocumentP18.pdf · uploaded 5 Mar 2026Source
  • Document2a57e144-7675-4027-b7fa-d857be2b460f 1.pdf · uploaded 6 Mar 2026Source
  • Documentb944d444-ad46-4d04-b052-5f90df7944e11.pdf · uploaded 6 Mar 2026Source

Technical (Architect)

  • DocumentRera Update Certificate-21-06-2024 - Copy.pdf · uploaded 25 Nov 2024Source
  • DocumentArchitect Certificate.pdf · uploaded 25 Nov 2024Source
  • DocumentForm 1 dt.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentPark 59 June form 2 (1).pdf · uploaded 25 Nov 2024Source
  • DocumentPark 59 form 2.pdf · uploaded 25 Nov 2024Source
  • Documentform 2 (14).pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK213 units in all
Address
259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947, Survey No 259/4 (P) Wakad Kaspate Road Near Aishvaryam Green Society, WakadPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
5,800 sq m (62,431 sq ft)
Permissible built-up area
23,279 sq m (2,50,567 sq ft)
Sanctioned built-up area
23,235 sq m (2,50,103 sq ft)
Recreational open space
654 sq m (7,042 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947

Land as published on MahaRERA's project page

259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947

Boundaries

North
By Cts No 2705
South
By Cts No 1904
East
By 45m Wide Road
West
By Cts No 1904

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking213 units

147 of 213 units booked (69%), as the promoter reported to MahaRERA

2BHK · 156 units3BHK · 57 units
BuildingTypeCarpet areaUnitsBooked
A Building2BHK56.75 sq m · 611 sq ft10
A Building2BHK58.38 sq m · 628 sq ft2212
A Building2BHK59.3 sq m · 638 sq ft10
A Building3BHK67.02 sq m · 721 sq ft10
A Building3BHK82.15 sq m · 884 sq ft10
A Building3BHK82.3 sq m · 886 sq ft11
A Building3BHK84.76 sq m · 912 sq ft217
B Building2BHK58.38 sq m · 628 sq ft218
Show all 22 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Building2BHK59.31 sq m · 638 sq ft10
B Building2BHK67.02 sq m · 721 sq ft10
B Building3BHK84.03 sq m · 904 sq ft11
B Building3BHK84.49 sq m · 909 sq ft11
B Building3BHK84.76 sq m · 912 sq ft228
C Building2BHK55.18 sq m · 594 sq ft6666
C Building3BHK73.23 sq m · 788 sq ft10
D Building2BHK75.47 sq m · 812 sq ft4343
E Building3BHK59.91 sq m · 645 sq ft10
E Building3BHK87.61 sq m · 943 sq ft10
E Building3BHK88.53 sq m · 953 sq ft10
E Building3BHK89.19 sq m · 960 sq ft30
E Building3BHK91.05 sq m · 980 sq ft10
E Building3BHK92.35 sq m · 994 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShankar Nimbalkar—
Chartered accountantAnita Laxman Limaye—
Chartered accountantMahesh Malhotra—
Chartered accountantRohit Jadhav—
EngineerGanesh Katke—
EngineerK P Badgujar Consultant Pvt Ltd—
EngineerRohinee Badgujar—
OtherSuda Infrastructures Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology