Shiv Developers

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shiv Samrudhi - A WingP52100014369WakadCertificate Signed30 Dec 201929 Dec 2021+24 mo
Shiv Darshan - B WingP52100014413WakadCertificate Signed30 Jun 201830 Jun 2018On date
Park59P52100024649WakadCertificate Signed29 Dec 202729 Apr 2028+4 mo
Shiv MalharP52100052401WakadCertificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology