Company or firm · first RERA registration 2017
Shiv Developers
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shiv Samrudhi - A WingP52100014369 | Wakad | Certificate Signed | 30 Dec 2019 | 29 Dec 2021 | +24 mo |
| Shiv Darshan - B WingP52100014413 | Wakad | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Park59P52100024649 | Wakad | Certificate Signed | 29 Dec 2027 | 29 Apr 2028 | +4 mo |
| Shiv MalharP52100052401 | Wakad | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology