Opus 76
Deedo IDDP-PUN-FPJPIts promised completion date, Oct 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 52% of its units are booked.
Wakad, Pune 411057 · Property rates in Wakad · by Om Sai Properties
Buying a flat here?
See every deed registered on it.
Its promised completion date, Oct 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 9 Oct 2019, completion promised 15 Oct 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
11 buildings
Open a building to see every flat, floor by floor.
- A Building15 floors · 71 units72% booked
- A WingSize not on record
- AWingSize not on record100% booked
- B Building15 floors · 71 units13% booked
- Building (P52100022594)Size not on record100% booked
- BWingSize not on record100% booked
- C Building15 floors · 103 units83% booked
- CWingSize not on record100% booked
- D Mhada Building11 floors · 35 units0% booked
- OWingSize not on record100% booked
- SWingSize not on record100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100022594
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100022594 | 9 Oct 2019 | 15 Oct 2024 | 15 Oct 2024 | Om Sai Properties | Project page |
Documents119
2 documents held by Deedo, 117 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardCOMPANY PAN opus 76.pdf · uploaded 2 Oct 2019Source
Legal
- Legal Title reportsearch title report.pdf · uploaded 2 Oct 2019Source
- Declaration Form Bform B.pdf · uploaded 2 Oct 2019Source
- Legal Title reportOSP_POA_compressed-1-12.pdf · uploaded 11 Dec 2020Source
- Legal Title reportOSP_POA_compressed-13-25.pdf · uploaded 11 Dec 2020Source
- Legal Title reportOSP_Kararnama_compressed-1-25-1-12.pdf · uploaded 11 Dec 2020Source
Show all 119 documentsShow fewer documents
Legal
- Legal Title reportOSP_Kararnama_compressed-1-25-13-25.pdf · uploaded 11 Dec 2020Source
- Legal Title reportOSP_Kararnama_compressed-26-35.pdf · uploaded 11 Dec 2020Source
- Legal Title reportSearch title 1-7.pdf · uploaded 16 Dec 2020Source
- Legal Title reportSearch title 8-14.pdf · uploaded 16 Dec 2020Source
- Legal Title reportscan0001483_compressed (1).pdf · uploaded 3 Jul 2021Source
- Legal Title reportsearch title opus76 1.pdf · uploaded 16 Jul 2021Source
- Legal Title reportsearch title opus76 2.pdf · uploaded 16 Jul 2021Source
Migrated
- 1 PAN CardCOMPANY PAN opus 76.pdf · uploaded 2 Oct 2019Source
- 1 Copy of the legal title reportsearch title report.pdf · uploaded 2 Oct 2019Source
- 1 Details of encumbrancesencumbrance certificate.pdf · uploaded 2 Oct 2019Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 2 Oct 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentIOD.pdf · uploaded 2 Oct 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 2 Oct 2019Source
- 1 Declaration in FORM Bform B.pdf · uploaded 2 Oct 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 2 Oct 2019Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 opus 76.pdf · uploaded 2 Oct 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A)Form 2A.pdf · uploaded 2 Oct 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 2 Oct 2019Source
- 1 Proforma of Allotment letterAgreement draft.pdf · uploaded 2 Oct 2019Source
- 2 Proforma of Allotment letterAllotment-Draft.pdf · uploaded 2 Oct 2019Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 29 Feb 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate_compressed.pdf · uploaded 29 Feb 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate.pdf · uploaded 29 Feb 2020Source
- 2 Copy of the legal title reportOSP_POA_compressed-1-12.pdf · uploaded 11 Dec 2020Source
- 3 Copy of the legal title reportOSP_POA_compressed-13-25.pdf · uploaded 11 Dec 2020Source
- 4 Copy of the legal title reportOSP_Kararnama_compressed-1-25-1-12.pdf · uploaded 11 Dec 2020Source
- 5 Copy of the legal title reportOSP_Kararnama_compressed-1-25-13-25.pdf · uploaded 11 Dec 2020Source
- 6 Copy of the legal title reportOSP_Kararnama_compressed-26-35.pdf · uploaded 11 Dec 2020Source
- 7 Copy of the legal title reportSearch title 1-7.pdf · uploaded 16 Dec 2020Source
- 8 Copy of the legal title reportSearch title 8-14.pdf · uploaded 16 Dec 2020Source
- 3 Proforma of Allotment letterAGREEMENT-oppus 76 Agreement Draft 14-12-2020 (1).pdf · uploaded 16 Dec 2020Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR CERTIFICATE -corrected.pdf · uploaded 19 Dec 2020Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR CERTIFICATE -corrected.pdf · uploaded 19 Dec 2020Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)opus july form 2.pdf · uploaded 19 Dec 2020Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)opus sep form 2.pdf · uploaded 19 Dec 2020Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)27 july_compressed.pdf · uploaded 13 Jan 2021Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)21 sep_compressed.pdf · uploaded 13 Jan 2021Source
- 9 Copy of the legal title reportscan0001483_compressed (1).pdf · uploaded 3 Jul 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentscan0001486_compressed.pdf · uploaded 3 Jul 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 3 Jul 2021Source
- 1 Declaration about Commencement Certificatecommencment.pdf · uploaded 3 Jul 2021Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR CERTIFICATE.pdf · uploaded 3 Jul 2021Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 3 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 3 Jul 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 3 Jul 2021Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD_compressed.pdf · uploaded 5 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)OSP - OPUS 76 - RERA Form 5 - FY 2019-20.pdf · uploaded 13 Jul 2021Source
- 10 Copy of the legal title reportsearch title opus76 1.pdf · uploaded 16 Jul 2021Source
- 11 Copy of the legal title reportsearch title opus76 2.pdf · uploaded 16 Jul 2021Source
- 4 Proforma of Allotment letterOpus76 revised draft.pdf · uploaded 16 Jul 2021Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 9 Apr 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_compressed.pdf · uploaded 9 Apr 2022Source
- 5 Proforma of Allotment letteropus76 mhada draft.pdf · uploaded 26 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)OSP_OPUS 76_RERA _Form 5_FY 2020-21_signed.pdf · uploaded 13 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)OSP_OPUS 76_RERA_Form 5_FY 2021-22_signed.pdf · uploaded 13 Feb 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)2-Form 2.pdf · uploaded 18 Feb 2023Source
- 2 Disclosure of sold/ booked inventory4-sold_compressed.pdf · uploaded 20 Feb 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)3-form 3_compressed.pdf · uploaded 20 Feb 2023Source
- 3 Disclosure of sold/ booked inventoryOpus 76 Sold Unsold Inventory.pdf · uploaded 17 Jul 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture Certificate Opus 76 March 24.pdf · uploaded 24 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Opus 76.pdf · uploaded 24 Jan 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Letter for December 2023.pdf · uploaded 24 Jan 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Letter for Month september 2023.pdf · uploaded 24 Jan 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Letter for Month June 2023.pdf · uploaded 24 Jan 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera letter for march 2023.pdf · uploaded 24 Jan 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)1-Form 1_compressed (1).pdf · uploaded 24 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Letter for Month september 2023.pdf · uploaded 24 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Opus 76.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Opus 76.pdf · uploaded 24 Jan 2025Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)OPUS 76 -SOCIETY REGISTRATION CERTIFICATE.pdf · uploaded 24 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 2019-2020.pdf · uploaded 24 Jan 2025Source
- 15 Disclosure of sold/ booked inventorySold-Unsold Dec 2023.pdf · uploaded 24 Jan 2025View
- 14 Disclosure of sold/ booked inventorySold-Unsold Sept 2023.pdf · uploaded 24 Jan 2025Source
- 13 Disclosure of sold/ booked inventorySold-Unsold June 2023.pdf · uploaded 24 Jan 2025Source
- 12 Disclosure of sold/ booked inventorySold-Unsold March 2023.pdf · uploaded 24 Jan 2025Source
- 11 Disclosure of sold/ booked inventorySold-Unsold Sept 2022.pdf · uploaded 24 Jan 2025Source
- 10 Disclosure of sold/ booked inventorySold-Unsold June 2022.pdf · uploaded 24 Jan 2025Source
- 9 Disclosure of sold/ booked inventorySold-Unsold March 2022.pdf · uploaded 24 Jan 2025Source
- 8 Disclosure of sold/ booked inventorySold-Unsold Dec 2021.pdf · uploaded 24 Jan 2025Source
- 7 Disclosure of sold/ booked inventorySold-Unsold Sept 2021.pdf · uploaded 24 Jan 2025Source
- 6 Disclosure of sold/ booked inventorySold-Unsold March 2021.pdf · uploaded 24 Jan 2025Source
- 5 Disclosure of sold/ booked inventorySold-Unsold Dec 2020.pdf · uploaded 24 Jan 2025Source
- 4 Disclosure of sold/ booked inventorySold-Unsold Sept 2020.pdf · uploaded 24 Jan 2025Source
- 3 Disclosure of sold/ booked inventorySold-Unsold June 2020.pdf · uploaded 24 Jan 2025Source
- 2 Disclosure of sold/ booked inventorySold-Unsold March 2020.pdf · uploaded 24 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold-Unsold Dec 2019.pdf · uploaded 24 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)June 2022.pdf · uploaded 25 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)march 2023.pdf · uploaded 25 Jan 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)June 2023.pdf · uploaded 25 Jan 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)0pus dec 2024.pdf · uploaded 25 Jan 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)sep 2023.pdf · uploaded 25 Jan 2025Source
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 9 Apr 2022Source
- DocumentForm 1- Opus 76.pdf · uploaded 24 Jan 2025Source
- DocumentForm 1- Opus 76.pdf · uploaded 24 Jan 2025Source
- DocumentRera Letter for Month september 2023.pdf · uploaded 24 Jan 2025Source
- Document1-Form 1_compressed (1).pdf · uploaded 24 Jan 2025Source
- DocumentRera letter for march 2023.pdf · uploaded 24 Jan 2025Source
- DocumentRera Letter for Month June 2023.pdf · uploaded 24 Jan 2025Source
- DocumentRera Letter for Month september 2023.pdf · uploaded 24 Jan 2025Source
- DocumentRera Letter for December 2023.pdf · uploaded 24 Jan 2025Source
- DocumentArchitecture Certificate Opus 76 March 24.pdf · uploaded 24 Jan 2025Source
Technical (Engineer)
- Document2-Form 2.pdf · uploaded 18 Feb 2023Source
- DocumentForm 2- Opus 76.pdf · uploaded 24 Jan 2025Source
- DocumentJune 2022.pdf · uploaded 25 Jan 2025Source
- Documentmarch 2023.pdf · uploaded 25 Jan 2025Source
- DocumentJune 2023.pdf · uploaded 25 Jan 2025Source
- Document0pus dec 2024.pdf · uploaded 25 Jan 2025Source
- Documentsep 2023.pdf · uploaded 25 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey no 762
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, Shop280 units in all
- Address
- Survey no 76-2, Bhumkar chowk Vinode wasti, WakadPIN 411057
- Village
- Wakad, Mulshi taluka
- Location
- 18.59999, 73.74134
- Land area for this project
- 10,000 sq m (1,07,639 sq ft)
- Permissible built-up area
- 15,776 sq m (1,69,811 sq ft)
- Sanctioned built-up area
- 15,776 sq m (1,69,811 sq ft)
- Recreational open space
- 1,000 sq m (10,764 sq ft)
- Designated bank account
- 171
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey no 76-2
Boundaries
- North
- By property of Survey no 77 P
- South
- By property of Jael park society
- East
- By property of Survey no 76-1
- West
- By boundary of village Hinjewadi
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking280 units
145 of 280 units booked (52%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Building | 1BHK | 33.02 sq m · 355 sq ft | 24 | 24 |
| A Building | 2BHK | 55.26 sq m · 595 sq ft | 11 | 2 |
| A Building | 2BHK | 55.98 sq m · 603 sq ft | 24 | 20 |
| A Building | 2BHK | 56.2 sq m · 605 sq ft | 12 | 5 |
| B Building | 1BHK | 33.02 sq m · 355 sq ft | 24 | 1 |
| B Building | 2BHK | 55.26 sq m · 595 sq ft | 11 | 2 |
| B Building | 2BHK | 55.98 sq m · 603 sq ft | 24 | 5 |
| B Building | 2BHK | 56.2 sq m · 605 sq ft | 12 | 1 |
Show all 19 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C Building | 2BHK | 53.05 sq m · 571 sq ft | 51 | 50 |
| C Building | 2BHK | 59.54 sq m · 641 sq ft | 26 | 15 |
| C Building | 3BHK | 73.64 sq m · 793 sq ft | 13 | 10 |
| C Building | 3BHK | 75.41 sq m · 812 sq ft | 13 | 10 |
| D Mhada Building | 1BHK | 38.35 sq m · 413 sq ft | 29 | 0 |
| D Mhada Building | Shop | 13.11 sq m · 141 sq ft | 1 | 0 |
| D Mhada Building | Shop | 16.21 sq m · 174 sq ft | 1 | 0 |
| D Mhada Building | Shop | 16.22 sq m · 175 sq ft | 1 | 0 |
| D Mhada Building | Shop | 16.74 sq m · 180 sq ft | 1 | 0 |
| D Mhada Building | Shop | 19.72 sq m · 212 sq ft | 1 | 0 |
| D Mhada Building | Shop | 20.36 sq m · 219 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Vikas Achalkar | — |
| Chartered accountant | CA Sumeet Kate | — |
| Engineer | Mr Kailas Badgujar | — |
| Other | Sachin Jawalkar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Wakad
- Maaisa GenesisRERA PR1260002602651
- PEBBLES BUSINESS BAY IT BuildingRERA PC1260002602561
- Wakad New ProjectRERA PR1260002602193
- Truspace Prima AltioraRERA PR1260002602057
- Arham PalazzoRERA PM1260002602013
- Austin AurusRERA PM1260002601438
- Jaijinendra NilayRERA PM1260002601417
- The Vantage A, B, C & DRERA PR1260002601066
All 314 projects in Wakad · Compare Opus 76 with another project