Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 5% of its units are booked.

Wakad, Pune 411057 · Property rates in Wakad · by M D Constructions

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales5% booked3 of 58 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 31 Dec 2025, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1260002501957
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM126000250195731 Dec 202531 Dec 203030 Apr 2031M D ConstructionsProject page
Documents66

1 document held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Finance

  • OthersEncumbrance to finance.pdf · uploaded 23 Sep 2025Source
  • OthersUndertaking for no charge.pdf · uploaded 23 Sep 2025Source
  • PAN CardM D CONSTRUCTION NEW PAN CARD.pdf · uploaded 6 Nov 2025Source
  • OthersSelf Declaration Regarding no Bank Accounts of Landowners Finance.pdf · uploaded 6 Nov 2025Source
  • OthersDeclaration for No bank account of Landowners- Final upload.pdf · uploaded 26 Nov 2025Source
  • OthersClarification Regarding Query Raised - Brahma Tower Phase II_Final.pdf · uploaded 9 Dec 2025Source

Legal

  • Declaration Form BDA Agreement- Blasaheb Kalate 1.pdf · uploaded 20 Sep 2025Source
Show all 66 documentsShow fewer documents

Legal

  • Declaration Form BDA Agreement- Blasaheb Kalate 2.pdf · uploaded 20 Sep 2025Source
  • Declaration Form BDA Agreement- Blasaheb Kalate 3.pdf · uploaded 20 Sep 2025Source
  • Declaration Form BDA Agreement- Blasaheb Kalate 4.pdf · uploaded 20 Sep 2025Source
  • Declaration Form BDA Agreement- Blasaheb Kalate 5.pdf · uploaded 20 Sep 2025Source
  • Declaration Form BDA Agreement- Blasaheb Kalate 6.pdf · uploaded 20 Sep 2025Source
  • Declaration Form BPOA 2973-2021 Balasaheb Kalate [1-18].pdf · uploaded 20 Sep 2025Source
  • Declaration Form BPOA 2973-2021 Balasaheb Kalate [19-36].pdf · uploaded 20 Sep 2025Source
  • OthersM D Const PARTNERSHEEP DEED D.pdf · uploaded 23 Sep 2025Source
  • Othersवाकड_176#1#2#3_Satbara.pdf · uploaded 23 Sep 2025Source
  • OthersDOI MD Constructions.pdf · uploaded 6 Nov 2025Source
  • Declaration Form BForm-B - promoter final_0001.pdf · uploaded 6 Nov 2025Source
  • OthersEncumbrance concerned to Legal.pdf · uploaded 7 Nov 2025Source
  • OthersDOI Bhimashankar tongale.pdf · uploaded 26 Nov 2025Source
  • OthersDOI Meenakshi Menkudale.pdf · uploaded 26 Nov 2025Source
  • OthersDOI Suvarna Dhurupe.pdf · uploaded 26 Nov 2025Source
  • OthersDOI Vishweshwar Dhurupe.pdf · uploaded 26 Nov 2025Source
  • OthersDOI Shubham Tongale.pdf · uploaded 26 Nov 2025Source
  • OthersDOI Vijaykumar Menkudale.pdf · uploaded 26 Nov 2025Source
  • Othersवाकड_176#1#6#3_Satbara.pdf · uploaded 26 Nov 2025Source
  • Declaration Form BLTR revised.pdf · uploaded 26 Nov 2025Source
  • Declaration Form Bवाकड_176#1#2#3_Satbara.pdf · uploaded 26 Nov 2025Source
  • Declaration Form Bवाकड_176#1#6#3_Satbara.pdf · uploaded 26 Nov 2025Source
  • OthersClarification Regarding Query Raised - Brahma Tower Phase II_Final.pdf · uploaded 9 Dec 2025Source
  • OthersSales Deed Agg1766_11zon.pdf · uploaded 17 Dec 2025Source
  • OthersClarification regarding Promoter Name Signed.pdf · uploaded 18 Dec 2025Source

Migrated

  • Withdrawal Update Form 1Form-1 Reg- Brahma Tower Ph 2.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 3Form 3 Brahma Tower Ph 2 Regisration.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 1Architect certificate 14-May-2026.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 2engg certificate.pdf · uploaded 14 May 2026Source
  • Withdrawal Update Form 3CA certificate 14-May-2026_compressed.pdf · uploaded 14 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A (4) (1).pdf · uploaded 24 Jul 2026Source
  • Form 2A (FY 2026-2027)Form 2A (4) (1).pdf · uploaded 24 Jul 2026Source
  • Form 5 (FY 2025-2026)M D Const Form 5.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 1Architect certificate 14-May-2026 (1).pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 2Form 2 MD.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 3Form 3 MD Constr.pdf · uploaded 29 Jul 2026Source

Technical

  • Document02 Ground Floor.pdf · uploaded 20 Sep 2025Source
  • Document03 First Floor.pdf · uploaded 20 Sep 2025Source
  • Document04 Second Floor.pdf · uploaded 20 Sep 2025Source
  • Document05 Third Floor.pdf · uploaded 20 Sep 2025Source
  • Document06 Fourth to Sixth.pdf · uploaded 20 Sep 2025Source
  • Document07 Parking Floor Plan.pdf · uploaded 20 Sep 2025Source
  • Document08 Elevation.pdf · uploaded 20 Sep 2025Source
  • OthersDeclaration About CC.pdf · uploaded 23 Sep 2025Source
  • OthersForm-1 Reg- Brahma Tower Ph 2.pdf · uploaded 3 Nov 2025Source
  • OthersForm 2.pdf · uploaded 6 Nov 2025Source
  • OthersSelf Declaration Regarding no Bank Accounts of Landowners Technical.pdf · uploaded 6 Nov 2025Source
  • Document01 Layout - Highlighted.pdf · uploaded 7 Nov 2025Source
  • DocumentDeclaration cum Undertaking - order 50.pdf · uploaded 7 Nov 2025Source
  • OthersDeclaration for units alloted to landowners- Final- upload.pdf · uploaded 26 Nov 2025Source
  • OthersDeclaration for No bank account of Landowners- Final upload.pdf · uploaded 26 Nov 2025Source
  • OthersScreenshot of CC.pdf · uploaded 26 Nov 2025Source
  • OthersClarification for units to landowner - to be uploaded.pdf · uploaded 26 Nov 2025Source
  • OthersClarification Regarding Query Raised - Brahma Tower Phase II_Final.pdf · uploaded 9 Dec 2025Source
  • OthersBrahma Tower Phase 1 - A and B wing units allotment to landowners.pdf · uploaded 20 Dec 2025Source

Technical (Architect)

  • DocumentArchitect certificate 14-May-2026 (1).pdf · uploaded 29 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 MD.pdf · uploaded 29 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 176/1/2/3(Part), 176/1/6/3

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—58 units in all
Address
Wakad Road, MulshiPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
3,280 sq m (35,302 sq ft)
Permissible built-up area
5,875 sq m (63,241 sq ft)
Sanctioned built-up area
5,543 sq m (59,660 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

176/1/2/3(Part)176/1/6/3

Land as published on MahaRERA's project page

176/1/6/3 & 176/1/2/3(Part)

Boundaries

North
By DP Road
South
By Colony Road
East
By land owned by Onkar Constructions & Developers out of S No 176/1/6/1 & S nos 176/1/2/2(pt) & 176/1/2/3 pt
West
By project Brahma Tower I

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking58 units

58 units registered

— · 58 units
TypeCarpet areaUnits
——58

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantCA S S Jaju—
EngineerVishal Waghmare—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Wakad

All 314 projects in Wakad · Compare Brahma Tower Phase II with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology