Skip to content
Others · 2 buildings · 193 unitsRERA P52100018878

Akshay Anantam

Deedo IDDP-PUN-Q57J

Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 72% of its units are booked.

Wakad, Pune 411057 · Property rates in Wakad · by Sneh Constructions

DeliveryExtended 4 moPromised Mar 2028 · now due Jul 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales72% booked139 of 193 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2028

  • This projectRegistered 10 Dec 2018, completion promised 31 Mar 2028, revised to 31 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100018878
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001887810 Dec 201831 Mar 202831 Jul 2028Sneh ConstructionsProject page
Documents198

1 document held by Deedo, 197 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD - SNEH.PDF · uploaded 23 Nov 2018Source

Legal

  • Legal Title reportTITLE Certificate.pdf · uploaded 23 Nov 2018Source
  • Declaration Form BForm B.pdf · uploaded 30 Nov 2018Source
  • Legal Title reportSUPP SEARCH FEB 22.pdf · uploaded 10 Apr 2022Source
  • Legal Title reportTitle Report _compressed.pdf · uploaded 20 Feb 2023Source
  • Declaration Form BForm B.pdf · uploaded 21 Aug 2023Source
  • Legal Title reportsupp s and t 080424.pdf · uploaded 10 Apr 2024Source
Show all 198 documentsShow fewer documents

Legal

  • Declaration Form BForm B.pdf · uploaded 12 Aug 2024Source

Migrated

  • 1 PAN CardPAN CARD - SNEH.PDF · uploaded 23 Nov 2018Source
  • 1 Copy of the legal title reportTITLE Certificate.pdf · uploaded 23 Nov 2018Source
  • 1 Details of encumbrancesNO Encumbrance.pdf · uploaded 23 Nov 2018Source
  • 1 Copy of Layout Approval (in case of layout)1 7 Layout BP.pdf · uploaded 23 Nov 2018Source
  • 1 Building Plan Approval (IOD)2 7 Build A B Parking Plan.pdf · uploaded 23 Nov 2018Source
  • 2 Building Plan Approval (IOD)3 7 Build A B P Plan.pdf · uploaded 23 Nov 2018Source
  • 3 Building Plan Approval (IOD)4 7 Build A B P 3 4 5 Floor Plan.pdf · uploaded 23 Nov 2018Source
  • 4 Building Plan Approval (IOD)5 7 Build A B P 6 7 Tarace Plan.pdf · uploaded 23 Nov 2018Source
  • 5 Building Plan Approval (IOD)6 7 Build B 1st Floor Plan.pdf · uploaded 23 Nov 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Nov 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTI.pdf · uploaded 23 Nov 2018Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 23 Nov 2018Source
  • 6 Building Plan Approval (IOD)7 7 Build B 2nd Floor Plan.pdf · uploaded 26 Nov 2018Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 30 Nov 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 ARCHITECT.pdf · uploaded 30 Nov 2018Source
  • 1 Certificates of CA (Form 3)CA CERTI.pdf · uploaded 30 Nov 2018Source
  • 2 Proforma of Allotment letterAgreement Draft.pdf · uploaded 30 Nov 2018Source
  • 7 Building Plan Approval (IOD)SANCTION PLAN.pdf · uploaded 8 Jan 2020Source
  • 3 Proforma of Allotment letterATS below 1 mb.pdf · uploaded 20 Jan 2020Source
  • 2 Certificates of CA (Form 3)Form-3.pdf · uploaded 10 Nov 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentnew commencment certificate.pdf · uploaded 11 Nov 2021Source
  • 2 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 12 Nov 2021Source
  • 8 Building Plan Approval (IOD)FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • 9 Building Plan Approval (IOD)FLOOR PLAN-10.pdf · uploaded 12 Nov 2021Source
  • 10 Building Plan Approval (IOD)FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • 11 Building Plan Approval (IOD)ELEVATION.pdf · uploaded 12 Nov 2021Source
  • 12 Building Plan Approval (IOD)FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • 13 Building Plan Approval (IOD)FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • 14 Building Plan Approval (IOD)BUILDING PLAN.pdf · uploaded 12 Nov 2021Source
  • 15 Building Plan Approval (IOD)G-P FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • 16 Building Plan Approval (IOD)BUILDING PLAN 2.pdf · uploaded 15 Nov 2021Source
  • 3 Certificates of CA (Form 3)FOR 3 TILL 310321.pdf · uploaded 30 Jan 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Form 5 till 3132021.pdf · uploaded 30 Jan 2022Source
  • 2 Copy of the legal title reportSUPP SEARCH FEB 22.pdf · uploaded 10 Apr 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate FORM - D.pdf · uploaded 25 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A March 20.pdf · uploaded 25 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A March 21.pdf · uploaded 25 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A March 22.pdf · uploaded 25 Jan 2023Source
  • 1 Disclosure of sold/ booked inventoryForm-D Sold Unsold.pdf · uploaded 25 Jan 2023Source
  • 4 Certificates of CA (Form 3)Form 03 March-22-compressed.pdf · uploaded 25 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 05.pdf · uploaded 25 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsA - Annexure A Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 11 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM_05-SCANNED_COPY.pdf · uploaded 15 Feb 2023Source
  • 3 Copy of the legal title reportTitle Report _compressed.pdf · uploaded 20 Feb 2023Source
  • 2 Details of encumbrancesENCUMBERANCE DATTE.pdf · uploaded 20 Feb 2023Source
  • 3 a Details of encumbrances concerned to FinanceENCUMBERANCE DATTE.pdf · uploaded 20 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalENCUMBERANCE DATTE.pdf · uploaded 20 Feb 2023Source
  • 17 Building Plan Approval (IOD)Plan 1_compressed.pdf · uploaded 20 Feb 2023Source
  • 18 Building Plan Approval (IOD)Plan 2_compressed.pdf · uploaded 20 Feb 2023Source
  • 19 Building Plan Approval (IOD)Plan 3_compressed.pdf · uploaded 20 Feb 2023Source
  • 20 Building Plan Approval (IOD)Plan 4_compressed.pdf · uploaded 20 Feb 2023Source
  • 21 Building Plan Approval (IOD)Plan 6_compressed.pdf · uploaded 20 Feb 2023Source
  • 22 Building Plan Approval (IOD)Plan 7_compressed.pdf · uploaded 20 Feb 2023Source
  • 23 Building Plan Approval (IOD)Plan 5_compressed.pdf · uploaded 20 Feb 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC New 16-02-2023_compressed.pdf · uploaded 20 Feb 2023Source
  • 5 Certificates of CA (Form 3)01 -FORM 03 SEP-22.pdf · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)DECLARATION REGARDING FORM 5 FY 17-18.pdf · uploaded 20 Feb 2023Source
  • 1 Proforma of Agreement for saledraft agreement.pdf · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 FY - 2018-2019.pdf · uploaded 25 Feb 2023Source
  • 2 Declaration about Commencement CertificateFormat D.pdf · uploaded 21 Aug 2023Source
  • 2 Declaration in FORM BForm B.pdf · uploaded 21 Aug 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)12_From_01_June_-_2023.pdf · uploaded 21 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 21 Aug 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)08_From_05_March_-_2019.pdf · uploaded 21 Aug 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)09_From_05_March_-_2020.pdf · uploaded 21 Aug 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)10_From_05_March_-_2021.pdf · uploaded 21 Aug 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)11_From_05_March_-_2022.pdf · uploaded 21 Aug 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)From 2 31-03-2023.pdf · uploaded 24 Aug 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)From 2 30-06-2023.pdf · uploaded 24 Aug 2023Source
  • 2 Disclosure of sold/ booked inventoryCircular 29 24-08-2023.pdf · uploaded 24 Aug 2023Source
  • 6 Certificates of CA (Form 3)FORM 3 March 2023.pdf · uploaded 24 Aug 2023Source
  • 7 Certificates of CA (Form 3)FORM 3 June 2023.pdf · uploaded 24 Aug 2023Source
  • 4 Copy of the legal title reportsupp s and t 080424.pdf · uploaded 10 Apr 2024Source
  • 3 Copy of Layout Approval (in case of layout)01of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 24 Building Plan Approval (IOD)02of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 25 Building Plan Approval (IOD)03of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 26 Building Plan Approval (IOD)04of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 27 Building Plan Approval (IOD)05of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 28 Building Plan Approval (IOD)06of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 29 Building Plan Approval (IOD)08of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 30 Building Plan Approval (IOD)09of09 1mb.pdf · uploaded 10 Apr 2024Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC 060424.pdf · uploaded 10 Apr 2024Source
  • 8 Certificates of CA (Form 3)form3 sep23.pdf · uploaded 10 Apr 2024Source
  • 2 Proforma of Agreement for saleats 1mb.pdf · uploaded 10 Apr 2024Source
  • 9 Certificates of CA (Form 3)SIGNED FORM 3 DEC 23_compressed_compressed.pdf · uploaded 10 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)SCANNED_FORM_5 fy 2022_23_compressed.pdf · uploaded 10 Aug 2024Source
  • 3 Declaration in FORM BForm B.pdf · uploaded 12 Aug 2024Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Mar 24.pdf · uploaded 12 Aug 2024Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Jun 24.pdf · uploaded 12 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 12 Aug 2024Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 12 Aug 2024Source
  • 3 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 12 Aug 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 12 Aug 2024Source
  • 3 Declaration about Commencement CertificateDECLARATION___COMMENCEMENT_CERTIFICATE.pdf · uploaded 13 Aug 2024Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 310324.pdf · uploaded 11 Oct 2024Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 300624.pdf · uploaded 11 Oct 2024Source
  • 1 Certificates of CA (Form 3)Form-3 310324_11zon (1).pdf · uploaded 11 Oct 2024Source
  • 1 Certificates of CA (Form 3)Form-3300624_11zon.pdf · uploaded 11 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryBooked_Inventory.pdf · uploaded 11 Oct 2024Source
  • 1 Certificates of CA (Form 3)Form-3 310324_11zon (1).pdf · uploaded 11 Oct 2024Source
  • 2 Certificates of CA (Form 3)Form-3300624_11zon.pdf · uploaded 11 Oct 2024Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 310324.pdf · uploaded 11 Oct 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 300624.pdf · uploaded 11 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryBooked_Inventory.pdf · uploaded 11 Oct 2024Source
  • Form 1FORM1 311224.pdf · uploaded 11 Jun 2025Source
  • Form 1FORM1 300924.pdf · uploaded 11 Jun 2025Source
  • Form 2ENGINEERCERTIFICATE311224.pdf · uploaded 11 Jun 2025Source
  • Form 2EngineerCERTIFICATE30092024.pdf · uploaded 11 Jun 2025Source
  • Form 3FORM3 311224.pdf · uploaded 11 Jun 2025Source
  • Form 3FORM3 300924.pdf · uploaded 11 Jun 2025Source
  • Disclosure of Sold and Booked Inventoryinventory update 311224.pdf · uploaded 11 Jun 2025Source
  • Disclosure of Sold and Booked Inventoryinventory update 300924.pdf · uploaded 11 Jun 2025Source
  • Form 1FORM1 310325.pdf · uploaded 25 Jul 2025Source
  • Form 2ENGINEERS_CERTIFICATE-31-03-2025.pdf · uploaded 25 Jul 2025Source
  • Form 3FORM-3_310325_compressed.pdf · uploaded 25 Jul 2025Source
  • Disclosure of Sold and Booked InventoryINVENTORY 31032025.pdf · uploaded 25 Jul 2025Source
  • Withdrawal Update Form 1Form 1 -AA.pdf · uploaded 18 Sep 2025Source
  • Withdrawal Update Form 2Form_02.pdf · uploaded 18 Sep 2025Source
  • Withdrawal Update Form 3Form_03.pdf · uploaded 18 Sep 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 2FORM 2 31-12-2025.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 (2).pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 (2).pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 31-12-2025 Final.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 31-12-2025 Final.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 31-12-2025 Final.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 31-12-2025 Final.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 3FORM 3 31-12-2025 Final.pdf · uploaded 4 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3FORM 3 (2).pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2024-2025)FORM_2A_FY_24-25.pdf · uploaded 20 May 2026Source
  • Form 2A (FY 2025-2026)FORM_2A_FY_25-26.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2021-2022)Form-5 March 2022.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2022-2023)Form-5 March 2023.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2023-2024)Form-5 March 2024 (2).pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2024-2025)Form-5 March 2025.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2024-2025)Form-5 March 2025.pdf · uploaded 20 May 2026Source

Technical

  • Document2 7 Build A B Parking Plan.pdf · uploaded 23 Nov 2018Source
  • Document3 7 Build A B P Plan.pdf · uploaded 23 Nov 2018Source
  • Document4 7 Build A B P 3 4 5 Floor Plan.pdf · uploaded 23 Nov 2018Source
  • Document5 7 Build A B P 6 7 Tarace Plan.pdf · uploaded 23 Nov 2018Source
  • Document6 7 Build B 1st Floor Plan.pdf · uploaded 23 Nov 2018Source
  • Document1 7 Layout BP.pdf · uploaded 23 Nov 2018Source
  • Document7 7 Build B 2nd Floor Plan.pdf · uploaded 26 Nov 2018Source
  • DocumentSANCTION PLAN.pdf · uploaded 8 Jan 2020Source
  • DocumentLAYOUT.pdf · uploaded 12 Nov 2021Source
  • DocumentFLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentFLOOR PLAN-10.pdf · uploaded 12 Nov 2021Source
  • DocumentFLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentELEVATION.pdf · uploaded 12 Nov 2021Source
  • DocumentFLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentFLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentBUILDING PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentG-P FLOOR PLAN.pdf · uploaded 12 Nov 2021Source
  • DocumentBUILDING PLAN 2.pdf · uploaded 15 Nov 2021Source
  • DocumentPlan 5_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 1_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 2_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 3_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 4_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 6_compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentPlan 7_compressed.pdf · uploaded 20 Feb 2023Source
  • Document01of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document02of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document03of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document04of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document05of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document06of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document08of09 1mb.pdf · uploaded 10 Apr 2024Source
  • Document09of09 1mb.pdf · uploaded 10 Apr 2024Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 12 May 2026Source

Technical (Engineer)

  • DocumentForm-2 310324.pdf · uploaded 11 Oct 2024Source
  • DocumentForm-2 300624.pdf · uploaded 11 Oct 2024Source
  • DocumentForm-2 310324.pdf · uploaded 11 Oct 2024Source
  • DocumentForm-2 300624.pdf · uploaded 11 Oct 2024Source
  • DocumentFORM 2.pdf · uploaded 12 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 4 Part, Survey No 168/2 Part

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop, 1RK193 units in all
Address
Survey No 168/2 Part and 4 Part, Wakad Thergaon Road, Near Datta MandirPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
3,256 sq m (35,051 sq ft)
Permissible built-up area
7,815 sq m (84,120 sq ft)
Sanctioned built-up area
3,222 sq m (34,681 sq ft)
Recreational open space
326 sq m (3,506 sq ft)
Designated bank account
28
Developed in phases
Yes

Survey, CTS, gat or plot numbers

4 PartSurvey No 168/2 Part

Land as published on MahaRERA's project page

Survey No 168/2 Part and 4 Part

Boundaries

North
S No 164 Cha 2 part and 3 part
South
S No 168 cha 5
East
By 45 mtr wide wakad thergaon road
West
S No 164 cha 2 part and 4 part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking193 units

139 of 193 units booked (72%), as the promoter reported to MahaRERA

1BHK · 138 units2BHK · 53 unitsShop · 1 unit1RK · 1 unit
BuildingTypeCarpet areaUnitsBooked
Building A1BHK21.63 sq m · 233 sq ft1918
Building A1BHK24.11 sq m · 260 sq ft11
Building A1BHK25.53 sq m · 275 sq ft2121
Building A1BHK25.7 sq m · 277 sq ft22
Building A1BHK42 sq m · 452 sq ft1111
Building A1BHK43.29 sq m · 466 sq ft54
Building A1BHK43.36 sq m · 467 sq ft55
Building A1BHK44.43 sq m · 478 sq ft1110
Show all 21 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building A2BHK45.87 sq m · 494 sq ft55
Building A2BHK45.96 sq m · 495 sq ft55
Building A2BHK49.28 sq m · 530 sq ft11
Building A2BHK50.01 sq m · 538 sq ft10
Building A2BHK51.41 sq m · 553 sq ft11
Building A2BHK52.76 sq m · 568 sq ft10
Building AShop73.75 sq m · 794 sq ft11
Building B1BHK32.51 sq m · 350 sq ft5026
Building B1BHK33.16 sq m · 357 sq ft137
Building B1RK13.92 sq m · 150 sq ft10
Building B2BHK46.49 sq m · 500 sq ft139
Building B2BHK46.72 sq m · 503 sq ft136
Building B2BHK51.66 sq m · 556 sq ft136

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVivek Garode—
EngineerJw Consultants LLP—
EngineerNitin Vijay Lale—
OtherAvinash Navathe Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Wakad

All 314 projects in Wakad · Compare Akshay Anantam with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology