Extended 18 mo13 floorsRERA P52100001456
B, Vermont
Deedo IDDP-PUN-BNKE-BMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked98%84 of 86 · MahaRERA
Completion29 Dec 202030 Jun 2019 · revised
Units & parking in B
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 37.5 m² (404 sq.ft) | 1 | 1 |
| 2BHK | 49.8 m² (536 sq.ft) | 22 | 21 |
| 2BHK | 50.6 m² (545 sq.ft) | 41 | 40 |
| 3BHK | 73.4 m² (790 sq.ft) | 20 | 20 |
| 3BHK | 73.6 m² (792 sq.ft) | 2 | 2 |
As registered with MahaRERA
- RERA registration
- P52100001456 · registered 28 Jul 2017
- Promised completion
- 30 Jun 2019
- Revised completion
- 29 Dec 2020
- Sanctioned habitable floors
- 13
- Sanctioned floors (incl. basement, stilt, podium)
- 13
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-BNKE-B
Questions about B
When is B due for completion?
The MahaRERA registration promises 30 Jun 2019, revised to 29 Dec 2020.
How many floors does B have?
13 sanctioned habitable floors, as registered with MahaRERA.