RERA projects in Wade Bolhai
3 projects under 3 MahaRERA registrations, registered 2017–2017. 67% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
2Completion still due1 past their completion date
38 monthsMedian extension beyond promised date67% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
Projects in Wade Bolhai
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sunrise CityAirspeed Realty | P52100012131 | 1 Sep 2017 | 31 Jan 2021 | 1 Jun 2023 | Extended 29 mo | 0 |
| Sai ShawasVilas Tukaram Wadghule | P52100007646 | 17 Aug 2017 | 23 Dec 2026 | 23 Dec 2026 | Not yet due | 0 |
| Aapla Ghar Wagholi Annex Phase IMaple Indus Developers | P52100004818 | 9 Aug 2017 | 30 Dec 2022 | 31 Dec 2026 | Extended 48 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Airspeed Realty1 project
- Maple Indus Developers1 project
- Vilas Tukaram Wadghule1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology