Malhar Residency
Deedo IDDP-PUN-6T3PMahaRERA shows it completed, after its date was pushed back 1 year and 1 month; no MahaRERA orders on record; 70% of its units are booked.
Wadagaon (Ct), Pune 412106 · Property rates in Wadagaon (Ct) · by Ranjeet Developers
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year and 1 month
- This projectRegistered 6 Aug 2017, completion promised 30 Dec 2019, revised to 31 Jan 2021.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100003817
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100003817 | 6 Aug 2017 | 30 Dec 2019 | 31 Jan 2021 | Ranjeet Developers | Project page |
Documents70
2 documents held by Deedo, 68 filings listed on MahaRERA's project page
Finance
- PAN CardRanjeet DEVELOPERS-PAN original.pdf · uploaded 15 Jul 2017Source
Legal
Show all 70 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportsearch and title report2017.pdf · uploaded 28 Jul 2017Source
- 1 Details of encumbrancesDecleration form B-.pdf · uploaded 28 Jul 2017Source
- 2 Details of encumbrancessearch and title report2017.pdf · uploaded 28 Jul 2017Source
- 1 Building Plan Approval (IOD)Sanctioned Plans pdf.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form 1(2)compressed.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Certificate.pdf · uploaded 28 Jul 2017Source
- 1 Proforma of Allotment letterAllotment Letter Proforma.pdf · uploaded 28 Jul 2017Source
- 2 Proforma of Allotment letteragreemeant to sale.pdf · uploaded 28 Jul 2017Source
- 3 Proforma of Allotment letter7 12.pdf · uploaded 28 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Plans pdf.pdf · uploaded 30 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)Sanctioned Plans pdf.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of CA (Form 3)Certificates of CA (Form 3).pdf · uploaded 30 Jul 2017Source
- 2 Certificates of CA (Form 3)CA FORM - 3.pdf · uploaded 26 Aug 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate form 2 29092017.pdf · uploaded 29 Sep 2017Source
- 3 Certificates of CA (Form 3)CA Certificate form 3 29092017-.pdf · uploaded 29 Sep 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect's certificate.pdf · uploaded 30 Mar 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 30 Mar 2018Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 30 Mar 2018Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 30 Mar 2018Source
- 4 Certificates of CA (Form 3)CA CERTIFICATE MARCH18.pdf · uploaded 30 Mar 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate-ilovepdf-compressed.pdf · uploaded 14 Jul 2018Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate march 18.pdf · uploaded 14 Jul 2018Source
- 5 Certificates of CA (Form 3)CA Certificate Form-3-ilovepdf-compressed.pdf · uploaded 14 Jul 2018Source
- 1 Certificates of CA (Form 5)Form-5.pdf · uploaded 15 Oct 2018Source
- 2 Certificates of CA (Form 5)Form-5.pdf · uploaded 15 Oct 2018Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certifiate fy1819 Q1-.pdf · uploaded 30 Jan 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 4 Feb 2019Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 4 Feb 2019Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 4 Feb 2019Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate fy1819 Q2.pdf · uploaded 4 Feb 2019Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate FY 1819 Q3.pdf · uploaded 4 Feb 2019Source
- 6 Certificates of CA (Form 3)Q1.pdf · uploaded 4 Feb 2019Source
- 7 Certificates of CA (Form 3)Q2.pdf · uploaded 4 Feb 2019Source
- 8 Certificates of CA (Form 3)Q3.pdf · uploaded 4 Feb 2019Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architct certificate fy 18-19 Q 4.pdf · uploaded 5 Sep 2019Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate fy 18-19 Q4.pdf · uploaded 5 Sep 2019Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate fy 18-19 Q4.pdf · uploaded 5 Sep 2019Source
- 9 Certificates of CA (Form 3)CA Certificate Q4 18-19 Ranjeet D_compressed.pdf · uploaded 5 Sep 2019Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate JUNE 2019.pdf · uploaded 18 Oct 2019Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificare june19.pdf · uploaded 18 Oct 2019Source
- 10 Certificates of CA (Form 3)CA certificate june 19_compressed.pdf · uploaded 18 Oct 2019Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect Certificate.pdf · uploaded 30 Dec 2019Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 30 Dec 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 30 Dec 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineer Certificate 2A.pdf · uploaded 1 Jan 2020Source
- 11 Certificates of CA (Form 3)ca form -3 q- 2 fy 19-20.pdf · uploaded 1 Jan 2020Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY REGISTRATION CERTIFICATE.pdf · uploaded 24 Jan 2020Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate Form I for Q3 19-20.pdf · uploaded 27 Aug 2020Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate Q4 2020.pdf · uploaded 27 Aug 2020Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Q3 fy 19-20_compressed.pdf · uploaded 27 Aug 2020Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engeener Certificate q4 19-20_compressed.pdf · uploaded 27 Aug 2020Source
- 12 Certificates of CA (Form 3)CA Form-3 Q3 19-20_compressed.pdf · uploaded 27 Aug 2020Source
- 13 Certificates of CA (Form 3)CA Form-3 Q4 19-20_compressed.pdf · uploaded 27 Aug 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CA form 5 FY 1819.pdf · uploaded 29 Sep 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)architect form 4.pdf · uploaded 29 Sep 2020Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentfinal OC Malhar Residency (1).pdf · uploaded 23 Oct 2020Source
- 1 Status of ConveyanceSOCIETY REGISTRATION CERTIFICATE.pdf · uploaded 21 Jul 2021Source
Technical
Technical (Architect)
- DocumentArchitects Certificate Q4 2020.pdf · uploaded 27 Aug 2020Source
Technical (Engineer)
- Documentengeener Certificate q4 19-20_compressed.pdf · uploaded 27 Aug 2020Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO63/4B2/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Residencial, Resincial, Resindencial, Rsidencial63 units in all
- Address
- Survey No-63/4b2/2PIN 412106
- Village
- Wadagaon (CT), Mawal taluka
- Location
- 19.17208, 72.94826
- Land area for this project
- 2,880 sq m (31,000 sq ft)
- Permissible built-up area
- 2,892 sq m (31,127 sq ft)
- Sanctioned built-up area
- 2,883 sq m (31,029 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO-63/4B2/2
Boundaries
- North
- Survey no 63 Part 5 and 6
- South
- Road
- East
- Survey no 64
- West
- Survey no 64 Part 3 and Survey no 63
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking63 units
44 of 63 units booked (70%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Residencial | 42.64 sq m · 459 sq ft | 7 | 3 |
| Residencial | 43.48 sq m · 468 sq ft | 4 | 2 |
| Residencial | 43.76 sq m · 471 sq ft | 4 | 2 |
| Residencial | 44.5 sq m · 479 sq ft | 11 | 8 |
| Residencial | 44.69 sq m · 481 sq ft | 6 | 6 |
| Residencial | 44.87 sq m · 483 sq ft | 4 | 3 |
| Residencial | 60.39 sq m · 650 sq ft | 4 | 3 |
| Residencial | 62.25 sq m · 670 sq ft | 4 | 4 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Residencial | 63.45 sq m · 683 sq ft | 3 | 2 |
| Residencial | 64.2 sq m · 691 sq ft | 4 | 3 |
| Resincial | 57.6 sq m · 620 sq ft | 3 | 2 |
| Resindencial | 62.43 sq m · 672 sq ft | 3 | 1 |
| Rsidencial | 43.57 sq m · 469 sq ft | 6 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Girish Chandrashekhar Mohile | — |
| Engineer | Rajesh Balasaheb Nigade | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Wadagaon (Ct)
- DEVI Crest building A2 Phase 2RERA PR1261012602474
- Shivkunj ApartmentRERA PM1260002602402
- Vedant PrideRERA PM1260002602007
- S M TowerRERA PR1260002601950
- Kutumb Prime LifeRERA PM1260002601509
- Shravani HeightsRERA PR1260002601305
- Kutumb WoodsRERA PR1260002601201
- Shri Vinayak HeightsRERA PR1260002600319
All 113 projects in Wadagaon (Ct) · Compare Malhar Residency with another project