RERA projects in Vitthal Nagar

2 projects under 2 MahaRERA registrations, registered 2020–2025. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
78 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20201
20210
20220
20230
20240
20251

Projects in Vitthal Nagar

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Tulsi KunjShree Venkateshwara EnterprisesP5210008035726 May 202531 Dec 2026—Not yet due0
Shubharambh Cornersudarshan realitiesP5210002700610 Nov 202030 Jun 202431 Dec 2030Extended 78 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shree Venkateshwara Enterprises1 project
  2. sudarshan realities1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology