Deedo IDDP-PUN-2C8GMahaRERA shows it completed, after its date was pushed back 3 years and 11 months; no MahaRERA orders on record; 63% of its units are booked.
Uravade, Pune 412115 · by A S Associates
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 3 years and 11 months
- This projectRegistered 7 Aug 2017, completion promised 31 Jul 2019, revised to 30 Jun 2023.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100004048
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100004048 | 7 Aug 2017 | 31 Jul 2019 | 30 Jun 2023 | A S Associates | Project page |
Documents32
2 documents held by Deedo, 30 filings listed on MahaRERA's project page
Finance
- PAN CardPan card ASAsss.pdf · uploaded 11 Jul 2017Source
Legal
Show all 32 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)scan01958.pdf · uploaded 27 Jul 2017Source
- 2 Building Plan Approval (IOD)scan01959.pdf · uploaded 27 Jul 2017Source
- 1 Details of encumbrancesENCRUMBANC AFFIDAVIT.pdf · uploaded 29 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)PLANS PDF.pdf · uploaded 29 Jul 2017Source
- 1 Declaration in FORM BA S ASSOCIATES FORM B.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letterENGINEER CERTIFICATE.pdf · uploaded 29 Jul 2017Source
- 2 Proforma of Allotment letterLETTER AT THE TIME OF AGGREMENT.pdf · uploaded 29 Jul 2017Source
- 3 Proforma of Allotment letterAgreement A S Associates.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTFICATE.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 31 Jul 2017Source
- 2 Certificates of CA (Form 3)FORM NO 3.pdf · uploaded 1 Dec 2018Source
- 3 Certificates of CA (Form 3)CA FORM NO 3.pdf · uploaded 1 Dec 2018Source
- 1 Certificates of CA (Form 5)Form No 5.pdf · uploaded 1 Dec 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 2018-19.pdf · uploaded 4 Feb 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Occupancy Certificate - Bhogavta Pramanpatra.pdf · uploaded 8 Jul 2021Source
- 1 Architect’s Certificate on Completion of Project (Form 4)A S ASSOCIATES - Form 4.pdf · uploaded 8 Jul 2021Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development1AS.pdf · uploaded 12 Mar 2024Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2ADD.pdf · uploaded 12 Mar 2024Source
Technical
Technical (Architect)
- DocumentARCHITECT CERTFICATE.pdf · uploaded 31 Jul 2017Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.pdf · uploaded 31 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 142 142 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK40 units in all
- Address
- 142 142 1PIN 412115
- Village
- Uravade, Mulshi taluka
- Location
- 18.48492, 73.66523
- Land area for this project
- 823 sq m (8,853 sq ft)
- Permissible built-up area
- 1,233 sq m (13,267 sq ft)
- Sanctioned built-up area
- 1,233 sq m (13,267 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
142 142 1
Boundaries
- North
- Deshpande Plot
- South
- Plot Gurav
- East
- Road
- West
- Plot Govt
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking40 units
25 of 40 units booked (63%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 26.31 sq m · 283 sq ft | 4 | 2 |
| 1BHK | 28.73 sq m · 309 sq ft | 4 | 2 |
| 1BHK | 28.96 sq m · 312 sq ft | 4 | 3 |
| 1BHK | 29.21 sq m · 314 sq ft | 4 | 2 |
| 1BHK | 29.79 sq m · 321 sq ft | 4 | 1 |
| 1BHK | 30.51 sq m · 328 sq ft | 12 | 8 |
| 1RK | 19.4 sq m · 209 sq ft | 4 | 4 |
| 1RK | 22.46 sq m · 242 sq ft | 4 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Babasaheb Dhavale & Associates | — |
| Engineer | Ajinkya Bhagat | — |
| Engineer | Vilas Purandare | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Uravade
- Nakshatra Angan C BuildingRERA PR1260002601686
- Evernest Phase 2RERA P52100055476
- Evernest Phase 1RERA P52100055283
- Hill TownRERA P52100051279
- Up-Life-Phase-5-IvoryRERA P52100024921
- Up-Life-Phase-2-EmeraldRERA P52100024865
- Up-Life-Phase-3-SapphireRERA P52100024824
- Up-Life-Phase-4-LavenderRERA P52100024849
All 17 projects in Uravade · Compare Vishnu Krupa with another project