Vasant Vihar
Deedo IDDP-PUN-VTNZIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; MahaRERA lists it: deregistered; 20% of its units are booked.
Talegaon Dabhade (R), Pune 410506 · Property rates in Talegaon Dabhade (R) · by Nakshatra Buildcon · 80% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 24 Jan 2023, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory record1
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- DeregisteredMatched by RERA number
Deregistered: VASANT VIHAR
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100048937
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100048937 | 24 Jan 2023 | 31 Dec 2025 | 31 Dec 2025 | Nakshatra Buildcon | Project page |
Documents43
1 document held by Deedo, 42 filings listed on MahaRERA's project page
Finance
- PAN CardNAKSHATRA-PAN CARD.pdf · uploaded 5 Jan 2023Source
Legal
Migrated
- 1 PAN CardNAKSHATRA-PAN CARD.pdf · uploaded 5 Jan 2023Source
- 1 Copy of the legal title reportsearch report.pdf · uploaded 7 Jan 2023Source
- 1 a Details of encumbrances concerned to Financelegal and finance no encubrance.pdf · uploaded 7 Jan 2023Source
- 1 b Details of encumbrances concerned to Legallegal and finance no encubrance.pdf · uploaded 7 Jan 2023Source
Show all 43 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 7 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentVASANT VIHAR.pdf · uploaded 7 Jan 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentNA ORDER.pdf · uploaded 7 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 7 Jan 2023Source
- 1 Declaration about Commencement Certificatedeclaration about comencement.pdf · uploaded 7 Jan 2023Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 7 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 7 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERIFICATE.pdf · uploaded 7 Jan 2023Source
- 1 CERSAI detailscersai not aplicable.pdf · uploaded 7 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizationsannexure A.pdf · uploaded 7 Jan 2023Source
- 1 Proforma of Agreement for saleAGREEMENT TO SALE.pdf · uploaded 7 Jan 2023Source
- 1 Proforma of Allotment letterModal form of Allotment Letter.pdf · uploaded 7 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate bank account for real estate projects.pdf · uploaded 7 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterNo deviation Report with respect to model copy of Allotment Letter.pdf · uploaded 7 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementNo deviation Report with respect to model copy of agreement to sale.pdf · uploaded 7 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3.pdf · uploaded 10 Jan 2023Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance Finance.pdf · uploaded 12 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance Finance.pdf · uploaded 12 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera quarterly update architect letter.pdf · uploaded 25 May 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)VASANTVIHAR_ENGINEERS CERTIFICATE (1).pdf · uploaded 25 May 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Nakshatra-.pdf · uploaded 25 May 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)engineer certificate Vasantviha.pdf · uploaded 15 Jul 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect-.pdf · uploaded 15 Jul 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate Vasantviha.pdf · uploaded 15 Jul 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate For Rera.pdf · uploaded 11 Nov 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg certificate .pdf · uploaded 11 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 -_compressed.pdf · uploaded 11 Nov 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect-dec 23.pdf · uploaded 2 Feb 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate Vasantviha -dec 23.pdf · uploaded 2 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 -dec 23_compressed (3).pdf · uploaded 2 Feb 2024Source
Technical
Technical (Architect)
- Documentarchitect-dec 23.pdf · uploaded 2 Feb 2024Source
Technical (Engineer)
- Documentengineer certificate Vasantviha -dec 23.pdf · uploaded 2 Feb 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 14 CTS NO 7366/29
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK10 units in all
- Address
- Plot No 14 Cts No 7366/29, Plot No 14 Cts No 7366/29 Kadolkar Colony 2, Talegaon DabhadePIN 410506
- Village
- Talegaon Dabhade (M Cl), Mawal taluka
- Location
- 18.71782, 73.67785
- Land area for this project
- 307 sq m (3,299 sq ft)
- Permissible built-up area
- 833 sq m (8,963 sq ft)
- Sanctioned built-up area
- 833 sq m (8,963 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 14 CTS NO 7366/29
Boundaries
- North
- Plot No 15
- South
- Plot No 13
- East
- Panchawati Colony Road
- West
- Colony Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking10 units
2 of 10 units booked (20%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 74.9 sq m · 806 sq ft | 5 | 1 |
| 3BHK | 75.77 sq m · 816 sq ft | 5 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Amey Nitin Wadekar | — |
| Chartered accountant | Nikhil Raheja | — |
| Engineer | Er Ajinkya M Malkar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Talegaon Dabhade (R)
- NakshatrabanRERA PM1260002602090
- Shree RamkunjRERA PR1260002602096
- Sai EmpireRERA PM1260002601050
- Neel-PrakashRERA PR1260002600727
- Shalom HarmonyRERA PM1260002600174
- Sankeshwar HeightsRERA PM1260002502658
- Sai AromaRERA PR1260002501886
- Hill Top ResidencyRERA PR1260002501836
All 144 projects in Talegaon Dabhade (R) · Compare Vasant Vihar with another project