Company or firm · first RERA registration 2019
Nakshatra Buildcon
Deedo IDDD-2AQ0Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 10 mo late.
Projects55 RERA registrations
Kept RERA date80%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Vasant ViharDeregistered: VASANT VIHAR | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| NakshatramP52100020949 | Talegaon Dabhade (R) | Certificate Signed | 7 Feb 2023 | 7 Feb 2023 | On date |
| Savitri ParkP52100022629 | Talegaon Dabhade (M Cl) | Certificate Signed | 1 Jul 2022 | 1 Jul 2022 | On date |
| KasturiP52100023848 | Talegaon Dabhade (M Cl) | Certificate Signed | 4 Dec 2022 | 4 Dec 2022 | On date |
| RutugandhP52100029278 | Talegaon Dabhade (M Cl) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Vasant ViharP52100048937 | Talegaon Dabhade (M Cl) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology