MahaRERA shows it completed, after its date was pushed back 1 year and 6 months
- This projectRegistered 7 Aug 2017, completion promised 30 Jun 2021, revised to 30 Dec 2022.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100004047
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100004047 | 7 Aug 2017 | 30 Jun 2021 | 30 Dec 2022 | Sujay Ventures | Project page |
Documents60
2 documents held by Deedo, 58 filings listed on MahaRERA's project page
Finance
- PAN CardSUJAY VENTURE PAN.pdf · uploaded 7 Apr 2023Source
Legal
- Declaration Form B6 Declaration in FORM B.pdf · uploaded 30 Jul 2017Source
- Legal Title reportSearch Report.pdf · uploaded 30 Jul 2017Source
- Declaration Form BForm B.pdf · uploaded 21 Aug 2017Source
- Declaration Form B30-09-2017 Certificate of Engineer (FORM2).pdf · uploaded 31 Mar 2018Source
- Declaration Form B31-12-2017 Certificate of Engineer (FORM2).pdf · uploaded 31 Mar 2018Source
Show all 60 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportSearch Report.pdf · uploaded 30 Jul 2017Source
- 1 Details of encumbrances3 Details of Encumbrances.pdf · uploaded 30 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)4 Copy of Layout Approval.pdf · uploaded 30 Jul 2017Source
- 1 Building Plan Approval (IOD)13 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- 2 Building Plan Approval (IOD)14 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- 3 Building Plan Approval (IOD)15 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- 4 Building Plan Approval (IOD)16 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- 1 Declaration in FORM B6 Declaration in FORM B.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)7 Certificate of architect(Form1).pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11 Certificate of Engineer (FORM 2) 1.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of CA (Form 3)9 Certificate of CA (FORM 3).pdf · uploaded 30 Jul 2017Source
- 1 Proforma of Allotment letter5 Proforma of Allotment Letter and agreemet to sale.pdf · uploaded 30 Jul 2017Source
- 2 Declaration in FORM BForm B.pdf · uploaded 21 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted development4 Copy of Layout Approval.pdf · uploaded 22 Mar 2018Source
- 3 Declaration in FORM B30-09-2017 Certificate of Engineer (FORM2).pdf · uploaded 31 Mar 2018Source
- 4 Declaration in FORM B31-12-2017 Certificate of Engineer (FORM2).pdf · uploaded 31 Mar 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-09-2017 Certificate of architect(Form1).pdf · uploaded 31 Mar 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-12-2017 Certificate of architect(Form1).pdf · uploaded 31 Mar 2018Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate_F.pdf · uploaded 27 Jul 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)30_06_2018 Certificate of Engineer (FORM 2)_F.pdf · uploaded 27 Jul 2018Source
- 2 Certificates of CA (Form 3)Form 3 CA Certificate_F.pdf · uploaded 27 Jul 2018Source
- 1 Certificates of CA (Form 5)FORM 5 Self Declaration Copy .pdf · uploaded 3 Oct 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate_F2 Building.pdf · uploaded 8 Jul 2022Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentF2_ Building Final COMPLETION CRTIFICATE.pdf · uploaded 22 Feb 2023Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC D2 Final.pdf · uploaded 22 Feb 2023Source
- 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 31 Mar 2023Source
- 1 PAN CardSUJAY VENTURE PAN.pdf · uploaded 7 Apr 2023Source
- 2 a Details of encumbrances concerned to FinanceENCUMBRANCES_Certifificate for legal.pdf · uploaded 7 Apr 2023Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCES_Certifificate for legal.pdf · uploaded 7 Apr 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)31_03_2019 - Copy.pdf · uploaded 7 Apr 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)30_09_2019 - Copy.pdf · uploaded 7 Apr 2023Source
- 1 Deviation Report with respect to model copy of Agreementdeviation report with respect model.pdf · uploaded 7 Apr 2023Source
- 1 CERSAI detailsSelf Declaration (1).pdf · uploaded 10 Apr 2023Source
- 6 Architect’s Certificate on Completion of Project (Form 4)FORM 4 -ARCHITECTS CERIFICATE D2 BUILDING (1).pdf · uploaded 10 Apr 2023Source
- 7 Architect’s Certificate on Completion of Project (Form 4)FORM 4 -ARCHITECTS CERIFICATE F2 BUILDING (1).pdf · uploaded 10 Apr 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Bank Account (2).pdf · uploaded 10 Apr 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report.pdf · uploaded 10 Apr 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 17 Apr 2023Source
- 1 Declaration about Commencement CertificateDelcartion commence certficate.pdf · uploaded 17 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)31_03_2020.pdf · uploaded 17 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)31_03_2021.pdf · uploaded 17 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)31_03_2022.pdf · uploaded 17 Apr 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 17 Apr 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)F2_Society Registration Certificate (1).pdf · uploaded 10 May 2023Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)IMG-20230425-WA0011 (1).pdf · uploaded 10 May 2023Source
Technical
- Document13 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- Document14 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- Document15 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- Document16 Building Approval Plan( IOD).pdf · uploaded 30 Jul 2017Source
- Document4 Copy of Layout Approval.pdf · uploaded 30 Jul 2017Source
Technical (Architect)
- DocumentArchitects Certificate_F.pdf · uploaded 27 Jul 2018Source
Technical (Engineer)
- Document30_09_2019 - Copy.pdf · uploaded 7 Apr 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 258 259 260 274 PART
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 1BHK129 units in all
- Address
- 258 259 260 274 PartPIN 410506
- Village
- Somatane, Mawal taluka
- Location
- 19.28552, 72.86930
- Land area for this project
- 2,775 sq m (29,870 sq ft)
- Permissible built-up area
- 6,395 sq m (68,839 sq ft)
- Sanctioned built-up area
- 6,395 sq m (68,839 sq ft)
- Recreational open space
- 277 sq m (2,982 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
258 259 260 274 PART
Boundaries
- North
- Adj G No 258 And Bldg Fi
- South
- 12m Wide Internal Road And Adjg No 261
- East
- Adj Bldg B2 And Gat No 34 Boundary Of Shirgaon
- West
- Adj Bldg D1 And Bldg E2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking129 units
37 of 129 units booked (29%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building D2 | 2BHK | 58.15 sq m · 626 sq ft | 2 | 2 |
| Building D2 | 2BHK | 58.79 sq m · 633 sq ft | 5 | 2 |
| Building D2 | 2BHK | 61.38 sq m · 661 sq ft | 7 | 7 |
| Building D2 | 2BHK | 63.03 sq m · 678 sq ft | 8 | 2 |
| Building D2 | 2BHK | 63.16 sq m · 680 sq ft | 13 | 4 |
| Building D2 | 2BHK | 65.78 sq m · 708 sq ft | 7 | 7 |
| Building F2 | 1BHK | 36.03 sq m · 388 sq ft | 18 | 2 |
| Building F2 | 1BHK | 36.11 sq m · 389 sq ft | 11 | 0 |
Show all 17 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building F2 | 1BHK | 36.16 sq m · 389 sq ft | 12 | 1 |
| Building F2 | 1BHK | 37.55 sq m · 404 sq ft | 12 | 1 |
| Building F2 | 1BHK | 37.58 sq m · 405 sq ft | 9 | 1 |
| Building F2 | 1BHK | 40.68 sq m · 438 sq ft | 1 | 1 |
| Building F2 | 1BHK | 40.77 sq m · 439 sq ft | 1 | 1 |
| Building F2 | 1BHK | 42.17 sq m · 454 sq ft | 1 | 1 |
| Building F2 | 2BHK | 50.18 sq m · 540 sq ft | 10 | 3 |
| Building F2 | 2BHK | 50.67 sq m · 545 sq ft | 11 | 1 |
| Building F2 | 2BHK | 57.35 sq m · 617 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | A Shivprasad Mahajan | — |
| Engineer | Arun Gokhale | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Somatane
- Joytown CapitalRERA P52100078355
- Surabhi City Phase 1RERA P52100054701
- Kotwal Business Zone Building ARERA P52100054072
- Kotwal Business Zone Building BRERA P52100054076
- Arianna HomesRERA P52100053619
- Supreme VillagioRERA P52100046867
- Silver CrystaRERA P52100034325
- Mg AurisRERA P52100031201
All 27 projects in Somatane · Compare Windchime Homes Phase 2 with another project