City Lights
Deedo IDDP-PUN-7XKBCompletion was pushed back 1 year and 6 months to Jun 2022, and that date has passed too; no MahaRERA orders on record; 61% of its units are booked.
Shiwapur, Pune 412205 · by Mohiniraj Associates
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year and 6 months to Jun 2022, and that date has passed too
- This projectRegistered 16 Oct 2017, completion promised 30 Dec 2020, revised to 30 Jun 2022, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- City Lights Wing A12 floors · 65 units92% booked
- City Lights Wing B12 floors
- City Lights Wing C12 floors · 63 units29% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100013655
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100013655 | 16 Oct 2017 | 30 Dec 2020 | 30 Jun 2022 | Mohiniraj Associates | Project page |
Documents62
3 documents held by Deedo, 59 filings listed on MahaRERA's project page
Show all 62 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesSelf Declaration for Encumbrances.pdf · uploaded 29 Sep 2017Source
- 1 Copy of Layout Approval (in case of layout)Map-01-17.pdf · uploaded 29 Sep 2017Source
- 1 Building Plan Approval (IOD)Map-01-17.pdf · uploaded 29 Sep 2017Source
- 2 Building Plan Approval (IOD)Map-02-17.pdf · uploaded 29 Sep 2017Source
- 3 Building Plan Approval (IOD)Map-03-17.pdf · uploaded 29 Sep 2017Source
- 4 Building Plan Approval (IOD)Map-04-17.pdf · uploaded 29 Sep 2017Source
- 5 Building Plan Approval (IOD)Map-05-17.pdf · uploaded 29 Sep 2017Source
- 6 Building Plan Approval (IOD)Map-06-17.pdf · uploaded 29 Sep 2017Source
- 7 Building Plan Approval (IOD)Map-07-17.pdf · uploaded 29 Sep 2017Source
- 8 Building Plan Approval (IOD)Map-08-17.pdf · uploaded 29 Sep 2017Source
- 9 Building Plan Approval (IOD)Map-09-17.pdf · uploaded 29 Sep 2017Source
- 10 Building Plan Approval (IOD)Map-10-17.pdf · uploaded 29 Sep 2017Source
- 11 Building Plan Approval (IOD)Map-11-17.pdf · uploaded 29 Sep 2017Source
- 12 Building Plan Approval (IOD)Map-12-17.pdf · uploaded 29 Sep 2017Source
- 13 Building Plan Approval (IOD)Map-13-17.pdf · uploaded 29 Sep 2017Source
- 14 Building Plan Approval (IOD)Map-14-17.pdf · uploaded 29 Sep 2017Source
- 15 Building Plan Approval (IOD)Map-15-17.pdf · uploaded 29 Sep 2017Source
- 16 Building Plan Approval (IOD)Map-16-17.pdf · uploaded 29 Sep 2017Source
- 17 Building Plan Approval (IOD)Map-17-17.pdf · uploaded 29 Sep 2017Source
- 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 29 Sep 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate_Final.pdf · uploaded 29 Sep 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer's Certificate.pdf · uploaded 29 Sep 2017Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 29 Sep 2017Source
- 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 29 Sep 2017Source
- 1 Details of Restarting of Construction work post lockdowncwing status.pdf · uploaded 20 Sep 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFIATE.pdf · uploaded 11 Oct 2021Source
- 1 Declaration about Commencement Certificatedecleration about Commencement certificate.pdf · uploaded 19 Oct 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2A 19-20.pdf · uploaded 19 Oct 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2A 20-21.pdf · uploaded 19 Oct 2021Source
- 1 Disclosure of sold/ booked inventorydisclosure of booked ,sold inventory.pdf · uploaded 19 Oct 2021View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)form 5 17-18.pdf · uploaded 19 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5 18-19.pdf · uploaded 19 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form 5 19-20.pdf · uploaded 19 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 20-21.pdf · uploaded 19 Oct 2021Source
Technical
- DocumentMap-14-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-15-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-12-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-13-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-17-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-01-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-16-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-01-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-02-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-03-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-04-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-05-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-06-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-07-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-08-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-09-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-10-17.pdf · uploaded 29 Sep 2017Source
- DocumentMap-11-17.pdf · uploaded 29 Sep 2017Source
Technical (Architect)
- DocumentArchitect Certificate_Final.pdf · uploaded 29 Sep 2017Source
Technical (Engineer)
- DocumentForm 2 Engineer's Certificate.pdf · uploaded 29 Sep 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 779 B, GAT NO 779 A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK128 units in all
- Address
- Gat No 779 A And 779 BPIN 412205
- Village
- Shiwapur, Haveli taluka
- Location
- 18.33256, 73.85159
- Land area for this project
- 7,600 sq m (81,806 sq ft)
- Permissible built-up area
- 7,346 sq m (79,072 sq ft)
- Sanctioned built-up area
- 7,346 sq m (79,072 sq ft)
- Recreational open space
- 762 sq m (8,202 sq ft)
- Designated bank account
- 66
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT NO 779 A AND 779 B
Boundaries
- North
- Gat No 821
- South
- Gat No 780 And 789 B
- East
- National Highway No 4
- West
- Gat No 777
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking128 units
78 of 128 units booked (61%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| City Lights Wing A | 1BHK | 2,130.23 sq m · 22,930 sq ft | 65 | 60 |
| City Lights Wing C | 1BHK | 2,368.65 sq m · 25,496 sq ft | 63 | 18 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ms Shailesh Salehittal | — |
| Chartered accountant | Avgkllp | — |
| Engineer | Navnath Lalu Kale | — |
Source: MahaRERA project page. Contact details are not shown.