Skip to content
Deedo home
Menu

Mango Tree Villa

Completion due Sep 2029

Shewalewadi, Pune 412307 |Promoter: Palchin Real Estates Private Limited

20 Sep 2023Registered with MahaRERAFirst of 6 registrations
30 Sep 2029Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
6
Phases
6

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.49439, 73.96726
Mango Tree Villa is at latitude 18.49439, longitude 73.96726.

Also registered as

Mango Tree Villa Tower 3Mango Tree Villa Tower 2Mango Tree Villa Tower 1Mango Tree Villa Tower 4Mango Tree Villa Phase 1Mango Tree Villa Phase 2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2027

P52100052683
Registered
20 Sep 2023
Promised
30 Jun 2027

Completion promised for 30 Jul 2027

P52100053177
Registered
17 Oct 2023
Promised
30 Jul 2027

Completion promised for 30 Jun 2029

P52100053927
Registered
11 Dec 2023
Promised
30 Jun 2029

Completion promised for 31 Mar 2029

P52100053966
Registered
18 Dec 2023
Promised
31 Mar 2029
Show 2 more registrations

Completion promised for 28 Feb 2029

P52100053978
Registered
18 Dec 2023
Promised
28 Feb 2029

Completion promised for 30 Sep 2029

P52100054077
Registered
27 Dec 2023
Promised
30 Sep 2029

6 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005268320 Sep 202330 Jun 2027—Palchin Real Estates Private LimitedProject page
P5210005317717 Oct 202330 Jul 2027—Palchin Real Estates Private LimitedProject page
P5210005392711 Dec 202330 Jun 2029—Palchin Real Estates Private LimitedProject page
P5210005396618 Dec 202331 Mar 202931 Mar 2029Palchin Real Estates Private LimitedProject page
P5210005397818 Dec 202328 Feb 2029—Palchin Real Estates Private LimitedProject page
P5210005407727 Dec 202330 Sep 2029—Palchin Real Estates Private LimitedProject page

Documents

9 documents held by Deedo

Extension certificates

  • Extension certificateP52100053966 · 26 Mar 2025ViewSource
  • Extension certificateP52100054077 · 13 Aug 2026ViewSource
  • Extension certificateP52100053978 · 21 Aug 2026ViewSource

Registration certificates

  • Registration certificateP52100054077 · 20 Aug 2026ViewSource
  • Registration certificateP52100053177 · 20 Aug 2026ViewSource
  • Registration certificateP52100052683 · 20 Aug 2026ViewSource
  • Registration certificateP52100053966 · 20 Aug 2026ViewSource
  • Registration certificateP52100053978 · 24 Aug 2026ViewSource
  • Registration certificateP52100053927 · 24 Aug 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shewalewadi

Survey, CTS, gat or plot numbers

11/111/2A11/2B11/2C11/2D/111/2D/212/4(P)12/513/113/2A141516 at71/1/1B71/A/1/1E at71/A/1/1F71/A/271/B71B71C/2Survey Nos. 11/1Survey Nos. 70A

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology