Completion was pushed back 4 months, to Jan 2030; no MahaRERA orders on record; 19% of its units are booked.

Shewalewadi, Pune 412307 · Property rates in Shewalewadi · by Palchin Real Estates Private Limited

DeliveryExtended 4 moPromised Sep 2029 · now due Jan 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales19% booked61 of 317 units · as the promoter reported to MahaRERAPrice₹13,630 /sq ft43.3% above Shewalewadi · 25 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jan 2030

  • P52100052683Registered 20 Sep 2023, completion promised 30 Jun 2027, revised to 30 Oct 2027.
  • P52100053177Registered 17 Oct 2023, completion promised 30 Jul 2027, revised to 30 Nov 2027.
  • P52100053927Registered 11 Dec 2023, completion promised 30 Jun 2029, revised to 30 Oct 2029.
  • P52100053966Registered 18 Dec 2023, completion promised 31 Mar 2029.
  • P52100053978Registered 18 Dec 2023, completion promised 28 Feb 2029, revised to 28 Jun 2029.
  • P52100054077Registered 27 Dec 2023, completion promised 30 Sep 2029, revised to 30 Jan 2030.

3 extension certificates on record.

6 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 107 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 20264 · 301Primary sale1,650 sq ftView Primary sale, Oct 2026
Sep 20263 · 704Primary sale1,160 sq ftView Primary sale, Sep 2026
Sep 20263 · 501Primary sale1,163 sq ftView Primary sale, Sep 2026
Sep 20264 · 403Primary sale1,252 sq ftView Primary sale, Sep 2026
Sep 20261 · 502Primary sale1,650 sq ftView Primary sale, Sep 2026
Aug 20264 · 102Primary sale1,650 sq ftView Primary sale, Aug 2026
Aug 20263 · 1301Primary sale1,163 sq ftView Primary sale, Aug 2026
Aug 20263 · 1302Primary sale1,167 sq ftView Primary sale, Aug 2026
Aug 20263 · 504Primary sale1,160 sq ftView Primary sale, Aug 2026
Jul 20263 · 804Primary sale1,160 sq ftView Primary sale, Jul 2026

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations6
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005268320 Sep 202330 Jun 202730 Oct 2027Palchin Real Estates Private LimitedProject page
P5210005317717 Oct 202330 Jul 202730 Nov 2027Palchin Real Estates Private LimitedProject page
P5210005392711 Dec 202330 Jun 202930 Oct 2029Palchin Real Estates Private LimitedProject page
P5210005396618 Dec 202331 Mar 202931 Mar 2029Palchin Real Estates Private LimitedProject page
P5210005397818 Dec 202328 Feb 202928 Jun 2029Palchin Real Estates Private LimitedProject page
P5210005407727 Dec 202330 Sep 202930 Jan 2030Palchin Real Estates Private LimitedProject page
Documents733

9 documents held by Deedo, 724 filings listed on MahaRERA's project page

Extension certificate (3)

  • Extension certificateP52100053966 · 26 Mar 2025ViewSource
  • Extension certificateP52100054077 · 13 Aug 2026ViewSource
  • Extension certificateP52100053978 · 21 Aug 2026ViewSource

Registration certificate (6)

  • Registration certificateP52100054077 · 20 Aug 2026ViewSource
  • Registration certificateP52100053177 · 20 Aug 2026ViewSource
  • Registration certificateP52100052683 · 20 Aug 2026ViewSource
  • Registration certificateP52100053966 · 20 Aug 2026ViewSource
  • Registration certificateP52100053978 · 24 Aug 2026ViewSource
Show all 733 documentsShow fewer documents

Registration certificate (6)

  • Registration certificateP52100053927 · 24 Aug 2026ViewSource

Finance

  • PAN CardP52100054077 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Jul 2023Source
  • PAN CardP52100052683 · Mrunmai PAN Card-LTD.pdf · uploaded 11 Aug 2023Source
  • PAN CardP52100053177 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Aug 2023Source
  • PAN CardP52100053966 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Aug 2023Source
  • PAN CardP52100053978 · PAN Card- Mrunmai.pdf · uploaded 31 Oct 2023Source
  • PAN CardP52100053927 · PAN Card- Mrunmai.pdf · uploaded 31 Oct 2023Source
  • Other – FinanceP52100053927 · V2- Declaration for Separate Bank Account 04122023.pdf · uploaded 4 Dec 2023Source
  • PAN CardP52100053177 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • PAN CardP52100054077 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • PAN CardP52100052683 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • PAN CardP52100053978 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • PAN CardP52100053927 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • PAN CardP52100053966 · Palchin PAN.pdf · uploaded 26 Jul 2024Source

Legal

  • Declaration Form BP52100054077 · MTV Tower 3- Form B.pdf · uploaded 14 Jul 2023Source
  • Legal Title reportP52100052683 · Title Report- Part 1.pdf · uploaded 11 Aug 2023Source
  • Legal Title reportP52100052683 · Title Report- Part 2.pdf · uploaded 11 Aug 2023Source
  • Declaration Form BP52100052683 · MTV Tower 1- Affidavit (Form B).pdf · uploaded 11 Aug 2023Source
  • Declaration Form BP52100053177 · MTV Tower 2- Form B.pdf · uploaded 14 Aug 2023Source
  • Declaration Form BP52100053966 · MTV Tower 4- Form B.pdf · uploaded 14 Aug 2023Source
  • Other – LegalP52100053177 · MTV T2- Declaration on Survey (legal)_signed.pdf · uploaded 9 Oct 2023Source
  • Legal Title reportP52100053177 · Part 1.pdf · uploaded 10 Oct 2023Source
  • Legal Title reportP52100053177 · Part 2.pdf · uploaded 10 Oct 2023Source
  • Legal Title reportP52100054077 · Part 1.pdf · uploaded 18 Oct 2023Source
  • Legal Title reportP52100054077 · Part 2.pdf · uploaded 18 Oct 2023Source
  • Legal Title reportP52100053966 · Part 1.pdf · uploaded 18 Oct 2023Source
  • Legal Title reportP52100053966 · Part 2.pdf · uploaded 18 Oct 2023Source
  • Legal Title reportP52100053978 · Part 1.pdf · uploaded 31 Oct 2023Source
  • Legal Title reportP52100053978 · Part 2.pdf · uploaded 31 Oct 2023Source
  • Declaration Form BP52100053978 · Villa Phase 1- Form B.pdf · uploaded 31 Oct 2023Source
  • Legal Title reportP52100053927 · Part 1.pdf · uploaded 31 Oct 2023Source
  • Legal Title reportP52100053927 · Part 2.pdf · uploaded 31 Oct 2023Source
  • Declaration Form BP52100053927 · Villa Phase 2- Form B.pdf · uploaded 4 Nov 2023Source
  • Other – LegalP52100053966 · NCLT Certified Order- 17th Feb 2020.pdf · uploaded 9 Nov 2023Source
  • Other – LegalP52100053966 · Mrunmai- Palchin Scheme.pdf · uploaded 9 Nov 2023Source
  • Other – LegalP52100054077 · NCLT Certified Order- 17th Feb 2020.pdf · uploaded 13 Nov 2023Source
  • Other – LegalP52100054077 · Mrunmai- Palchin Scheme.pdf · uploaded 13 Nov 2023Source
  • Other – LegalP52100054077 · NCLT Order dtd 10th July 2023.pdf · uploaded 28 Nov 2023Source
  • Other – LegalP52100054077 · T3- Declaration for 2012 Demerger.pdf · uploaded 28 Nov 2023Source
  • Other – LegalP52100054077 · Part 1.pdf · uploaded 28 Nov 2023Source
  • Other – LegalP52100054077 · Part 2.pdf · uploaded 28 Nov 2023Source
  • Other – LegalP52100054077 · Part 3.pdf · uploaded 28 Nov 2023Source
  • Other – LegalP52100053978 · (1) Mrunmai- Palchin Scheme.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · (2) NCLT Order- 17th Feb 2020.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · V1- Declaration on Survey (legal) 04122023.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · NCLT Order dtd 10th July 2023.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · Villa 1- Declaration for 2012 Demerger.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · Part 1.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · Part 2.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053978 · Part 3.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · V2- Declaration on Survey (legal) 04122023.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · (2) NCLT Order- 17th Feb 2020.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · (1) Mrunmai- Palchin Scheme.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · (3) NCLT Order dtd 10th July 2023.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · Villa 2- Declaration for 2012 Demerger.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · Part 1.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · Part 2.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053927 · Part 3.pdf · uploaded 4 Dec 2023Source
  • Other – LegalP52100053966 · (3) NCLT Order dtd 10th July 2023.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100053966 · T4- Declaration for 2012 Demerger.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100053966 · Part 1.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100053966 · Part 2.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100053966 · Part 3.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100053966 · T4- Declaration on Survey (legal) 08122023.pdf · uploaded 8 Dec 2023Source
  • Other – LegalP52100054077 · T3- Declaration on Survey (legal) 28112023.pdf · uploaded 11 Dec 2023Source
  • Other – LegalP52100054077 · Mrunmai BR- Statutory.pdf · uploaded 19 Dec 2023Source
  • Legal Title reportP52100053177 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Legal Title reportP52100054077 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Legal Title reportP52100052683 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Legal Title reportP52100053978 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Legal Title reportP52100053927 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Legal Title reportP52100053966 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • Other – LegalP52100053177 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053177 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100054077 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100054077 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100052683 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100052683 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053978 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053978 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053927 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053927 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053966 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • Other – LegalP52100053966 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • Declaration Form BP52100053966 · MTV T4- Form B Affidavit- 31 Mar 2029.pdf · uploaded 28 Feb 2025Source
  • OthersP52100054077 · Annex F- T3- Form B Affidavit.pdf · uploaded 5 Sep 2025Source

Migrated

  • 1 PAN CardP52100054077 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Jul 2023Source
  • 1 Declaration in FORM BP52100054077 · MTV Tower 3- Form B.pdf · uploaded 14 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100054077 · Mrunmai- Director Declarations.pdf · uploaded 14 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100054077 · Layout- BP (reduced).pdf · uploaded 11 Aug 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100054077 · Layout- IOD (reduced).pdf · uploaded 11 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100054077 · T2 T3- FLoor Plan.pdf · uploaded 11 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100054077 · T3 Section Plan.pdf · uploaded 11 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100054077 · CC.pdf · uploaded 11 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · MTV Tower 3- CA Certificate.pdf · uploaded 11 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100054077 · Tower 3- Declaration for Separate Bank Account.pdf · uploaded 11 Aug 2023Source
  • 1 PAN CardP52100052683 · Mrunmai PAN Card-LTD.pdf · uploaded 11 Aug 2023Source
  • 1 Copy of the legal title reportP52100052683 · Title Report- Part 1.pdf · uploaded 11 Aug 2023Source
  • 2 Copy of the legal title reportP52100052683 · Title Report- Part 2.pdf · uploaded 11 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100052683 · T1- Legal Encumbrance.pdf · uploaded 11 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100052683 · T1- Legal Encumbrance.pdf · uploaded 11 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100052683 · Layout- BP (reduced).pdf · uploaded 11 Aug 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100052683 · Layout- IOD (reduced).pdf · uploaded 11 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100052683 · T1- Floor Plan (reduced).pdf · uploaded 11 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100052683 · T1 Section Plan.pdf · uploaded 11 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100052683 · CC.pdf · uploaded 11 Aug 2023Source
  • 1 Declaration about Commencement CertificateP52100052683 · MTV Tower 1- Declaration about CC.pdf · uploaded 11 Aug 2023Source
  • 1 Declaration in FORM BP52100052683 · MTV Tower 1- Affidavit (Form B).pdf · uploaded 11 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100052683 · Mrunmai- Director Declarations.pdf · uploaded 11 Aug 2023Source
  • 1 Proforma of Allotment letterP52100052683 · T1- Draft Allotment Letter.pdf · uploaded 11 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100052683 · T1- Deviation Report Letter of Allotment.pdf · uploaded 11 Aug 2023Source
  • 1 PAN CardP52100053177 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100053177 · T2- Financial Encumbrance.pdf · uploaded 14 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100053177 · T2- Financial Encumbrance.pdf · uploaded 14 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100053177 · Layout- BP (reduced).pdf · uploaded 14 Aug 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100053177 · Layout- IOD (reduced).pdf · uploaded 14 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100053177 · T2 Floor Plan (reduced).pdf · uploaded 14 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100053177 · T2 Section Plan.pdf · uploaded 14 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100053177 · MTV- Commencement Certificate.pdf · uploaded 14 Aug 2023Source
  • 1 Declaration about Commencement CertificateP52100053177 · MTV Tower 2- Declaration about CC.pdf · uploaded 14 Aug 2023Source
  • 1 Declaration in FORM BP52100053177 · MTV Tower 2- Form B.pdf · uploaded 14 Aug 2023Source
  • 1 CERSAI detailsP52100053177 · CERSAI_Search_Report_Aug 23.pdf · uploaded 14 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · MTV Tower 2- CA Certificate_signed.pdf · uploaded 14 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100053177 · Mrunmai- Director Declarations.pdf · uploaded 14 Aug 2023Source
  • 1 Proforma of Agreement for saleP52100053177 · Tower 2- Draft AFS.pdf · uploaded 14 Aug 2023Source
  • 1 Proforma of Allotment letterP52100053177 · Tower 2- Draft Allotment Letter.pdf · uploaded 14 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100053177 · Tower 2- Deviation Report to Allotment Letter.pdf · uploaded 14 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100053177 · Tower 2- Deviation Report to AFS.pdf · uploaded 14 Aug 2023Source
  • 1 PAN CardP52100053966 · Mrunmai PAN Card-LTD.pdf · uploaded 14 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100053966 · Layout- BP (reduced).pdf · uploaded 14 Aug 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100053966 · Layout- IOD (reduced).pdf · uploaded 14 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100053966 · T4 Floor Plan (reduced).pdf · uploaded 14 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100053966 · T4 Section Plan.pdf · uploaded 14 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100053966 · MTV- Commencement Certificate.pdf · uploaded 14 Aug 2023Source
  • 1 Declaration in FORM BP52100053966 · MTV Tower 4- Form B.pdf · uploaded 14 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · MTV Tower 4- CA Certificate.pdf · uploaded 14 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100053966 · Mrunmai- Director Declarations.pdf · uploaded 14 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100053966 · Tower 4- Declaration for Separate Bank Account.pdf · uploaded 14 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100053177 · Tower 2- Separate Bank Account Declaration (latest).pdf · uploaded 24 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · MTV Tower 1- CA Certificate- July 23.pdf · uploaded 24 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100052683 · Tower 1- Separate Bank Account Declaration (latest).pdf · uploaded 24 Aug 2023Source
  • 1 Proforma of Agreement for saleP52100052683 · T1- Draft AFS.pdf · uploaded 29 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100052683 · T1- Deviation Report for AFS.pdf · uploaded 29 Aug 2023Source
  • 1 Other – TechnicalP52100052683 · PMRDA Mail and CC MTV.pdf · uploaded 29 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100052683 · MTV Tower 1- Declaration about CC (revised).pdf · uploaded 12 Sep 2023Source
  • 2 Other – TechnicalP52100052683 · MTV T1- Declaration on Survey.pdf · uploaded 12 Sep 2023Source
  • 3 Other – TechnicalP52100052683 · Annexure 1.pdf · uploaded 12 Sep 2023Source
  • 4 Other – TechnicalP52100052683 · Annexure 2.pdf · uploaded 12 Sep 2023Source
  • 5 Other – TechnicalP52100052683 · Annexure 3 (updated).pdf · uploaded 13 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100052683 · T1- Financial Encumbrance.pdf · uploaded 14 Sep 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100052683 · T1- Financial Encumbrance.pdf · uploaded 14 Sep 2023Source
  • 1 CERSAI detailsP52100052683 · T1- Declaration and CERSAI Report.pdf · uploaded 14 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100053177 · T2- Legal Encumbrance (revised)_signed.pdf · uploaded 9 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100053177 · T2- Legal Encumbrance (revised)_signed.pdf · uploaded 9 Oct 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100053177 · MTV Tower 2- CC Declaration (revised)_signed.pdf · uploaded 9 Oct 2023Source
  • 1 Other – LegalP52100053177 · MTV T2- Declaration on Survey (legal)_signed.pdf · uploaded 9 Oct 2023Source
  • 1 Other – TechnicalP52100053177 · MTV T2- Declaration on Survey_signed.pdf · uploaded 9 Oct 2023Source
  • 2 Other – TechnicalP52100053177 · Annexure 1.pdf · uploaded 9 Oct 2023Source
  • 3 Other – TechnicalP52100053177 · Annexure 2.pdf · uploaded 9 Oct 2023Source
  • 4 Other – TechnicalP52100053177 · Annexure 3.pdf · uploaded 9 Oct 2023Source
  • 1 Copy of the legal title reportP52100053177 · Part 1.pdf · uploaded 10 Oct 2023Source
  • 2 Copy of the legal title reportP52100053177 · Part 2.pdf · uploaded 10 Oct 2023Source
  • 3 a Details of encumbrances concerned to FinanceP52100053177 · T2- Financial Encumbrance.pdf · uploaded 11 Oct 2023Source
  • 3 b Details of encumbrances concerned to LegalP52100053177 · T2- Financial Encumbrance.pdf · uploaded 11 Oct 2023Source
  • 2 CERSAI detailsP52100053177 · T2- CERSAI Declaration and Report.pdf · uploaded 11 Oct 2023Source
  • 1 Copy of the legal title reportP52100054077 · Part 1.pdf · uploaded 18 Oct 2023Source
  • 2 Copy of the legal title reportP52100054077 · Part 2.pdf · uploaded 18 Oct 2023Source
  • 1 Declaration about Commencement CertificateP52100054077 · MTV Tower 3- CC Declaration (revised)_signed.pdf · uploaded 18 Oct 2023Source
  • 1 Other – TechnicalP52100054077 · T3- Declaration on Survey (technical)_signed.pdf · uploaded 18 Oct 2023Source
  • 2 Other – TechnicalP52100054077 · Annexure 1.pdf · uploaded 18 Oct 2023Source
  • 3 Other – TechnicalP52100054077 · Annexure 2.pdf · uploaded 18 Oct 2023Source
  • 4 Other – TechnicalP52100054077 · Annexure 3.pdf · uploaded 18 Oct 2023Source
  • 1 Copy of the legal title reportP52100053966 · Part 1.pdf · uploaded 18 Oct 2023Source
  • 2 Copy of the legal title reportP52100053966 · Part 2.pdf · uploaded 18 Oct 2023Source
  • 1 Declaration about Commencement CertificateP52100053966 · MTV Tower 4- CC Declaration (revised)_signed.pdf · uploaded 18 Oct 2023Source
  • 1 Other – TechnicalP52100053966 · T4- Declaration on Survey (technical)_signed.pdf · uploaded 18 Oct 2023Source
  • 2 Other – TechnicalP52100053966 · Annexure 1.pdf · uploaded 18 Oct 2023Source
  • 3 Other – TechnicalP52100053966 · Annexure 2.pdf · uploaded 18 Oct 2023Source
  • 4 Other – TechnicalP52100053966 · Annexure 3.pdf · uploaded 18 Oct 2023Source
  • 1 PAN CardP52100053978 · PAN Card- Mrunmai.pdf · uploaded 31 Oct 2023Source
  • 1 Copy of the legal title reportP52100053978 · Part 1.pdf · uploaded 31 Oct 2023Source
  • 2 Copy of the legal title reportP52100053978 · Part 2.pdf · uploaded 31 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100053978 · Layout- BP (reduced).pdf · uploaded 31 Oct 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100053978 · Layout- IOD (reduced).pdf · uploaded 31 Oct 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100053978 · MTV- Commencement Certificate.pdf · uploaded 31 Oct 2023Source
  • 1 Declaration in FORM BP52100053978 · Villa Phase 1- Form B.pdf · uploaded 31 Oct 2023Source
  • 1 CERSAI detailsP52100053978 · CERSAI Report - 26th Oct.pdf · uploaded 31 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100053978 · Mrunmai- Director Declarations.pdf · uploaded 31 Oct 2023Source
  • 1 PAN CardP52100053927 · PAN Card- Mrunmai.pdf · uploaded 31 Oct 2023Source
  • 1 Copy of the legal title reportP52100053927 · Part 1.pdf · uploaded 31 Oct 2023Source
  • 2 Copy of the legal title reportP52100053927 · Part 2.pdf · uploaded 31 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100053927 · Layout- BP (reduced).pdf · uploaded 31 Oct 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100053927 · Layout- IOD (reduced).pdf · uploaded 31 Oct 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100053927 · Row House Plan.pdf · uploaded 31 Oct 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100053927 · MTV- Commencement Certificate.pdf · uploaded 31 Oct 2023Source
  • 1 CERSAI detailsP52100053927 · CERSAI Report - 26th Oct.pdf · uploaded 31 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100053927 · Mrunmai- Director Declarations.pdf · uploaded 31 Oct 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100053978 · V1- Mrunmai- Financial Encumbrance.pdf · uploaded 2 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100053978 · V1- Mrunmai- Financial Encumbrance.pdf · uploaded 2 Nov 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100053978 · Row House Plan.pdf · uploaded 2 Nov 2023Source
  • 1 Declaration about Commencement CertificateP52100053978 · V1- CC Declaration.pdf · uploaded 2 Nov 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa Phase 1- Form 3- June 23.pdf · uploaded 2 Nov 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100053978 · V1- Deviation Report for Allotment Letter.pdf · uploaded 2 Nov 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100053978 · V1- Deviation Report for AFS.pdf · uploaded 2 Nov 2023Source
  • 1 Other – TechnicalP52100053978 · V1- Declaration on Survey (technical).pdf · uploaded 2 Nov 2023Source
  • 2 Other – TechnicalP52100053978 · Annexure 1.pdf · uploaded 2 Nov 2023Source
  • 3 Other – TechnicalP52100053978 · Annexure 2.pdf · uploaded 2 Nov 2023Source
  • 4 Other – TechnicalP52100053978 · Villa 1- Annexure 3.pdf · uploaded 2 Nov 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100053927 · V2- Mrunmai- Financial Encumbrance.pdf · uploaded 2 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100053927 · V2- Mrunmai- Financial Encumbrance.pdf · uploaded 2 Nov 2023Source
  • 1 Declaration about Commencement CertificateP52100053927 · V2- CC Declaration.pdf · uploaded 2 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100053927 · V2- Declaration for Separate Bank Account.pdf · uploaded 2 Nov 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100053927 · V2- Deviation Report for AFS.pdf · uploaded 2 Nov 2023Source
  • 1 Other – TechnicalP52100053927 · V2- Declaration on Survey (technical).pdf · uploaded 2 Nov 2023Source
  • 2 Other – TechnicalP52100053927 · Annexure 1.pdf · uploaded 2 Nov 2023Source
  • 3 Other – TechnicalP52100053927 · Annexure 2.pdf · uploaded 2 Nov 2023Source
  • 4 Other – TechnicalP52100053927 · Villa 2- Annexure 3.pdf · uploaded 2 Nov 2023Source
  • 1 Proforma of Agreement for saleP52100053978 · Draft AFS- Villa Phase 1.pdf · uploaded 3 Nov 2023Source
  • 1 Proforma of Allotment letterP52100053978 · Draft Allotment Letter- Villa Phase 1.pdf · uploaded 3 Nov 2023Source
  • 1 Proforma of Agreement for saleP52100053927 · Draft AFS- Villa Phase 2.pdf · uploaded 3 Nov 2023Source
  • 1 Declaration in FORM BP52100053927 · Villa Phase 2- Form B.pdf · uploaded 4 Nov 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100053966 · T4- Financial Encumbrance (revised).pdf · uploaded 9 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100053966 · T4- Financial Encumbrance (revised).pdf · uploaded 9 Nov 2023Source
  • 1 Other – LegalP52100053966 · NCLT Certified Order- 17th Feb 2020.pdf · uploaded 9 Nov 2023Source
  • 2 Other – LegalP52100053966 · Mrunmai- Palchin Scheme.pdf · uploaded 9 Nov 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100054077 · T3- Financial Encumbrance (revised)_signed.pdf · uploaded 13 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100054077 · T3- Financial Encumbrance (revised)_signed.pdf · uploaded 13 Nov 2023Source
  • 1 Other – LegalP52100054077 · NCLT Certified Order- 17th Feb 2020.pdf · uploaded 13 Nov 2023Source
  • 2 Other – LegalP52100054077 · Mrunmai- Palchin Scheme.pdf · uploaded 13 Nov 2023Source
  • 1 CERSAI detailsP52100053966 · CERSAI Report - 26th Oct.pdf · uploaded 17 Nov 2023Source
  • 1 CERSAI detailsP52100054077 · CERSAI Report - 26th Oct.pdf · uploaded 20 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100054077 · T3- Mrunmai- Legal Encumbrance 28112023.pdf · uploaded 28 Nov 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100054077 · T3- Mrunmai- Legal Encumbrance 28112023.pdf · uploaded 28 Nov 2023Source
  • 2 CERSAI detailsP52100054077 · T3- CERSAI Declaration 28112023.pdf · uploaded 28 Nov 2023Source
  • 1 Proforma of Agreement for saleP52100054077 · T3- AFS 21112023.pdf · uploaded 28 Nov 2023Source
  • 1 Proforma of Allotment letterP52100054077 · T3- Allotment Letter 21112023.pdf · uploaded 28 Nov 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100054077 · T3- Deviation Report for Allotment Letter 21112023.pdf · uploaded 28 Nov 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100054077 · T3- Deviation Report for AFS 21112023.pdf · uploaded 28 Nov 2023Source
  • 3 Other – LegalP52100054077 · NCLT Order dtd 10th July 2023.pdf · uploaded 28 Nov 2023Source
  • 4 Other – LegalP52100054077 · Part 1.pdf · uploaded 28 Nov 2023Source
  • 5 Other – LegalP52100054077 · Part 2.pdf · uploaded 28 Nov 2023Source
  • 6 Other – LegalP52100054077 · Part 3.pdf · uploaded 28 Nov 2023Source
  • 7 Other – LegalP52100054077 · T3- Declaration for 2012 Demerger.pdf · uploaded 28 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100053978 · V1- Mrunmai- Legal Encumbrance 04122023.pdf · uploaded 4 Dec 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100053978 · V1- Mrunmai- Legal Encumbrance 04122023.pdf · uploaded 4 Dec 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100053978 · V1- Declaration for Separate Bank Account 04122023.pdf · uploaded 4 Dec 2023Source
  • 1 Other – LegalP52100053978 · V1- Declaration on Survey (legal) 04122023.pdf · uploaded 4 Dec 2023Source
  • 2 Other – LegalP52100053978 · NCLT Order dtd 10th July 2023.pdf · uploaded 4 Dec 2023Source
  • 3 Other – LegalP52100053978 · Villa 1- Declaration for 2012 Demerger.pdf · uploaded 4 Dec 2023Source
  • 4 Other – LegalP52100053978 · Part 1.pdf · uploaded 4 Dec 2023Source
  • 5 Other – LegalP52100053978 · Part 2.pdf · uploaded 4 Dec 2023Source
  • 6 Other – LegalP52100053978 · Part 3.pdf · uploaded 4 Dec 2023Source
  • 7 Other – LegalP52100053978 · (1) Mrunmai- Palchin Scheme.pdf · uploaded 4 Dec 2023Source
  • 8 Other – LegalP52100053978 · (2) NCLT Order- 17th Feb 2020.pdf · uploaded 4 Dec 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100053927 · V2- Mrunmai- Legal Encumbrance 04122023.pdf · uploaded 4 Dec 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100053927 · V2- Mrunmai- Legal Encumbrance 04122023.pdf · uploaded 4 Dec 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa Phase 2- Form 3- Oct 23.pdf · uploaded 4 Dec 2023Source
  • 1 Proforma of Allotment letterP52100053927 · Draft Allotment letter Villa Phase 2 (21112023).pdf · uploaded 4 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100053927 · Deviation Report- Allotment Letter- Villas Phase 2 (21112023).pdf · uploaded 4 Dec 2023Source
  • 1 Other – LegalP52100053927 · V2- Declaration on Survey (legal) 04122023.pdf · uploaded 4 Dec 2023Source
  • 2 Other – LegalP52100053927 · (2) NCLT Order- 17th Feb 2020.pdf · uploaded 4 Dec 2023Source
  • 3 Other – LegalP52100053927 · (1) Mrunmai- Palchin Scheme.pdf · uploaded 4 Dec 2023Source
  • 4 Other – LegalP52100053927 · (3) NCLT Order dtd 10th July 2023.pdf · uploaded 4 Dec 2023Source
  • 5 Other – LegalP52100053927 · Villa 2- Declaration for 2012 Demerger.pdf · uploaded 4 Dec 2023Source
  • 6 Other – LegalP52100053927 · Part 1.pdf · uploaded 4 Dec 2023Source
  • 7 Other – LegalP52100053927 · Part 2.pdf · uploaded 4 Dec 2023Source
  • 8 Other – LegalP52100053927 · Part 3.pdf · uploaded 4 Dec 2023Source
  • 1 Other – FinanceP52100053927 · V2- Declaration for Separate Bank Account 04122023.pdf · uploaded 4 Dec 2023Source
  • 5 Other – TechnicalP52100053927 · Mrunmai BR- Statutory.pdf · uploaded 8 Dec 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100053966 · T4- Mrunmai- Legal Encumbrance 08122023.pdf · uploaded 8 Dec 2023Source
  • 2 b Details of encumbrances concerned to LegalP52100053966 · T4- Mrunmai- Legal Encumbrance 08122023.pdf · uploaded 8 Dec 2023Source
  • 2 CERSAI detailsP52100053966 · T4- CERSAI Declaration 08122023.pdf · uploaded 8 Dec 2023Source
  • 1 Proforma of Agreement for saleP52100053966 · T4- Draft AFS 28-11-2023.pdf · uploaded 8 Dec 2023Source
  • 1 Proforma of Allotment letterP52100053966 · T4- Draft Allotment letter 28-11-2023.pdf · uploaded 8 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100053966 · T4- Deviation Report Letter of Allotment 30-11-2023.pdf · uploaded 8 Dec 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100053966 · T4- Deviation Report AFS 30-11-2023.pdf · uploaded 8 Dec 2023Source
  • 3 Other – LegalP52100053966 · (3) NCLT Order dtd 10th July 2023.pdf · uploaded 8 Dec 2023Source
  • 4 Other – LegalP52100053966 · T4- Declaration for 2012 Demerger.pdf · uploaded 8 Dec 2023Source
  • 5 Other – LegalP52100053966 · Part 1.pdf · uploaded 8 Dec 2023Source
  • 6 Other – LegalP52100053966 · Part 2.pdf · uploaded 8 Dec 2023Source
  • 7 Other – LegalP52100053966 · Part 3.pdf · uploaded 8 Dec 2023Source
  • 8 Other – LegalP52100053966 · T4- Declaration on Survey (legal) 08122023.pdf · uploaded 8 Dec 2023Source
  • 5 Other – TechnicalP52100053966 · Mrunmai BR- Statutory.pdf · uploaded 8 Dec 2023Source
  • 8 Other – LegalP52100054077 · T3- Declaration on Survey (legal) 28112023.pdf · uploaded 11 Dec 2023Source
  • 5 Other – TechnicalP52100053978 · Mrunmai BR- Statutory.pdf · uploaded 11 Dec 2023Source
  • 9 Other – LegalP52100054077 · Mrunmai BR- Statutory.pdf · uploaded 19 Dec 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- No Progress Declaration- Sept'23_signed.pdf · uploaded 6 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- Form 1- Dec 2023_signed.pdf · uploaded 6 Feb 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- No Progress Declaration- Dec'23_Signed.pdf · uploaded 6 Feb 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · T1- No Progress Declaration- Sept'23_signed.pdf · uploaded 6 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · T1- Form 2- Dec 2023_signed.pdf · uploaded 6 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · T1- No Withdrawals- Sept 2023_signed.pdf · uploaded 6 Feb 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · T1- No Withdrawals- Dec 2023_signed.pdf · uploaded 6 Feb 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Form 1- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Physical Progress Declaration- Dec'23.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053177 · T2- Form 2- Dec 2023.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · T2- No Withdrawals- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054077 · T3- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawals- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · Villa 1- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawals- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053927 · Villa 2- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawals- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053966 · T4- No Progress Declaration- Dec'23_signed.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- No Withdrawals- Dec 2023_signed.pdf · uploaded 12 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Form 1- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053177 · T2- Form 2- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100053177 · T2- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100053177 · Tower 2- Inventory Report- 25 Apr 2024.pdf · uploaded 25 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054077 · T3- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100054077 · T3- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawals- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- Form 1- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · T1- Form 2- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100052683 · T1- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100052683 · Tower 1- Inventory Report- 25 Apr 2024.pdf · uploaded 25 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · Villa 1- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100053978 · Villa 1- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawals- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053927 · Villa 2- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100053927 · Villa 2- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawals- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053966 · T4- Physical Progress Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100053966 · T4- Form 2A Declaration- Mar'24.pdf · uploaded 25 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- No Withdrawals- Mar 2024.pdf · uploaded 25 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · T2- Form 3- March 2024.pdf · uploaded 27 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · T1- Form 3- March 2024.pdf · uploaded 27 Jun 2024Source
  • 2 PAN CardP52100053177 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 2 PAN CardP52100054077 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 2 PAN CardP52100052683 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 2 PAN CardP52100053978 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 2 PAN CardP52100053927 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 2 PAN CardP52100053966 · Palchin PAN.pdf · uploaded 26 Jul 2024Source
  • 3 Copy of the legal title reportP52100053177 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Copy of the legal title reportP52100054077 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Copy of the legal title reportP52100052683 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Copy of the legal title reportP52100053978 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Copy of the legal title reportP52100053927 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Copy of the legal title reportP52100053966 · Palchin- Title Report (MTV Project).pdf · uploaded 6 Aug 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · MTV Villa 2- Form 1- June 2024.pdf · uploaded 13 Aug 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · MTV Villa 2- Physical Progress- June 2024.pdf · uploaded 13 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053927 · MTV Villa 2- Form 2- June 2024.pdf · uploaded 13 Aug 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100053927 · MTV Villa 2- Inventory Report- June 2024.pdf · uploaded 13 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · MTV Villa 2- Form 3- June 2024 (reduced).pdf · uploaded 13 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · MTV Villa 2- No Withdrawals- June 2024.pdf · uploaded 13 Aug 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · MTV T4- Form 1- June 2024.pdf · uploaded 13 Aug 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · MTV T4- Physical Progress- June 2024.pdf · uploaded 13 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053966 · MTV T4- Form 2- June 2024.pdf · uploaded 13 Aug 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100053966 · MTV T4- Inventory Report- June 2024.pdf · uploaded 13 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · MTV T4- Form 3- June 2024 (reduced).pdf · uploaded 13 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · MTV T4- No Withdrawals- June 2024.pdf · uploaded 13 Aug 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · MTV T2- Form 1- June 2024.pdf · uploaded 14 Aug 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · MTV T2- Physical Progress- June 2024.pdf · uploaded 14 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053177 · MTV T2- Form 2- June 2024.pdf · uploaded 14 Aug 2024Source
  • 2 Disclosure of sold/ booked inventoryP52100053177 · MTV T2- Inventory Report- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · MTV T2- Form 3- June 2024 (reduced).pdf · uploaded 14 Aug 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · MTV T3- Form 1- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · MTV T3- Physical Progress- June 2024.pdf · uploaded 14 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054077 · MTV T3- Form 2- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · MTV T3- Form 3- June 2024 (reduced).pdf · uploaded 14 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · MTV T3- No Withdrawals- June 2024.pdf · uploaded 14 Aug 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · MTV T1- Form 1- June 2024.pdf · uploaded 14 Aug 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · MTV T1- Physical Progress- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · MTV T1- Form 2- June 2024.pdf · uploaded 14 Aug 2024Source
  • 2 Disclosure of sold/ booked inventoryP52100052683 · MTV T1- Inventory Report- June 2024.pdf · uploaded 14 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · MTV T1- Form 3- June 2024 (reduced).pdf · uploaded 14 Aug 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · MTV Villa 1- Form 1- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · MTV Villa 1- Form 1- June 2024.pdf · uploaded 14 Aug 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · MTV Villa 1- Physical Progress- June 2024.pdf · uploaded 14 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · MTV Villa 1- Form 2- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · MTV Villa 1- Form 2- June 2024.pdf · uploaded 14 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · MTV Villa 1- Form 3- June 2024 (reduced).pdf · uploaded 14 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · MTV Villa 1- No Withdrawals- June 2024.pdf · uploaded 14 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100053177 · AFS Mrunmai Palchin T2 (for RERA) 04-07-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100053177 · Allotment letter T2 Palchin (for RERA) 04-07-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Other – LegalP52100053177 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 3 Other – LegalP52100053177 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100054077 · Allotment letter T3 Palchin (for RERA) 21-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100054077 · AFS Mrunmai T3 Palchin (for RERA) 21-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 10 Other – LegalP52100054077 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 11 Other – LegalP52100054077 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100052683 · AFS Mrunmai Palchin T1 (for RERA) 20-09-2023 dt 20-08-2024.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100052683 · Allotment letter T1 Palchin (for RERA) 24-06-2023 dt 20-08-2024.pdf · uploaded 20 Aug 2024Source
  • 1 Other – LegalP52100052683 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 2 Other – LegalP52100052683 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100053978 · AFS Mrunmai Villa Phase 1 (for RERA) 19-12-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100053978 · Allotment letter Villa Phase 1(for RERA) 21-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 9 Other – LegalP52100053978 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 10 Other – LegalP52100053978 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100053927 · AFS Mrunmai Villa 2 (for RERA) 19-12-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100053927 · Allotment letter Villa 2 (for RERA) 21-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 9 Other – LegalP52100053927 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 10 Other – LegalP52100053927 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Agreement for saleP52100053966 · AFS Mrunmai T4 (for RERA) 28-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 2 Proforma of Allotment letterP52100053966 · Allotment letter T4 (for RERA) 28-11-2023 (20-08-2024).pdf · uploaded 20 Aug 2024Source
  • 9 Other – LegalP52100053966 · Palchin Regd Scheme Part 1.pdf · uploaded 20 Aug 2024Source
  • 10 Other – LegalP52100053966 · Palchin Regd Scheme Part 2.pdf · uploaded 20 Aug 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100053177 · MTV T2- Inventory Report.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100053177 · T2- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawal- Sept 2024.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawal- Dec 2024.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100054077 · T3- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100052683 · MTV T1- Inventory Report.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100052683 · T1- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawal- Sept 2024.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawal- Dec 2024.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100053978 · Villa 1- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawal- Sept 2024.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawal- Dec 2024.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100053927 · Villa 2- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- No Withdrawal- Sept 2024.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- No Withdrawal- Dec 2024.pdf · uploaded 20 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100053966 · T4- Form 5- FY 23-24.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- PPR- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- Form 1- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- PPR- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053966 · T4- Form 1- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- Form 3- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053966 · T4- Form 3- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053966 · T4- Form 2- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053966 · T4- Form 2- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053177 · T2- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · T2- Form 3- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053177 · T2- Form 3- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053177 · T2- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053177 · T2- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054077 · T3- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawal- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- Form 3- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- No Withdrawal- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054077 · T3- Form 3- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054077 · T3- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054077 · T3- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100052683 · T1- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · T1- Form 3- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100052683 · T1- Form 3- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · T1- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100052683 · T1- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053978 · Villa 1- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawal- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- Form 3- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- No Withdrawal- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053978 · Villa 1- Form 3- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · Villa 1- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053978 · Villa 1- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100053927 · Villa 2- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawal- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- Form 3- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- No Withdrawal- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100053927 · Villa 2- Form 3- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053927 · Villa 2- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100053927 · Villa 2- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • 1 Declaration in FORM BP52100053966 · MTV T4- Form B Affidavit- 31 Mar 2029.pdf · uploaded 28 Feb 2025Source
  • Form 1P52100054077 · T3- Form 1- March 2025.pdf · uploaded 4 Sep 2025Source
  • Form 2P52100054077 · T3- Form 2- March 2025.pdf · uploaded 4 Sep 2025Source
  • Form 3P52100054077 · T3- Form 3- March 2025.pdf · uploaded 4 Sep 2025Source
  • Disclosure of Sold and Booked InventoryP52100054077 · MTV T3- Inventory Report.pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 1P52100054077 · T3- Form 1- June 2025.pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 1P52100054077 · T3- Form 1- June 2025.pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 2P52100054077 · T3- Form 2- June 2025.pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 2P52100054077 · T3- Form 2- June 2025.pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 3P52100054077 · T3- Form 3- June 2025 (reduced).pdf · uploaded 4 Sep 2025Source
  • Withdrawal Update Form 3P52100054077 · T3- Form 3- June 2025 (reduced).pdf · uploaded 4 Sep 2025Source
  • Form 2A (FY 2024-2025)P52100054077 · T3- Form 2A- March 2025.pdf · uploaded 5 Sep 2025Source
  • Form 5 (FY 2024-2025)P52100054077 · Tower 3- Form 5- FY 24-25 (signed).pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1P52100053978 · Villa 1- Form 1- June 2025.pdf · uploaded 15 Feb 2026Source
  • Withdrawal Update Form 2P52100053978 · Villa 1- Form 2- June 2025.pdf · uploaded 15 Feb 2026Source
  • Withdrawal Update Form 3P52100053978 · Villa 1- Form 3- June 2025.pdf · uploaded 15 Feb 2026Source
  • Form 2A (FY 2024-2025)P52100053978 · Villa 1- Form 2A- March 2025.pdf · uploaded 15 Feb 2026Source
  • Withdrawal Update Form 1P52100053978 · Villa 1- Form 1- Sept 2025.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 1P52100053978 · Villa 1- Form 1- Dec 2025.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 2P52100053978 · Villa 1- Form 2- Sept 2025.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 2P52100053978 · Villa 1- Form 2- Dec 2025.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3P52100053978 · FORM3_VILLA Phase1_Sept-25.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3P52100053978 · Villa 1- Form 3- Dec 2025.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 1P52100053927 · Villa 2- Form 1- Dec 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 1P52100053927 · Villa 2- Form 1- June 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 1P52100053927 · Villa 2- Form 1- Sept 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 2P52100053927 · Villa 2- Form 2- Dec 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 2P52100053927 · Villa 2- Form 2- June 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 2P52100053927 · Villa 2- Form 2- Sept 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 3P52100053927 · Villa 2- Form 3- Dec 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 3P52100053927 · Villa 2- Form 3- June 2025.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 3P52100053927 · FORM3_VILLA Phase2_Sept-25.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 1P52100052683 · T1- Form 1- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100052683 · T1- Form 1- Sept 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100052683 · T1- Form 1- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100052683 · T1- Form 2- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100052683 · T1- Form 2- Sept 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100052683 · T1- Form 2- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100052683 · T1- Form 3- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100052683 · FORM3_T1_Sept-25.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100052683 · T1- Form 3- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100053966 · T4- Form 1- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100053966 · T4- Form 1- Sept 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100053966 · T4- Form 1- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100053966 · T4- Form 2- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100053966 · T4- Form 2- Sept 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2P52100053966 · T4- Form 2- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100053966 · T4- Form 3- June 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100053966 · FORM3_T4_Sept-25.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3P52100053966 · T4- Form 3- Dec 2025.pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1P52100053177 · T2- Form 1- June 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1P52100053177 · T2- Form 1- Sept 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1P52100053177 · T2- Form 1- Dec 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2P52100053177 · T2- Form 2- June 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2P52100053177 · T2- Form 2- Sept 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 2P52100053177 · T2- Form 2- Sept 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3P52100053177 · T2- Form 3- June 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3P52100053177 · FORM3_T2_Sept-25.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 3P52100053177 · T2- Form 3- Dec 2025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1P52100054077 · T3- Form 1- Sept 2025.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 1P52100054077 · T3- Form 1- Dec 2025.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 2P52100054077 · T3- Form 2- Sept 2025.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 2P52100054077 · T3- Form 2- Sept 2025.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 3P52100054077 · FORM3_T3_Sept-25.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 3P52100054077 · T3- Form 3- Dec 2025.pdf · uploaded 22 Feb 2026Source
  • Withdrawal Update Form 1P52100052683 · Tower 1- Form 1- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 2P52100052683 · Tower 1- Form 2- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 3P52100052683 · 202603 RERA Certificate MTV Tower 1 - RERA.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 1P52100053978 · Villa Phase 1- Form 1- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 2P52100053978 · Villa 1- Form 2- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 3P52100053978 · 202603 RERA Certificate MTV Villa Phase 1 - RERA.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 1P52100053927 · Villa Phase 2- Form 1- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 2P52100053927 · Villa 2- Form 2- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 3P52100053927 · 202603 RERA Certificate MTV Villa Phase 2 - RERA.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 1P52100053966 · Tower 4- Form 1- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 2P52100053966 · Tower 4- Form 2- March 2026.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 3P52100053966 · 202603 RERA Certificate MTV Tower 4 - RERA.pdf · uploaded 28 May 2026Source
  • Withdrawal Update Form 1P52100054077 · Tower 3- Form 1- March 2026.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 2P52100054077 · Tower 3- Form 2- March 2026.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 3P52100054077 · Form 3- MTV Tower 3- RERA.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 1P52100053177 · Tower 2- Form 1- March 2026.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 2P52100053177 · Tower 2- Form 2- March 2026.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 3P52100053177 · 202603 RERA Certificate MTV Tower 2 - RERA.pdf · uploaded 3 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100053177 · T2- Form 2A- March 2025.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100053177 · Tower 2- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100054077 · Tower 3- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100052683 · T1- Form 2A- March 2025.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100052683 · Tower 1- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100053978 · Villa 1- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100053927 · Villa 2- Form 2A- March 2025.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100053927 · Villa 2- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100053966 · T4- Form 2A- March 2025.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100053966 · Tower 4- Form 2A (FY 25-26).pdf · uploaded 29 Jun 2026Source
  • Form 5 (FY 2024-2025)P52100053177 · T2- Form 5- FY 24-25.pdf · uploaded 30 Jun 2026Source
  • Form 5 (FY 2024-2025)P52100052683 · T1- Form 5- FY 24-25.pdf · uploaded 30 Jun 2026Source
  • Form 5 (FY 2024-2025)P52100053978 · Villa 1- Form 5- FY 24-25.pdf · uploaded 30 Jun 2026Source
  • Form 5 (FY 2024-2025)P52100053927 · Villa 2- Form 5- FY 24-25.pdf · uploaded 30 Jun 2026Source
  • Form 5 (FY 2024-2025)P52100053966 · T4- Form 5- FY 24-25.pdf · uploaded 30 Jun 2026Source
  • Disclosure of Sold and Booked InventoryP52100053177 · T2- Inventory Report- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 1P52100053177 · T2- Form 1- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 2P52100053177 · T2- Form 2- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 3P52100053177 · T2- Form 3- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 1P52100052683 · T1- Form 1- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 2P52100052683 · T1- Form 2- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 3P52100052683 · T1- Form 3- March 2025.pdf · uploaded 3 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100052683 · T1- Inventory Report- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 1P52100053978 · Villa 1- Form 1- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 2P52100053978 · Villa 1- Form 2- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 3P52100053978 · Villa 1- Form 3- March 2025.pdf · uploaded 3 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100053978 · Villa 1- Inventory Report- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 1P52100053927 · Villa 2- Form 1- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 2P52100053927 · Villa 2- Form 2- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 3P52100053927 · Villa 2- Form 3- March 2025.pdf · uploaded 3 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100053927 · Villa 2- Inventory Report- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 1P52100053966 · T4- Form 1- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 2P52100053966 · T4- Form 2- March 2025.pdf · uploaded 3 Jul 2026Source
  • Form 3P52100053966 · T4- Form 3- March 2025.pdf · uploaded 3 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100053966 · T4- Inventory Report- March 2025.pdf · uploaded 3 Jul 2026Source
  • Withdrawal Update Form 1P52100053978 · Villa 1- Form 1- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2P52100053978 · Villa 1- Form 2- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3P52100053978 · Villa 1- Form 3- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 1P52100053927 · Villa 2- Form 1- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2P52100053927 · Villa 2- Form 2- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3P52100053927 · Villa 2- Form 3- June 2026.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 1P52100053177 · Tower 2- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 2P52100053177 · Tower 2- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 3P52100053177 · Tower 2- Form 3- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 1P52100054077 · Tower 3- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 2P52100054077 · Tower 3- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 3P52100054077 · Tower 3- Form 3- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 1P52100052683 · Tower 1- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 2P52100052683 · Tower 1- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 3P52100052683 · Tower 1- Form 3- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 1P52100053966 · Tower 4- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 2P52100053966 · Tower 4- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • Withdrawal Update Form 3P52100053966 · Tower 4- Form 3- June 2026.pdf · uploaded 15 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100053177 · MTV T2- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100054077 · MTV T3- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100052683 · MTV T1- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100053978 · MTV Villa 1- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100053927 · MTV Villa 2- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100053966 · MTV T4- Form 5- FY 25-26.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentP52100054077 · Layout- BP (reduced).pdf · uploaded 11 Aug 2023Source
  • DocumentP52100054077 · Layout- IOD (reduced).pdf · uploaded 11 Aug 2023Source
  • DocumentP52100054077 · T3 Section Plan.pdf · uploaded 11 Aug 2023Source
  • DocumentP52100054077 · T2 T3- FLoor Plan.pdf · uploaded 11 Aug 2023Source
  • DocumentP52100052683 · Layout- BP (reduced).pdf · uploaded 11 Aug 2023Source
  • DocumentP52100052683 · Layout- IOD (reduced).pdf · uploaded 11 Aug 2023Source
  • DocumentP52100052683 · T1- Floor Plan (reduced).pdf · uploaded 11 Aug 2023Source
  • DocumentP52100052683 · T1 Section Plan.pdf · uploaded 11 Aug 2023Source
  • DocumentP52100053177 · Layout- BP (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053177 · Layout- IOD (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053177 · T2 Floor Plan (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053177 · T2 Section Plan.pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053966 · Layout- BP (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053966 · Layout- IOD (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053966 · T4 Floor Plan (reduced).pdf · uploaded 14 Aug 2023Source
  • DocumentP52100053966 · T4 Section Plan.pdf · uploaded 14 Aug 2023Source
  • Other – TechnicalP52100052683 · PMRDA Mail and CC MTV.pdf · uploaded 29 Aug 2023Source
  • Other – TechnicalP52100052683 · MTV T1- Declaration on Survey.pdf · uploaded 12 Sep 2023Source
  • Other – TechnicalP52100052683 · Annexure 1.pdf · uploaded 12 Sep 2023Source
  • Other – TechnicalP52100052683 · Annexure 2.pdf · uploaded 12 Sep 2023Source
  • Other – TechnicalP52100052683 · Annexure 3 (updated).pdf · uploaded 13 Sep 2023Source
  • Other – TechnicalP52100053177 · MTV T2- Declaration on Survey_signed.pdf · uploaded 9 Oct 2023Source
  • Other – TechnicalP52100053177 · Annexure 1.pdf · uploaded 9 Oct 2023Source
  • Other – TechnicalP52100053177 · Annexure 2.pdf · uploaded 9 Oct 2023Source
  • Other – TechnicalP52100053177 · Annexure 3.pdf · uploaded 9 Oct 2023Source
  • Other – TechnicalP52100054077 · T3- Declaration on Survey (technical)_signed.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100054077 · Annexure 1.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100054077 · Annexure 2.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100054077 · Annexure 3.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100053966 · T4- Declaration on Survey (technical)_signed.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100053966 · Annexure 1.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100053966 · Annexure 2.pdf · uploaded 18 Oct 2023Source
  • Other – TechnicalP52100053966 · Annexure 3.pdf · uploaded 18 Oct 2023Source
  • DocumentP52100053978 · Layout- BP (reduced).pdf · uploaded 31 Oct 2023Source
  • DocumentP52100053978 · Layout- IOD (reduced).pdf · uploaded 31 Oct 2023Source
  • DocumentP52100053927 · Layout- BP (reduced).pdf · uploaded 31 Oct 2023Source
  • DocumentP52100053927 · Layout- IOD (reduced).pdf · uploaded 31 Oct 2023Source
  • DocumentP52100053927 · Row House Plan.pdf · uploaded 31 Oct 2023Source
  • DocumentP52100053978 · Row House Plan.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053978 · V1- Declaration on Survey (technical).pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053978 · Annexure 1.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053978 · Annexure 2.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053978 · Villa 1- Annexure 3.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053927 · Annexure 1.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053927 · Annexure 2.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053927 · Villa 2- Annexure 3.pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053927 · V2- Declaration on Survey (technical).pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalP52100053927 · Mrunmai BR- Statutory.pdf · uploaded 8 Dec 2023Source
  • Other – TechnicalP52100053966 · Mrunmai BR- Statutory.pdf · uploaded 8 Dec 2023Source
  • Other – TechnicalP52100053978 · Mrunmai BR- Statutory.pdf · uploaded 11 Dec 2023Source
  • DocumentP52100054077 · T3- Layout Highlighted.pdf · uploaded 29 May 2026Source
  • DocumentP52100054077 · T3- Elevation Plan.pdf · uploaded 29 May 2026Source
  • DocumentP52100054077 · T3- Floor Plan.pdf · uploaded 29 May 2026Source
  • DocumentP52100054077 · T3- Section.pdf · uploaded 29 May 2026Source
  • DocumentP52100053927 · Villa Phase 2 Plans_ S4.pdf · uploaded 29 May 2026Source
  • DocumentP52100053927 · Villa Phase 2_ S12.pdf · uploaded 29 May 2026Source
  • DocumentP52100053927 · Commencement Certificate.pdf · uploaded 29 May 2026Source
  • DocumentP52100053978 · Layout Plan (Highlighted).pdf · uploaded 29 Jul 2026Source
  • DocumentP52100053978 · Villa- Highlighted Plan.pdf · uploaded 29 Jul 2026Source

Technical (Architect)

  • DocumentP52100053966 · T4- PPR- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053966 · T4- Form 1- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053966 · T4- PPR- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053966 · T4- Form 1- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053177 · T2- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053177 · T2- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053177 · T2- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053177 · T2- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100054077 · T3- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100054077 · T3- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100054077 · T3- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- PPR- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- Form 1- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- PPR- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- Form 1- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 1- June 2026.pdf · uploaded 21 Jul 2026Source
  • DocumentP52100053927 · Villa 2- Form 1- June 2026.pdf · uploaded 21 Jul 2026Source
  • DocumentP52100053177 · Tower 2- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100054077 · Tower 3- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100052683 · Tower 1- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100053966 · Tower 4- Form 1- June 2026.pdf · uploaded 15 Sep 2026Source

Technical (Engineer)

  • DocumentP52100053966 · T4- Form 2- Sept 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053966 · T4- Form 2- Dec 2024.pdf · uploaded 6 Feb 2025Source
  • DocumentP52100053177 · T2- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053177 · T2- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100054077 · T3- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100054077 · T3- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100052683 · T1- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- Form 2- Sept 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053927 · Villa 2- Form 2- Dec 2024.pdf · uploaded 19 Feb 2025Source
  • DocumentP52100053978 · Villa 1- Form 2- June 2026.pdf · uploaded 21 Jul 2026Source
  • DocumentP52100053927 · Villa 2- Form 2- June 2026.pdf · uploaded 21 Jul 2026Source
  • DocumentP52100053177 · Tower 2- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100054077 · Tower 3- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100052683 · Tower 1- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source
  • DocumentP52100053966 · Tower 4- Form 2- June 2026.pdf · uploaded 15 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 11/1, 11/2A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
6
Unit types
4 BHK Villa, 3BHK, 3BHK Podium Garden, 4BHK, 4BHK Podium Garden, 3 BHK Podium Garden, 4 BHK Podium Garden317 units in all
Address
Survey Nos. 11/1, 11/2A, 11/2B, 11/2C, 11/2D/1, 11/2D/2, 12/4(P), 12/5, 13/1, 13/2A, 14, 15, 16 at Village Shewalwadi and Survey Nos. 70A, 71/A/2, 71/B, 71C/2, 71/1/1B, 71/A/1/1F & 71/A/1/1E at Village Manjri Budruk, Pune Solapur Road, ShewalewadiPIN 412307
Village
Shewalewadi, Haveli taluka
Land area for this project
2,866 sq m (30,853 sq ft)
Permissible built-up area
26,556 sq m (2,85,843 sq ft)
Sanctioned built-up area
13,278 sq m (1,42,921 sq ft)
Recreational open space
5,763 sq m (62,029 sq ft)
Designated bank account
85
Developed in phases
No
Also registered as
Mango Tree Villa Tower 3, Mango Tree Villa Tower 2, Mango Tree Villa Tower 1, Mango Tree Villa Tower 4, Mango Tree Villa Phase 1, Mango Tree Villa Phase 2

Survey, CTS, gat or plot numbers

11/111/2A11/2B11/2C11/2D/111/2D/212/4(P)12/513/113/2A141516 at71/1/1B71/A/1/1E at71/A/1/1F71/A/271/B71B71C/2Survey Nos. 11/1Survey Nos. 70A

Land as published on MahaRERA's project page

Survey Nos. 11/1, 11/2A, 11/2B, 11/2C, 11/2D/1, 11/2D/2, 12/4(P), 12/5, 13/1, 13/2A, 14, 15, 16 at Village Shewalwadi and Survey Nos. 70A, 71/A/2, 71/B, 71C/2, 71/1/1B, 71/A/1/1F & 71/A/1/1E at Village Manjri Budruk

Boundaries

North
Premium Tower 2
South
Canal
East
Ramp
West
9 m Driveway

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking317 units

61 of 317 units booked (19%), as the promoter reported to MahaRERA

4 BHK Villa · 13 units3BHK · 216 units3BHK Podium Garden · 6 units4BHK · 72 units4BHK Podium Garden · 2 units3 BHK Podium Garden · 6 units4 BHK Podium Garden · 2 units
RERABuildingTypeCarpet areaUnitsBooked
P52100053978Row House R1 to R84 BHK Villa242.67 sq m · 2,612 sq ft80
P52100053927Row House R9 to R134 BHK Villa242.67 sq m · 2,612 sq ft50
P52100052683Tower 13BHK116.27 sq m · 1,252 sq ft3620
P52100052683Tower 13BHK Podium Garden116.27 sq m · 1,252 sq ft20
P52100052683Tower 14BHK153.33 sq m · 1,650 sq ft3617
P52100052683Tower 14BHK Podium Garden153.33 sq m · 1,650 sq ft22
P52100053177Tower 23BHK107.8 sq m · 1,160 sq ft186
P52100053177Tower 23BHK108.05 sq m · 1,163 sq ft189
Show all 22 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100053177Tower 23BHK108.46 sq m · 1,167 sq ft365
P52100053177Tower 23 BHK Podium Garden107.8 sq m · 1,160 sq ft10
P52100053177Tower 23 BHK Podium Garden108.05 sq m · 1,163 sq ft10
P52100053177Tower 23 BHK Podium Garden108.46 sq m · 1,167 sq ft22
P52100054077Tower 33BHK107.8 sq m · 1,160 sq ft180
P52100054077Tower 33BHK108.05 sq m · 1,163 sq ft180
P52100054077Tower 33BHK108.46 sq m · 1,167 sq ft360
P52100054077Tower 33BHK Podium Garden107.8 sq m · 1,160 sq ft10
P52100054077Tower 33BHK Podium Garden108.05 sq m · 1,163 sq ft10
P52100054077Tower 33BHK Podium Garden108.46 sq m · 1,167 sq ft20
P52100053966Tower 43BHK116.27 sq m · 1,252 sq ft360
P52100053966Tower 43 BHK Podium Garden116.27 sq m · 1,252 sq ft20
P52100053966Tower 44BHK153.33 sq m · 1,650 sq ft360
P52100053966Tower 44 BHK Podium Garden153.33 sq m · 1,650 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals26

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectFourth Dimension Architects Private Limited—P52100053177
ArchitectFourth Dimension Architects Private Limited—P52100053927
ArchitectFourth Dimension Architects Private Limited—P52100054077
ArchitectFourth Dimension Architects Private Limited—P52100053978
ArchitectFourth Dimension Architects Private Limited—P52100053966
ArchitectFourth Dimension Architects Private Limited—P52100052683
Chartered accountantB R Nagda & Co—P52100053927
Chartered accountantB R Nagda & Co—P52100054077
Show all 26 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Chartered accountantB R Nagda & Co—P52100053978
Chartered accountantBR Nagda & Company—P52100052683
Chartered accountantBR Nagda & Company—P52100053177
Chartered accountantBR Nagda & Company—P52100053966
EngineerER. Ambadas T Kharatmol—P52100052683
EngineerER. Ambadas T Kharatmol—P52100053927
EngineerER. Ambadas T Kharatmol—P52100054077
EngineerER. Ambadas T Kharatmol—P52100053177
EngineerER. Ambadas T Kharatmol—P52100053978
EngineerER. Ambadas T Kharatmol Kharatmol—P52100053966
EngineerRahul Krishna Singh Revulagadda—P52100053177
EngineerRahul Krishna Singh Revulagadda—P52100052683
EngineerRahul Krishna Singh Revulagadda—P52100054077
EngineerRahul Krishna Singh Revulagadda—P52100053966
EngineerRahul Krishna Singh Revulagadda—P52100053927
EngineerRahul Krishna Singh Revulagadda—P52100053978
OtherRahul Krishna Singh Revulagadda—P52100054077
OtherSiddhant—P52100053978

Source: MahaRERA project page. Contact details are not shown.

Other projects in Shewalewadi

All 216 projects in Shewalewadi · Compare Mango Tree Villa with another project

Mango Tree Villa in numbers

Registered deals, summarised

Deedo has 25 registered documents at Mango Tree Villa, from Feb 2024 to Sep 2026: 25 sales. The median registered sale since Feb 2024 works out to about ₹13,600 per sq ft, at a median of ₹1.77 Cr a deal; 0% of sales were resales.

What is the price per sq ft at Mango Tree Villa?
The median registered sale since Feb 2024 works out to about ₹13,600 per sq ft, at a median of ₹1.77 Cr a deal; 0% of sales were resales.
How many properties have been sold at Mango Tree Villa?
25 sales are registered at Mango Tree Villa.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Mango Tree Villa by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Primary sale · Oct 2026

₹2–3.5 Cr

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology