Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 12% of its units are booked.

Sasvad (M Cl), Pune 412301 · Property rates in Sasvad (M Cl) · by Sankalp Developers

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales12% booked18 of 154 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 5 Oct 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100052848
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000528485 Oct 202331 Dec 202630 Apr 2027Sankalp DevelopersProject page
Documents57

1 document held by Deedo, 56 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1) FIRM PAN CARD.pdf · uploaded 1 Jul 2023Source

Legal

  • Declaration Form BForm - B.pdf · uploaded 16 Jul 2023Source
  • Legal Title reportLegal Title Report.pdf · uploaded 5 Aug 2023Source

Migrated

  • 1 PAN Card1) FIRM PAN CARD.pdf · uploaded 1 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)LAUYOUT PLAN_compressed.pdf · uploaded 1 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentfloor plan_compressed.pdf · uploaded 1 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted development3) Commencement lattre.pdf · uploaded 1 Jul 2023Source
Show all 57 documentsShow fewer documents

Migrated

  • 1 Declaration about Commencement Certificatecomencemwnt.pdf · uploaded 1 Jul 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECH CERTIFICAYTE.pdf · uploaded 1 Jul 2023Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 1 Jul 2023Source
  • 1 Proforma of Agreement for saleDraft for Rera.pdf · uploaded 1 Jul 2023Source
  • 1 Proforma of Allotment letterallotment latter.pdf · uploaded 1 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterdeviation.pdf · uploaded 1 Jul 2023Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation.pdf · uploaded 1 Jul 2023Source
  • 1 Declaration in FORM BForm - B.pdf · uploaded 16 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (2).pdf · uploaded 22 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBAANK ACCOUNT.pdf · uploaded 22 Jul 2023Source
  • 1 a Details of encumbrances concerned to FinanceENCUMBARANCE.pdf · uploaded 23 Jul 2023Source
  • 1 b Details of encumbrances concerned to LegalENCUMBARANCE.pdf · uploaded 23 Jul 2023Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 5 Aug 2023Source
  • 1 Other – Technicalscan0411_compressed.pdf · uploaded 16 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 2 Sep 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentMAIL FOR NAGARPALIKA FOR CONFIRMING CC.pdf · uploaded 14 Sep 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-31-12-24.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 6 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Feb 2025Source
  • Withdrawal Update Form 1FORM 1- sankalp developers.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 (2).pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 1Form 1_page.pdf · uploaded 30 Jul 2025Source
  • Withdrawal Update Form 2Form 2_page.pdf · uploaded 30 Jul 2025Source
  • Withdrawal Update Form 3Form 3_page.pdf · uploaded 30 Jul 2025Source
  • Withdrawal Update Form 1Form 1_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Form 1_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2Form 2_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 2Form 2_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3Form 3_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 3Form 3_page.pdf · uploaded 21 Jan 2026Source
  • Withdrawal Update Form 1Form-1 Q2.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 1Form-1 Q3.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 2Final Form 2 Sankalp Q2.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 2Final Form-2 Sankalp Q3.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 3Final Form-3 Q2.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 3Final Form-3 Q3.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3Final Form 3 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form 1_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 2Form 2_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 3Form 3_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source

Technical

  • DocumentLAUYOUT PLAN_compressed.pdf · uploaded 1 Jul 2023Source
  • Documentfloor plan_compressed.pdf · uploaded 1 Jul 2023Source
  • Other – Technicalscan0411_compressed.pdf · uploaded 16 Aug 2023Source

Technical (Architect)

  • DocumentForm 1-31-12-24.pdf · uploaded 6 Feb 2025Source
  • DocumentForm 1_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 72/A/1/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK154 units in all
Address
72/A/1/1, Sonori Road, SaswadPIN 412301
Village
Sasvad (M Cl), Purandhar taluka
Land area for this project
14,600 sq m (1,57,153 sq ft)
Permissible built-up area
11,336 sq m (1,22,014 sq ft)
Sanctioned built-up area
11,336 sq m (1,22,014 sq ft)
Recreational open space
1,426 sq m (15,353 sq ft)
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

72/A/1/1

Land as published on MahaRERA's project page

72/A/1/1

Boundaries

North
D Building
South
72 A 1 13 To 16
East
Sr No 72 4
West
Podium

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking154 units

18 of 154 units booked (12%), as the promoter reported to MahaRERA

1BHK · 84 units2BHK · 70 units
TypeCarpet areaUnitsBooked
1BHK3,632.64 sq m · 39,101 sq ft8418
2BHK4,296.42 sq m · 46,246 sq ft700

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVishal Kumbharkar—
Chartered accountantCa Omkar Deokar—
EngineerShreyash Namdeo Kumbharkar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Sasvad (M Cl)

All 56 projects in Sasvad (M Cl) · Compare Anand Baug C Wing with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology