Deedo IDDP-PUN-01VPCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 12% of its units are booked.
Sasvad (M Cl), Pune 412301 · Property rates in Sasvad (M Cl) · by Sankalp Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 5 Oct 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052848
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052848 | 5 Oct 2023 | 31 Dec 2026 | 30 Apr 2027 | Sankalp Developers | Project page |
Documents57
1 document held by Deedo, 56 filings listed on MahaRERA's project page
Finance
- PAN Card1) FIRM PAN CARD.pdf · uploaded 1 Jul 2023Source
Legal
Migrated
- 1 PAN Card1) FIRM PAN CARD.pdf · uploaded 1 Jul 2023Source
- 1 Copy of Layout Approval (in case of layout)LAUYOUT PLAN_compressed.pdf · uploaded 1 Jul 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentfloor plan_compressed.pdf · uploaded 1 Jul 2023Source
- 1 Commencement Certificates / NA Order for plotted development3) Commencement lattre.pdf · uploaded 1 Jul 2023Source
Show all 57 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement Certificatecomencemwnt.pdf · uploaded 1 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECH CERTIFICAYTE.pdf · uploaded 1 Jul 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 1 Jul 2023Source
- 1 Proforma of Agreement for saleDraft for Rera.pdf · uploaded 1 Jul 2023Source
- 1 Proforma of Allotment letterallotment latter.pdf · uploaded 1 Jul 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation.pdf · uploaded 1 Jul 2023Source
- 1 Deviation Report with respect to model copy of Agreementdeviation.pdf · uploaded 1 Jul 2023Source
- 1 Declaration in FORM BForm - B.pdf · uploaded 16 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (2).pdf · uploaded 22 Jul 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBAANK ACCOUNT.pdf · uploaded 22 Jul 2023Source
- 1 a Details of encumbrances concerned to FinanceENCUMBARANCE.pdf · uploaded 23 Jul 2023Source
- 1 b Details of encumbrances concerned to LegalENCUMBARANCE.pdf · uploaded 23 Jul 2023Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 5 Aug 2023Source
- 1 Other – Technicalscan0411_compressed.pdf · uploaded 16 Aug 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 2 Sep 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentMAIL FOR NAGARPALIKA FOR CONFIRMING CC.pdf · uploaded 14 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-31-12-24.pdf · uploaded 6 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 6 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Feb 2025Source
- Withdrawal Update Form 1FORM 1- sankalp developers.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3FORM 3 (2).pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1Form 1_page.pdf · uploaded 30 Jul 2025Source
- Withdrawal Update Form 2Form 2_page.pdf · uploaded 30 Jul 2025Source
- Withdrawal Update Form 3Form 3_page.pdf · uploaded 30 Jul 2025Source
- Withdrawal Update Form 1Form 1_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 1Form 1_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2Form 2_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2Form 2_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3Form 3_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3Form 3_page.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 1Form-1 Q2.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 1Form-1 Q3.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 2Final Form 2 Sankalp Q2.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 2Final Form-2 Sankalp Q3.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 3Final Form-3 Q2.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 3Final Form-3 Q3.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 1FORM 1 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 2FORM 2 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 3Final Form 3 Sankalp developers Q4.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 1Form 1_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 2Form 2_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 3Form 3_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
Technical
Technical (Architect)
Technical (Engineer)
- DocumentForm 2_Q1_Sankalp.pdf · uploaded 22 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 72/A/1/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK154 units in all
- Address
- 72/A/1/1, Sonori Road, SaswadPIN 412301
- Village
- Sasvad (M Cl), Purandhar taluka
- Land area for this project
- 14,600 sq m (1,57,153 sq ft)
- Permissible built-up area
- 11,336 sq m (1,22,014 sq ft)
- Sanctioned built-up area
- 11,336 sq m (1,22,014 sq ft)
- Recreational open space
- 1,426 sq m (15,353 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
72/A/1/1
Boundaries
- North
- D Building
- South
- 72 A 1 13 To 16
- East
- Sr No 72 4
- West
- Podium
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking154 units
18 of 154 units booked (12%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 3,632.64 sq m · 39,101 sq ft | 84 | 18 |
| 2BHK | 4,296.42 sq m · 46,246 sq ft | 70 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vishal Kumbharkar | — |
| Chartered accountant | Ca Omkar Deokar | — |
| Engineer | Shreyash Namdeo Kumbharkar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Sasvad (M Cl)
- Vrundavan ViharRERA PM1260002601714
- Moraya ViharRERA PR1260002600078
- Bhairavi TranquilityRERA PM1260002502217
- Balaji ParadiseRERA PR1260002501352
- Shree Sai SahwasRERA PR1260002500756
- Prestige PlatinumRERA PM1260002500447
- Narayan BaugRERA P52100079239
- Sangameshwar GoldRERA P52100078664
All 56 projects in Sasvad (M Cl) · Compare Anand Baug C Wing with another project