RERA projects in Sangarun
3 projects under 3 MahaRERA registrations, registered 2017–2017. 100% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
0Completion still due3 past their completion date
51 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
20Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
Projects in Sangarun
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Countryside Phase IIPate Developers | P52100005008 | 9 Aug 2017 | 31 Dec 2019 | 30 Dec 2023 | Extended 48 mo | 0 |
| Countryside Phase IIIPate Developers | P52100004089 | 7 Aug 2017 | 31 Dec 2019 | 31 Dec 2024 | Extended 60 mo | 0 |
| Countryside Phase 1Pate Developers | P52100002809 | 4 Aug 2017 | 31 Dec 2019 | 30 Mar 2024 | Extended 51 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Pate Developers3 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology