3 projects under 3 MahaRERA registrations, registered 2017–2017. 100% have a completion date extended beyond the one promised.

Locality
3RERA projects
3Registrations
0Completion still due3 past their completion date
51 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
20Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173

Projects in Sangarun

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Countryside Phase IIPate DevelopersP521000050089 Aug 201731 Dec 201930 Dec 2023Extended 48 mo0
Countryside Phase IIIPate DevelopersP521000040897 Aug 201731 Dec 201931 Dec 2024Extended 60 mo0
Countryside Phase 1Pate DevelopersP521000028094 Aug 201731 Dec 201930 Mar 2024Extended 51 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Pate Developers3 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology