Others · 2 buildings · 124 unitsRERA P52100050912

Vision Vanessa

Deedo IDDP-PUN-G296

MahaRERA shows it completed; no MahaRERA orders on record; 47% of its units are booked.

Ravet, Pune 411044 · Property rates in Ravet · by P4 Group

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales47% booked58 of 124 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 15 May 2023, completion promised 31 Dec 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Jul 2026Not on recordMortgage—View Mortgage, Jul 2026
Jun 2026Not on recordMortgage—View Mortgage, Jun 2026
Mar 2026B Building · 1002Mortgage—View Mortgage, Mar 2026
Jan 2026Not on recordMortgage—View Mortgage, Jan 2026

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100050912
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005091215 May 202331 Dec 202631 Dec 2026P4 GroupProject page
Documents199

1 document held by Deedo, 198 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardP4 GROUP PAN CARD.pdf · uploaded 13 Apr 2023Source

Legal

  • Declaration Form BFORM-B Affidavit cum Declaration.pdf · uploaded 20 Apr 2023Source
  • Legal Title report1 Copy of the legal title report_opt.pdf · uploaded 21 Apr 2023Source
  • Legal Title report1 Copy of the legal title report3.pdf · uploaded 21 Apr 2023Source
  • Legal Title report1 Copy of the legal title report4.pdf · uploaded 21 Apr 2023Source
  • Other – LegalAssignment Deed Plot No 9.pdf · uploaded 26 Apr 2023Source
  • Other – LegalAssignment Deed Plot No 10.pdf · uploaded 26 Apr 2023Source
Show all 199 documentsShow fewer documents

Legal

  • Other – LegalAssignment Deed Plot No 11.pdf · uploaded 26 Apr 2023Source
  • Other – LegalAssignment Deed Plot No 12.pdf · uploaded 26 Apr 2023Source
  • Other – LegalAssignment Deed Plot No 13.pdf · uploaded 26 Apr 2023Source
  • Other – LegalAssignment Deed Plot No 14.pdf · uploaded 26 Apr 2023Source
  • Other – LegalSupplementary Assignment Deed Plot No 9 to 14.pdf · uploaded 26 Apr 2023Source
  • Other – LegalAMALGAMATION ORDER NO 208 ( 09_04_2021).pdf · uploaded 26 Apr 2023Source
  • Other – LegalTRANSFER CERTIFICATE OF PLOT NO 09 TO 14.pdf · uploaded 8 May 2023Source

Migrated

  • 1 PAN CardP4 GROUP PAN CARD.pdf · uploaded 13 Apr 2023Source
  • 1 Copy of Layout Approval (in case of layout)IOD-compressed.pdf · uploaded 13 Apr 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1_3 Layout.pdf · uploaded 13 Apr 2023Source
  • 2 Building Plan Approval / NA Order for plotted development4_6 Layout.pdf · uploaded 13 Apr 2023Source
  • 3 Building Plan Approval / NA Order for plotted development7_9 Layout.pdf · uploaded 13 Apr 2023Source
  • 4 Building Plan Approval / NA Order for plotted development10_11 Layout.pdf · uploaded 13 Apr 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate-compressed.pdf · uploaded 13 Apr 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 20 Apr 2023Source
  • 1 Declaration in FORM BFORM-B Affidavit cum Declaration.pdf · uploaded 20 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 20 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report with respect to Allotment letter.pdf · uploaded 20 Apr 2023Source
  • 1 Copy of the legal title report1 Copy of the legal title report_opt.pdf · uploaded 21 Apr 2023Source
  • 2 Copy of the legal title report1 Copy of the legal title report3.pdf · uploaded 21 Apr 2023Source
  • 3 Copy of the legal title report1 Copy of the legal title report4.pdf · uploaded 21 Apr 2023Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 21 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal.pdf · uploaded 21 Apr 2023Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 21 Apr 2023Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal.pdf · uploaded 21 Apr 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 21 Apr 2023Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale.pdf · uploaded 21 Apr 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 21 Apr 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report with respect to model copy of Agreement.pdf · uploaded 21 Apr 2023Source
  • 1 Other – TechnicalAdobe Scan 24 Apr 2023.pdf · uploaded 24 Apr 2023Source
  • 1 CERSAI detailsCERSAI REPORT WITH UNDERTAKING.pdf · uploaded 25 Apr 2023Source
  • 1 Other – LegalAssignment Deed Plot No 9.pdf · uploaded 26 Apr 2023Source
  • 2 Other – LegalAssignment Deed Plot No 10.pdf · uploaded 26 Apr 2023Source
  • 3 Other – LegalAssignment Deed Plot No 11.pdf · uploaded 26 Apr 2023Source
  • 4 Other – LegalAssignment Deed Plot No 12.pdf · uploaded 26 Apr 2023Source
  • 5 Other – LegalAssignment Deed Plot No 13.pdf · uploaded 26 Apr 2023Source
  • 6 Other – LegalAssignment Deed Plot No 14.pdf · uploaded 26 Apr 2023Source
  • 7 Other – LegalSupplementary Assignment Deed Plot No 9 to 14.pdf · uploaded 26 Apr 2023Source
  • 8 Other – LegalAMALGAMATION ORDER NO 208 ( 09_04_2021).pdf · uploaded 26 Apr 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form No 03 P4 Group.pdf · uploaded 4 May 2023Source
  • 9 Other – LegalTRANSFER CERTIFICATE OF PLOT NO 09 TO 14.pdf · uploaded 8 May 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work.pdf · uploaded 19 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project.pdf · uploaded 19 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate on Project Cost and Fund withdrawal.pdf · uploaded 19 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory_P4 GROUP.pdf · uploaded 23 Oct 2023Source
  • 3 a Details of encumbrances concerned to FinanceDETAILS OF ENCUMBRANCES CONCERNED TO FINANCE_VISION VANESSA.pdf · uploaded 2 Nov 2023Source
  • 3 b Details of encumbrances concerned to LegalDETAILS OF ENCUMBRANCES CONCERNED TO FINANCE_VISION VANESSA.pdf · uploaded 2 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work.pdf · uploaded 13 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project.pdf · uploaded 15 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate on Project Cost And Fund withdrawal.pdf · uploaded 15 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryVISION VANESSA DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf · uploaded 19 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work P4 GROUP.pdf · uploaded 15 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project-Vanessa.pdf · uploaded 15 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate on Project Cost Vision Vanessa.pdf · uploaded 15 Apr 2024Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD_BOOKED INVENTORY_VISION VANESSA.pdf · uploaded 17 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineers Certificate on Quality Assurance Vanessa.pdf · uploaded 18 May 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work.pdf · uploaded 15 Jul 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project.pdf · uploaded 15 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate on Project Cost And Fund withdrawal.pdf · uploaded 15 Jul 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD_UNSOLD INVENTORY (VISION VANESSA).pdf · uploaded 17 Jul 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration About Seperate Bank Account_Vision Vanessa.pdf · uploaded 29 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentVANESSA _ SANCTION LAYOUT _ 1_3.pdf · uploaded 31 Jul 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentVANESSA _ SANCTION LAYOUT _ 4_7.pdf · uploaded 31 Jul 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentVANESSA _ SANCTION LAYOUT _ 8_11.pdf · uploaded 31 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentVANESSA _ COMMENCEMENT.pdf · uploaded 31 Jul 2024Source
  • 2 Declaration about Commencement CertificateVANESSA _ COMMENCEMENT.pdf · uploaded 31 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work.pdf · uploaded 16 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate on Project Cost And Fund withdrawal.pdf · uploaded 16 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project.pdf · uploaded 16 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Annual Audit Report of Statutory CA Vanessa.pdf · uploaded 16 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryVISION VANESSA SOLD UNSOLD INVENTORY LIST.pdf · uploaded 11 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 7 Dec 2024Source
  • 2 Building Plan Approval / NA Order for plotted development3_4.pdf · uploaded 7 Dec 2024Source
  • 6 Building Plan Approval / NA Order for plotted development11_12.pdf · uploaded 7 Dec 2024Source
  • 5 Building Plan Approval / NA Order for plotted development9_10.pdf · uploaded 7 Dec 2024Source
  • 4 Building Plan Approval / NA Order for plotted development7_8.pdf · uploaded 7 Dec 2024Source
  • 3 Building Plan Approval / NA Order for plotted development5_6.pdf · uploaded 7 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1_2.pdf · uploaded 7 Dec 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 9 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM NO 01 P4 GROUP VANESSA.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)VISION VANESSA FORM NO 3.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM NO 02 P4 GROUP VANESSA.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP4 GROUP.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work P4 GROUP FORM 01.pdf · uploaded 14 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP 4 GROUP CC.pdf · uploaded 2 May 2025Source
  • 1 Declaration about Commencement CertificateDeclaration about CC P4 group.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 P4 Vanessa 31 3 2025.pdf · uploaded 6 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project P4 Group 31 3 2025.pdf · uploaded 6 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 02 VISION VANESSA 31 03 2025.pdf · uploaded 6 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted development1-2.pdf · uploaded 10 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted development3-5.pdf · uploaded 10 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted development6-9.pdf · uploaded 10 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted development10-12.pdf · uploaded 10 May 2025Source
  • Form 2A (FY 2024-2025)FORM 2A (P4 GROUP).pdf · uploaded 16 Jul 2025Source
  • Form 5 (FY 2023-2024)Annual Audit Report of Statutory CA Vanessa 2023 24.pdf · uploaded 25 Sep 2025Source
  • Form 5 (FY 2024-2025)Form 5 P4 Group Vision Vanessa.pdf · uploaded 25 Sep 2025Source
  • Withdrawal Update Form 1P4 GROUP FORM NO 1 ARCHITECT CERTIFICATE.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 1P4 GROUP FORM NO 1 ARCHITECT CERTIFICATE.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 2P4 GROUP ENGINEER CERTIFICATE FORN NO 2.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 2P4 GROUP ENGINEER CERTIFICATE FORN NO 2.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 3P4 GROUP CA CERTIFICATE FORM NO 3 30 09 2025.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 3P4 GROUP CA CERTIFICATE FORM NO 3 30 09 2025.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 1P4 GROUP FORM NO 1 ARCHITECT CERTIFICATE.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 2P4 GROUP ENGINEER CERTIFICATE FORN NO 2.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 3P4 GROUP CA CERTIFICATE FORM NO 3 30 09 2025.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1P4 GROUP FORM 1 31 12 2025.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 2Form 2 -Vision Vanessa -FY 2025-26 -Q 3.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 3P4 GROUP- Vision Vanessa (1).pdf · uploaded 19 Jan 2026Source
  • Form 1Form 01 Mar 24.pdf · uploaded 23 Feb 2026Source
  • Form 2Form 02 Mar 24.pdf · uploaded 23 Feb 2026Source
  • Form 3Form - 3 Mar 24.pdf · uploaded 23 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory Mar 24.pdf · uploaded 23 Feb 2026Source
  • Form 1Form - 1.pdf · uploaded 21 Mar 2026Source
  • Form 1Form - 1.pdf · uploaded 21 Mar 2026Source
  • Form 1Form - 1.pdf · uploaded 21 Mar 2026Source
  • Form 1FORM NO -01 P4 GROUP VANESSA.pdf · uploaded 21 Mar 2026Source
  • Form 2Form - 2.pdf · uploaded 21 Mar 2026Source
  • Form 2Form - 2.pdf · uploaded 21 Mar 2026Source
  • Form 2Form - 2.pdf · uploaded 21 Mar 2026Source
  • Form 2FORM NO -02 P4 GROUP VANESSA.pdf · uploaded 21 Mar 2026Source
  • Form 3Form - 3.pdf · uploaded 21 Mar 2026Source
  • Form 3Form - 3.pdf · uploaded 21 Mar 2026Source
  • Form 3Form - 3.pdf · uploaded 21 Mar 2026Source
  • Form 3V VANESSA -FORM NO 3.pdf · uploaded 21 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 21 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 21 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 21 Mar 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 21 Mar 2026Source
  • Withdrawal Update Form 1V Vanessa P4 Rera Form 1.pdf · uploaded 17 Apr 2026Source
  • Withdrawal Update Form 2Form 02.pdf · uploaded 17 Apr 2026Source
  • Withdrawal Update Form 3P4 Group Form 3 Q4.pdf · uploaded 17 Apr 2026Source
  • Form 1Architect Certificate 30 09 2024.pdf · uploaded 10 Jun 2026Source
  • Form 1RERA FORM 01 31 3 2025.pdf · uploaded 10 Jun 2026Source
  • Form 2Engineer Certificate 30 09 2024.pdf · uploaded 10 Jun 2026Source
  • Form 2RERA FORM 02 31 03 2025.pdf · uploaded 10 Jun 2026Source
  • Form 3CA Certificate 30 09 25.pdf · uploaded 10 Jun 2026Source
  • Form 3RERA FORM 03 31 03 2025.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 30 09 24.pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory 31 03 2025.pdf · uploaded 10 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A for FY 2025-26.pdf · uploaded 3 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 05 06 2026 Vision Vanessa.pdf · uploaded 4 Jul 2026Source
  • Withdrawal Update Form 2P4 GROUP FORM 2.pdf · uploaded 4 Jul 2026Source
  • Withdrawal Update Form 3P4 GROP FORM 3 05 06 2026.pdf · uploaded 4 Jul 2026Source
  • Form 2A (FY 2023-2024)FORM 2A 2023 24.pdf · uploaded 4 Jul 2026Source
  • Form 5 (FY 2025-2026)FORM 05 VISION VANESSA.pdf · uploaded 8 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 05 06 2026 Vision Vanessa.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 2P4 GROUP FORM 2.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 3P4 GROP FORM 3 05 06 2026.pdf · uploaded 10 Aug 2026Source
  • Occupational CertificateOccupancy Certificate.pdf · uploaded 3 Sep 2026Source

Technical

  • DocumentIOD-compressed.pdf · uploaded 13 Apr 2023Source
  • Document1_3 Layout.pdf · uploaded 13 Apr 2023Source
  • Document4_6 Layout.pdf · uploaded 13 Apr 2023Source
  • Document7_9 Layout.pdf · uploaded 13 Apr 2023Source
  • Document10_11 Layout.pdf · uploaded 13 Apr 2023Source
  • Other – TechnicalAdobe Scan 24 Apr 2023.pdf · uploaded 24 Apr 2023Source
  • DocumentVANESSA _ SANCTION LAYOUT _ 1_3.pdf · uploaded 31 Jul 2024Source
  • DocumentVANESSA _ SANCTION LAYOUT _ 4_7.pdf · uploaded 31 Jul 2024Source
  • DocumentVANESSA _ SANCTION LAYOUT _ 8_11.pdf · uploaded 31 Jul 2024Source
  • Document1_2.pdf · uploaded 7 Dec 2024Source
  • Document3_4.pdf · uploaded 7 Dec 2024Source
  • Document5_6.pdf · uploaded 7 Dec 2024Source
  • Document7_8.pdf · uploaded 7 Dec 2024Source
  • Document9_10.pdf · uploaded 7 Dec 2024Source
  • Document11_12.pdf · uploaded 7 Dec 2024Source
  • Document1-2.pdf · uploaded 10 May 2025Source
  • Document3-5.pdf · uploaded 10 May 2025Source
  • Document6-9.pdf · uploaded 10 May 2025Source
  • Document10-12.pdf · uploaded 10 May 2025Source
  • DocumentV Vanessa _Ravet_Approved layout_compressed.pdf · uploaded 17 Apr 2026Source
  • DocumentV Vanessa _Ravet_Comencement Certificate.pdf · uploaded 17 Apr 2026Source
  • DocumentPlan 01.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 01.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 02.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 03.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 04.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 05.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 06.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 07.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 08.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 09.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 10.pdf · uploaded 3 Jul 2026Source
  • DocumentPlan 11.pdf · uploaded 3 Jul 2026Source

Technical (Architect)

  • DocumentArchitect’s Certificate of Percentage of Completion of Work.pdf · uploaded 16 Oct 2024Source
  • DocumentFORM NO 01 P4 GROUP VANESSA.pdf · uploaded 20 Jan 2025Source
  • DocumentArchitect’s Certificate of Percentage of Completion of Work P4 GROUP FORM 01.pdf · uploaded 14 Apr 2025Source
  • DocumentFORM 1 ARCHITECT CERTIFICATE 05 06 2026 Vision Vanessa.pdf · uploaded 22 Jun 2026Source

Technical (Engineer)

  • DocumentEngineer’s Certificate on Cost Incurred on Project.pdf · uploaded 16 Oct 2024Source
  • DocumentFORM NO 02 P4 GROUP VANESSA.pdf · uploaded 20 Jan 2025Source
  • DocumentEngineer’s Certificate on Cost Incurred on Project P4 Group 31 3 2025.pdf · uploaded 6 May 2025Source
  • DocumentFORM 02 VISION VANESSA 31 03 2025.pdf · uploaded 6 May 2025Source
  • DocumentP4 GROUP FORM 2.pdf · uploaded 27 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No. 09 to 14, Sector No. 32A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
3BHK124 units in all
Address
Plot No 09 To 14 Sector No 32a, Sector No 32a, Ravet PradhikaranPIN 411044
Village
Ravet, Haveli taluka
Land area for this project
6,767 sq m (72,840 sq ft)
Permissible built-up area
27,232 sq m (2,93,122 sq ft)
Sanctioned built-up area
27,232 sq m (2,93,122 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Plot No. 09 to 14Sector No. 32A

Land as published on MahaRERA's project page

Sector No. 32A, Plot No. 09 to 14

Boundaries

North
9 Meter Road
South
12 Meter Road
East
Property Of Remaining Layout And Plot No 5
West
Plot No 06

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking124 units

58 of 124 units booked (47%), as the promoter reported to MahaRERA

3BHK · 124 units
BuildingTypeCarpet areaUnitsBooked
A Building3BHK122.18 sq m · 1,315 sq ft8053
B Building3BHK122.18 sq m · 1,315 sq ft445

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals34

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMs Mahendra Thakur And Associates—
Chartered accountantBankim Patel & Associates—
EngineerMayank Shubhaschandra Patel—
EngineerNarendra Pandurang Kulkarni—
EngineerRameshwar Chitale—
EngineerSaurabh Vijay Bendale—
EngineerSpectrum Consultants—
EngineerSwapnil Sasane—
Show all 34 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentAbhishek Arun Bhukan—
Registered real estate agentAb Housing Realty Private Limited—
Registered real estate agentAkshay Arun Kulkarni—
Registered real estate agentAmit Khandu Khandagale—
Registered real estate agentAniket Gate—
Registered real estate agentAshwani Fotedar—
Registered real estate agentHouse Mart Properties—
Registered real estate agentMahendra Ashok Amrutkar—
Registered real estate agentManvendra Tripathi—
Registered real estate agentNavnath Chandrakant Dhore—
Registered real estate agentPradip Kundlik Bhosale—
Registered real estate agentPranoo Realty—
Registered real estate agentPropdeal Realtors and Consulting Private Limited—
Registered real estate agentPropinn Properties Private Limited—
Registered real estate agentPurnendu Prasad—
Registered real estate agentRavi Ranjan Kumar Gautam—
Registered real estate agentRK's Marketing—
Registered real estate agentRupeshkumar Satishkumar Zanzari—
Registered real estate agentSagar Balasaheb Brahmane—
Registered real estate agentSpaceindia Nest Private Limited—
Registered real estate agentSwapnil Satyawan Dethe—
Registered real estate agentSwati Jain—
Registered real estate agentSwati Parag Degaonkar—
Registered real estate agentVaibhav Balasaheb Borkar—
Registered real estate agentVimalesh Kumar Singh—
Registered real estate agentYogesh Pandurang Ingole—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ravet

All 958 projects in Ravet · Compare Vision Vanessa with another project

Vision Vanessa in numbers

Registered deals, summarised

Deedo has 4 registered documents at Vision Vanessa, from Jan 2026 to Jul 2026: 4 mortgages.

Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Vision Vanessa by Deedo, last updated with deals registered in Jul 2026.

Latest deal · Mortgage · Jul 2026

Exact price & Index II