Swanandi Blossom Phase 2

Deedo IDDP-PUN-H99B

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Ravet, Pune 412101 · Property rates in Ravet · by Samarth Chintamani Properties

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 36 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 31 Jul 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100077253
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007725331 Jul 202431 Dec 202830 Apr 2029Samarth Chintamani PropertiesProject page
Documents84

1 document held by Deedo, 83 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 11 Jul 2024Source
  • Other – FinanceBANK Letter 25-07-2024.pdf · uploaded 26 Jul 2024Source

Legal

  • Other – Legal7-12.pdf · uploaded 11 Jul 2024Source
  • Legal Title reportSearch Report.pdf · uploaded 11 Jul 2024Source
  • Declaration Form BForm B Promoter.pdf · uploaded 11 Jul 2024Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 11 Jul 2024Source
  • 1 Copy of the legal title reportSearch Report.pdf · uploaded 11 Jul 2024Source
Show all 84 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to Financeencumbrance concerned.pdf · uploaded 11 Jul 2024Source
  • 1 b Details of encumbrances concerned to Legalencumbrance concerned.pdf · uploaded 11 Jul 2024Source
  • 1 Copy of Layout Approval (in case of layout)imgw-709074122_page-0001 (1).pdf · uploaded 11 Jul 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 11 Jul 2024Source
  • 2 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 11 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted development13 D.pdf · uploaded 11 Jul 2024Source
  • 4 Building Plan Approval / NA Order for plotted development14 D.pdf · uploaded 11 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentClub House.pdf · uploaded 11 Jul 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 11 Jul 2024Source
  • 1 Declaration about Commencement CertificateC C DEC PHS 2.pdf · uploaded 11 Jul 2024Source
  • 1 Declaration in FORM BForm B Promoter.pdf · uploaded 11 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 PHS 2.pdf · uploaded 11 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 PHS 2.pdf · uploaded 11 Jul 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectFinance Availed.pdf · uploaded 11 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 333.pdf · uploaded 11 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOUSURE OF INTREST IN REAL ESTATE 1.pdf · uploaded 11 Jul 2024Source
  • 1 Proforma of Allotment letterANNEXURE 1.pdf · uploaded 11 Jul 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT DRAFT 11 -07-2024.pdf · uploaded 11 Jul 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A1.pdf · uploaded 11 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterALLOTMENT LETTER DEV.pdf · uploaded 11 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT WITH RESPECT TO AGRERMENT.pdf · uploaded 11 Jul 2024Source
  • 1 Other – Legal7-12.pdf · uploaded 11 Jul 2024Source
  • 2 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE CONCERNED OF FINANCE_page-0001.pdf · uploaded 18 Jul 2024Source
  • 2 b Details of encumbrances concerned to LegalNO ENCUMBRANCE CONCERNED OF FINANCE_page-0001.pdf · uploaded 18 Jul 2024Source
  • 1 CERSAI detailsCERSAI REPORT_page-0001.pdf · uploaded 18 Jul 2024Source
  • 1 Other – TechnicalCC Verification Email.pdf · uploaded 18 Jul 2024Source
  • 2 Other – TechnicalANNEXURE A_page-0001.pdf · uploaded 18 Jul 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)SCP Format B.pdf · uploaded 26 Jul 2024Source
  • 1 Other – FinanceBANK Letter 25-07-2024.pdf · uploaded 26 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 15 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_11zon.pdf · uploaded 15 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 1 - Ph 2.pdf · uploaded 29 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 29 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 29 Apr 2025Source
  • Form 1Form 1 samarth chintamani.pdf · uploaded 20 Jul 2025Source
  • Form 2Form 2.PDF · uploaded 20 Jul 2025Source
  • Form 3Form 3_compressed.pdf · uploaded 20 Jul 2025Source
  • Disclosure of Sold and Booked InventorySwanandi Blossom.PDF · uploaded 20 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 24-25.pdf · uploaded 29 Sep 2025Source
  • Form 1Form 1.pdf · uploaded 8 Oct 2025Source
  • Form 2Form 2.pdf · uploaded 8 Oct 2025Source
  • Form 3Form 3_compressed (1).pdf · uploaded 8 Oct 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold 3092025.pdf · uploaded 8 Oct 2025Source
  • Form 1Form 1.PDF · uploaded 19 Jan 2026Source
  • Form 2Form 2 - Ph 2.PDF · uploaded 19 Jan 2026Source
  • Form 3Form 3.pdf · uploaded 19 Jan 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold.PDF · uploaded 19 Jan 2026Source
  • Form 1Form 1.PDF · uploaded 17 Apr 2026Source
  • Form 2Form 2 Sign.pdf · uploaded 17 Apr 2026Source
  • Form 3Form 3 Sign_compressed (1).pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold.PDF · uploaded 17 Apr 2026Source
  • Form 5 (FY 2025-2026)Form 5 Sign.PDF · uploaded 2 Jun 2026Source
  • Form 1Form 1.pdf · uploaded 15 Jul 2026Source
  • Form 2Form 2.pdf · uploaded 15 Jul 2026Source
  • Form 3Form 3.pdf · uploaded 15 Jul 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 15 Jul 2026Source

Technical

  • Documentimgw-709074122_page-0001 (1).pdf · uploaded 11 Jul 2024Source
  • Document1.pdf · uploaded 11 Jul 2024Source
  • Document2.pdf · uploaded 11 Jul 2024Source
  • Document13 D.pdf · uploaded 11 Jul 2024Source
  • Document14 D.pdf · uploaded 11 Jul 2024Source
  • DocumentClub House.pdf · uploaded 11 Jul 2024Source
  • Other – TechnicalCC Verification Email.pdf · uploaded 18 Jul 2024Source
  • Other – TechnicalANNEXURE A_page-0001.pdf · uploaded 18 Jul 2024Source

Technical (Architect)

  • DocumentForm 1 PHS 2.pdf · uploaded 11 Jul 2024Source
  • DocumentForm 1.pdf · uploaded 18 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 1 - Ph 2.pdf · uploaded 29 Apr 2025Source

Technical (Engineer)

  • DocumentForm 2 PHS 2.pdf · uploaded 11 Jul 2024Source
  • DocumentForm 2.pdf · uploaded 18 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 29 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 267(P), 269(P)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 2 BHK LANDOWNER, 3BHK, 3 BHK LANDOWNER36 units in all
Address
Sr No 206/2a(P), C.t.s. No 271(P), 267(P), 269(P), 270(P), 339(P), Near Sant Tukaram Maharaj Bridge, Bhondve Corner, RavetPIN 412101
Village
Ravet, Haveli taluka
Land area for this project
3,884 sq m (41,802 sq ft)
Permissible built-up area
16,586 sq m (1,78,533 sq ft)
Sanctioned built-up area
4,386 sq m (47,213 sq ft)
Recreational open space
1,279 sq m (13,764 sq ft)
Designated bank account
119
Developed in phases
No

Survey, CTS, gat or plot numbers

267(P)269(P)270(P)339(P)C.T.S. NO 271(P)SR NO 206/2A(P)

Land as published on MahaRERA's project page

SR NO 206/2A(P), C.T.S. NO 271(P), 267(P), 269(P), 270(P), 339(P)

Boundaries

North
Part Of Land Bearing Of Sr No 207 Of Pcntda
South
45 Meter Wide Dp Road
East
Part Of Land Bearing Of Sr No206 Of Govind Bhondve
West
Part Of Land Bearing Sr No 206 2b Of N B Bhondave

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking36 units

0 of 36 units booked (0%), as the promoter reported to MahaRERA

2BHK · 14 units2 BHK LANDOWNER · 2 units3BHK · 13 units3 BHK LANDOWNER · 7 units
TypeCarpet areaUnitsBooked
2BHK63.75 sq m · 686 sq ft70
2BHK68.08 sq m · 733 sq ft10
2BHK68.1 sq m · 733 sq ft10
2BHK87.72 sq m · 944 sq ft50
2 BHK LANDOWNER63.75 sq m · 686 sq ft20
3BHK88.11 sq m · 948 sq ft50
3BHK88.91 sq m · 957 sq ft80
3 BHK LANDOWNER87.72 sq m · 944 sq ft30
3 BHK LANDOWNER88.11 sq m · 948 sq ft30
3 BHK LANDOWNER88.91 sq m · 957 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVishal Bafana—
Chartered accountantCA Mohmedyasir A. Bagwan—
Chartered accountantShubham Bora—
EngineerAjinkya Ankush Lahigude—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ravet

All 958 projects in Ravet · Compare Swanandi Blossom Phase 2 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology