Itrend Waterfront
Deedo IDDP-PUN-J646Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Ravet, Pune 412101 · Property rates in Ravet · by Neev Sai Developers · 75% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 30 Aug 2021, completion promised 30 Sep 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Mortgage · Aug 2026No amount
- Resale · Dec 2025
- Primary sale · Aug 2025
- Resale · May 2025
- Resale · May 2025
- Primary sale · Apr 2025
- Mortgage · May 2022No amount
- Mortgage · Mar 2022No amount
- Mortgage · Mar 2022No amount
- Mortgage · Feb 2022No amount
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Aug 2026 | Not on record | Mortgage | — | View Mortgage, Aug 2026 | |
| Dec 2025 | T2 · 0306 | Resale | 562 sq ft | View Resale, Dec 2025 | |
| Aug 2025 | T2 · 0306 | Primary sale | 562 sq ft | View Primary sale, Aug 2025 | |
| May 2025 | Main building · 102 | Resale | 614 sq ft | View Resale, May 2025 | |
| May 2025 | Main building · 309 | Resale | 562 sq ft | View Resale, May 2025 | |
| Apr 2025 | Main building · 309 | Primary sale | 562 sq ft | View Primary sale, Apr 2025 | |
| May 2022 | Not on record | Mortgage | — | View Mortgage, May 2022 | |
| Mar 2022 | Not on record | Mortgage | — | View Mortgage, Mar 2022 | |
| Mar 2022 | Not on record | Mortgage | — | View Mortgage, Mar 2022 | |
| Feb 2022 | Not on record | Mortgage | — | View Mortgage, Feb 2022 |
9 buildings
Open a building to see every flat, floor by floor.
- Building (P52100030538)Size not on record100% booked
- T1Size not on record100% booked
- T2Size not on record100% booked
- T3Size not on record100% booked
- T4Size not on record100% booked
- Tower 117 floors
- Tower 217 floors
- Tower 317 floors
- Tower 417 floors
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100030538
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030538 | 30 Aug 2021 | 30 Sep 2025 | 30 Sep 2025 | Neev Sai Developers | Project page |
Documents85
2 documents held by Deedo, 83 filings listed on MahaRERA's project page
Show all 85 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 4 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentFinal IOD_compressed.pdf · uploaded 4 Aug 2021Source
- 1 Declaration in FORM BForm B_compressed.pdf · uploaded 4 Aug 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)210730 - Architect Cert Form 1.pdf · uploaded 4 Aug 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 CA Certificate_compressed.pdf · uploaded 4 Aug 2021Source
- 1 Proforma of Allotment letterAllotment Letter_compressed.pdf · uploaded 4 Aug 2021Source
- 2 Proforma of Allotment letterAgree.pdf · uploaded 4 Aug 2021Source
- 1 Copy of the legal title reportSearch.pdf · uploaded 5 Aug 2021Source
- 1 OtherSearch Annexure Compress.pdf · uploaded 5 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCC New.pdf · uploaded 13 Aug 2021Source
- 1 Declaration about Commencement CertificateCommencement Declaration.pdf · uploaded 13 Aug 2021Source
- 2 Copy of Layout Approval (in case of layout)Copy of layout.pdf · uploaded 7 Jan 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement cert.pdf · uploaded 7 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Itrend Waterfront Form 5.pdf · uploaded 17 Jan 2023Source
- 2 Details of encumbrancesEncumbarance Legal.pdf · uploaded 31 Jan 2023Source
- 3 a Details of encumbrances concerned to FinanceEncumbarance Legal.pdf · uploaded 31 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbarance Legal.pdf · uploaded 31 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed (2).pdf · uploaded 31 Jan 2023Source
- 1 Disclosure of sold/ booked inventorySold Unsold (1).pdf · uploaded 31 Jan 2023View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3_compressed.pdf · uploaded 31 Jan 2023Source
- 1 Proforma of Agreement for saleAgreement Draft_compressed.pdf · uploaded 31 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank ACC.pdf · uploaded 31 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterRavet Allotment Letter.pdf · uploaded 31 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementAgreement Ravet.pdf · uploaded 31 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200259354388_For_Asset_Based_Search_02_02_2023_18_06_40_249.pdf · uploaded 2 Feb 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsSachin Sir Disclosure.pdf · uploaded 2 Feb 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations Vineet Sir.pdf · uploaded 2 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer CertificateRavet.pdf · uploaded 3 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Waterfront 2021-22.pdf · uploaded 3 Feb 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront_11zon.pdf · uploaded 27 Jun 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Waterfront.pdf · uploaded 3 Jul 2023Source
- 2 Disclosure of sold/ booked inventoryI Trend Waterfront_compressed.pdf · uploaded 3 Jul 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ravet Architect Certificate_compressed.pdf · uploaded 24 Aug 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ravet Engineer Certificate.pdf · uploaded 24 Aug 2023Source
- 3 Disclosure of sold/ booked inventoryRavet Sold Unsold_compressed.pdf · uploaded 24 Aug 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Ravet.pdf · uploaded 24 Aug 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 27 Oct 2023Source
- 4 Disclosure of sold/ booked inventorySold Unsold_compressed.pdf · uploaded 27 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Ravet.pdf · uploaded 30 Oct 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed.pdf · uploaded 30 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Ravet.pdf · uploaded 26 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 20 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineet Certificate.pdf · uploaded 20 Jan 2024Source
- 5 Disclosure of sold/ booked inventorySold Unsold RAVET.pdf · uploaded 20 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE RAVET.pdf · uploaded 20 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certficate Waterfront.pdf · uploaded 20 Apr 2024Source
- 6 Disclosure of sold/ booked inventorySold Unsold Waterfront_compressed.pdf · uploaded 20 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certi.pdf · uploaded 22 Apr 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate form 3.pdf · uploaded 22 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Waterfront.pdf · uploaded 20 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate-Waterfront.pdf · uploaded 20 Jul 2024Source
- 7 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 20 Jul 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate Waterfront_compressed.pdf · uploaded 20 Jul 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Waterfront.pdf · uploaded 17 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Waterfront_com.pdf · uploaded 17 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Waterfront.pdf · uploaded 17 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold Certificate Waterfront.pdf · uploaded 17 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Waterfront.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Waterfront_compressed.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Waterfront.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold Waterfront_compressed (1).pdf · uploaded 20 Jan 2025View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Waterfront.pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cerificate_compressed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryRavet (1).pdf · uploaded 20 Apr 2025View
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 18/2, Sr No. 17/3/1 P
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Address
- Sr No. 17/3/1 P and 18/2, Bangalore - Mumbai Express Highway, RavetPIN 412101
- Village
- Ravet, Haveli taluka
- Location
- 18.52043, 73.85674
- Land area for this project
- 9,689 sq m (1,04,291 sq ft)
- Permissible built-up area
- 25,340 sq m (2,72,762 sq ft)
- Sanctioned built-up area
- 19,310 sq m (2,07,851 sq ft)
- Recreational open space
- 633 sq m (6,815 sq ft)
- Designated bank account
- 43
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Sr No. 17/3/1 P and 18/2
Boundaries
- North
- Part of Sr No 18
- South
- Part of Sr No 17 3 1 Being Area under reservation
- East
- Part of Sr No 16
- West
- Part of Sr No 19 and 27
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar. Hrishikesh Kulkarni | — |
| Chartered accountant | NPSR & ASSOCIATES- Nandkishor Lahoti | — |
| Chartered accountant | SPAK & Co | — |
| Engineer | Strudcom Consultants Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.
Itrend Waterfront in numbers
Registered deals, summarised
Deedo has 42 registered documents at Itrend Waterfront, from Sep 2021 to Aug 2026: 34 sales, 8 mortgages. The median registered sale since Sep 2021 works out to about ₹7,300 per sq ft, at a median of ₹44 L a deal; 9% of sales were resales.
- What is the price per sq ft at Itrend Waterfront?
- The median registered sale since Sep 2021 works out to about ₹7,300 per sq ft, at a median of ₹44 L a deal; 9% of sales were resales.
- How many properties have been sold at Itrend Waterfront?
- 34 sales are registered at Itrend Waterfront, 3 of them resales.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Itrend Waterfront by Deedo, last updated with deals registered in Aug 2026.
Latest deal · Mortgage · Aug 2026