Neev Sai Developers
Deedo IDDD-MX3VOf 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 9 mo late.
Delivery record
2 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Itrend LifeP52100021202 | Wakad | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Itrend Life 2P52100028333 | Wakad | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Itrend Life 3P52100029658 | Wakad | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Itrend WaterfrontP52100030538 | Ravet | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | +14 mo* |
| Itrend City LifeP52100048252 | Hinjavadi (Ct) | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 mo |
Neev Sai Developers, in questions
Does Neev Sai Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 9 mo late. Across Maharashtra, 73% kept their date.
How many projects has Neev Sai Developers registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Neev Sai Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.