Completion due May 2030Ravet, Pune 412101 |Promoter: Satkar Properties
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
- Buildings
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 May 2030
PR1260002601221- Registered
- 17 Jul 2026
- Promised
- 30 May 2030
Completion promised for 30 May 2030
PR1260002601290- Registered
- 23 Jul 2026
- Promised
- 30 May 2030
Completion promised for 30 May 2030
PR1260002601644- Registered
- 25 Aug 2026
- Promised
- 30 May 2030
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002601221 | 17 Jul 2026 | 30 May 2030 | — | Satkar Properties | Project page |
| PR1260002601290 | 23 Jul 2026 | 30 May 2030 | — | Satkar Properties | Project page |
| PR1260002601644 | 25 Aug 2026 | 30 May 2030 | — | Satkar Properties | Project page |
3 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
3 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ravet
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.