Completion due May 2030

Ravet, Pune 412101 |Promoter: Satkar Properties

17 Jul 2026Registered with MahaRERAFirst of 3 registrations
30 May 2030Promised completionLatest across registrations
3Buildings3 phases
58Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
3
Phases
3
Buildings
3

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.64558, 73.74252
Calistara is at latitude 18.64558, longitude 73.74252.

Also registered as

Calistara Tower 1Calistara Tower 3Calistara Tower 2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 May 2030

PR1260002601221
Registered
17 Jul 2026
Promised
30 May 2030

Completion promised for 30 May 2030

PR1260002601290
Registered
23 Jul 2026
Promised
30 May 2030

Completion promised for 30 May 2030

PR1260002601644
Registered
25 Aug 2026
Promised
30 May 2030

3 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR126000260122117 Jul 202630 May 2030—Satkar PropertiesProject page
PR126000260129023 Jul 202630 May 2030—Satkar PropertiesProject page
PR126000260164425 Aug 202630 May 2030—Satkar PropertiesProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Tower-1154
Tower-261030
Tower-361024

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificatePR1260002601221 · 17 Jul 2026ViewSource
  • Registration certificatePR1260002601290 · 23 Jul 2026ViewSource
  • Registration certificatePR1260002601644 · 25 Aug 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ravet

Survey, CTS, gat or plot numbers

8/2BSurvey No. 8/2A

Source: registration certificates, as stated there.