Punepune (M Corp.), Pune
10 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects1
Registrations1
Completion still due10 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Punepune (M Corp.)
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| CentralvistaNaiknavare Developers Pvt. Ltd. | P52100080806 | 10 Jul 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
Nearby: other localities in Pune City
Pune (M Corp.) · 1,232 projectsKeshavnagarmundwa · 26 projectsPune (Cb) · 24 projectsKeshavnagar Mundwa · 18 projectsShivajinagar Bhamburda · 18 projectsKondhwa Budruk · 6 projectsAundh · 4 projectsGultekadi · 4 projectsBibwewadi-Munjeri · 3 projectsErandwane North · 3 projectsSadashiv Peth · 3 projectsBhamburda · 2 projects
Most active promoters
- Naiknavare Developers Pvt. Ltd.1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology