Completion was pushed back 4 months, to Jul 2027; 2 listings and orders with MahaRERA on record; 41% of its units are booked.

Pune (M Corp.), Pune 411037 · by Classic Promoters And Builders Pvt. Ltd · 0% of its projects kept the RERA date

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027Regulatory2 listings and ordersLatest: Regulatory order, 2025Sales41% booked226 of 550 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • P52100017521Registered 23 Aug 2018, completion promised 31 Dec 2026.
  • P52100017591Registered 28 Aug 2018, completion promised 31 Mar 2027, revised to 31 Jul 2027.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory record2

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order14 Nov 2025Matched by RERA number

    Regulatory order: PROJECT NAME: SOLITAIRE BUSINESS HUB PHASE II, SOLITAIRE WORLD (Regulatory Case No. 415 OF 2025) dated 14 Nov, 2025.

  • Regulatory order26 Dec 2024Matched by RERA number

    Regulatory order: PROJECT NAME: SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORLD (Regulatory Case No. 310 OF 2024) dated 26 Dec 2024.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001752123 Aug 201831 Dec 202631 Dec 2026Classic Promoters and Builders Private LimitedProject page
P5210001759128 Aug 201831 Mar 202731 Jul 2027Classic Promoters and Builders Private LimitedProject page
Documents1,019

2 documents held by Deedo, 1,017 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100017521 · 14 Aug 2026ViewSource
  • Registration certificateP52100017591 · 14 Aug 2026ViewSource

Finance

  • PAN CardP52100017521 · PAN .pdf · uploaded 16 Oct 2019Source
  • PAN CardP52100017591 · PAN .pdf · uploaded 16 Oct 2019Source

Legal

  • Legal Title reportP52100017521 · Legal title report.pdf · uploaded 31 Jul 2018Source
  • Legal Title reportP52100017591 · Legal title report.pdf · uploaded 31 Jul 2018Source
  • Declaration Form BP52100017521 · Promoter declartion SBH Phase I.pdf · uploaded 3 Aug 2018Source
  • Declaration Form BP52100017591 · Promoter declartion SBH Phsae II.pdf · uploaded 3 Aug 2018Source
Show all 1019 documentsShow fewer documents

Legal

  • OtherP52100017521 · Supplementory Deed Part I.pdf · uploaded 27 Nov 2018Source
  • OtherP52100017521 · Supplementory Deed Part II.pdf · uploaded 27 Nov 2018Source
  • OtherP52100017591 · Supplementory Deed Part I.pdf · uploaded 27 Nov 2018Source
  • OtherP52100017591 · Supplementory Deed Part II.pdf · uploaded 27 Nov 2018Source
  • OtherP52100017521 · SBH PH I Declaration.pdf · uploaded 8 Nov 2019Source
  • OtherP52100017521 · Supplimentary Deed Part I 1-12.pdf · uploaded 17 Jan 2020Source
  • OtherP52100017521 · Supplimentary Deed Part 2 13 27.pdf · uploaded 17 Jan 2020Source
  • OtherP52100017591 · Supplimentary Deed Part I 1-12.pdf · uploaded 17 Jan 2020Source
  • OtherP52100017591 · Supplimentary Deed Part 2 13 27.pdf · uploaded 17 Jan 2020Source
  • Legal Title reportP52100017521 · Updated TRS Solitaire World 09092021.pdf · uploaded 15 Oct 2021Source
  • Legal Title reportP52100017591 · Updated TRS Solitaire World 09092021.pdf · uploaded 15 Oct 2021Source
  • Declaration Form BP52100017591 · sharp scanner_20230607_151831.pdf · uploaded 7 Jun 2023Source
  • Declaration Form BP52100017521 · SBH PH I - Revised form B.pdf · uploaded 29 Mar 2025Source

Migrated

  • 1 Building Plan Approval (IOD)P52100017521 · 1_17.pdf · uploaded 14 Apr 2018Source
  • 2 Building Plan Approval (IOD)P52100017521 · 8_17.pdf · uploaded 14 Apr 2018Source
  • 3 Building Plan Approval (IOD)P52100017521 · 9_17.pdf · uploaded 14 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100017521 · CC.pdf · uploaded 14 Apr 2018Source
  • 1 Building Plan Approval (IOD)P52100017591 · 1_17.pdf · uploaded 14 Apr 2018Source
  • 2 Building Plan Approval (IOD)P52100017591 · 8_17.pdf · uploaded 14 Apr 2018Source
  • 3 Building Plan Approval (IOD)P52100017591 · 9_17.pdf · uploaded 14 Apr 2018Source
  • 4 Building Plan Approval (IOD)P52100017591 · 10_17.pdf · uploaded 14 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100017591 · CC.pdf · uploaded 14 Apr 2018Source
  • 1 Copy of the legal title reportP52100017521 · Legal title report.pdf · uploaded 31 Jul 2018Source
  • 1 Details of encumbrancesP52100017521 · Encumbrances Certificate SBH PH I.pdf · uploaded 31 Jul 2018Source
  • 1 Copy of Layout Approval (in case of layout)P52100017521 · Buiulding Layout.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH Phase I Architect Cert 05072018.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · 1SBH Phase I Engineers Certificate 3718.pdf · uploaded 31 Jul 2018Source
  • 1 Copy of the legal title reportP52100017591 · Legal title report.pdf · uploaded 31 Jul 2018Source
  • 1 Details of encumbrancesP52100017591 · Encumbrance Certificate SBH PH II.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · SBH Phase II Architect Certificate 05072018.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · SBH Phase II Engineers Certificate 3718.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of CA (Form 3)P52100017521 · Solitaire Business Hub Phase 1.pdf · uploaded 2 Aug 2018Source
  • 1 Certificates of CA (Form 3)P52100017591 · Solitaire Business Hub Phase 2-ilovepdf-compressed.pdf · uploaded 2 Aug 2018Source
  • 1 Declaration in FORM BP52100017521 · Promoter declartion SBH Phase I.pdf · uploaded 3 Aug 2018Source
  • 1 Proforma of Allotment letterP52100017521 · ATS Solitaire Business Hub 1 Solitaire World.pdf · uploaded 3 Aug 2018Source
  • 2 Proforma of Allotment letterP52100017521 · Allotment letter SBH PH 1.pdf · uploaded 3 Aug 2018Source
  • 1 Copy of Layout Approval (in case of layout)P52100017591 · SBH Ph2 Floor plan.pdf · uploaded 3 Aug 2018Source
  • 1 Declaration in FORM BP52100017591 · Promoter declartion SBH Phsae II.pdf · uploaded 3 Aug 2018Source
  • 1 Proforma of Allotment letterP52100017591 · ATS Solitaire Business Hub 2 Solitaire World.pdf · uploaded 3 Aug 2018Source
  • 2 Proforma of Allotment letterP52100017591 · Allotment letter SBH PH 2.pdf · uploaded 3 Aug 2018Source
  • 1 OtherP52100017521 · Supplementory Deed Part I.pdf · uploaded 27 Nov 2018Source
  • 2 OtherP52100017521 · Supplementory Deed Part II.pdf · uploaded 27 Nov 2018Source
  • 1 OtherP52100017591 · Supplementory Deed Part I.pdf · uploaded 27 Nov 2018Source
  • 2 OtherP52100017591 · Supplementory Deed Part II.pdf · uploaded 27 Nov 2018Source
  • 2 Copy of Layout Approval (in case of layout)P52100017521 · 1-39_layout.pdf · uploaded 25 Jun 2019Source
  • 4 Building Plan Approval (IOD)P52100017521 · 16-39_SBH1.pdf · uploaded 25 Jun 2019Source
  • 5 Building Plan Approval (IOD)P52100017521 · 17-39_SBH1n2.pdf · uploaded 25 Jun 2019Source
  • 6 Building Plan Approval (IOD)P52100017521 · 25-39_SBH1.pdf · uploaded 25 Jun 2019Source
  • 2 Copy of Layout Approval (in case of layout)P52100017591 · 1-39_layout.pdf · uploaded 25 Jun 2019Source
  • 5 Building Plan Approval (IOD)P52100017591 · 17-39_SBH1n2.pdf · uploaded 25 Jun 2019Source
  • 6 Building Plan Approval (IOD)P52100017591 · 18-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • 7 Building Plan Approval (IOD)P52100017591 · 19-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • 8 Building Plan Approval (IOD)P52100017591 · 20-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100017521 · SBH P1_compressed.pdf · uploaded 30 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100017591 · SBH P 2_compressed.pdf · uploaded 30 Sep 2019Source
  • 7 Building Plan Approval (IOD)P52100017521 · 1.pdf · uploaded 15 Oct 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100017521 · CC.pdf · uploaded 15 Oct 2019Source
  • 9 Building Plan Approval (IOD)P52100017591 · 1.pdf · uploaded 15 Oct 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100017591 · CC.pdf · uploaded 15 Oct 2019Source
  • 1 PAN CardP52100017521 · PAN .pdf · uploaded 16 Oct 2019Source
  • 1 PAN CardP52100017591 · PAN .pdf · uploaded 16 Oct 2019Source
  • 3 OtherP52100017521 · SBH PH I Declaration.pdf · uploaded 8 Nov 2019Source
  • 4 OtherP52100017521 · Supplimentary Deed Part I 1-12.pdf · uploaded 17 Jan 2020Source
  • 5 OtherP52100017521 · Supplimentary Deed Part 2 13 27.pdf · uploaded 17 Jan 2020Source
  • 3 OtherP52100017591 · Supplimentary Deed Part I 1-12.pdf · uploaded 17 Jan 2020Source
  • 4 OtherP52100017591 · Supplimentary Deed Part 2 13 27.pdf · uploaded 17 Jan 2020Source
  • 8 Building Plan Approval (IOD)P52100017521 · 16 SBH 1.pdf · uploaded 15 Feb 2020Source
  • 9 Building Plan Approval (IOD)P52100017521 · 17 SBH 1.pdf · uploaded 15 Feb 2020Source
  • 10 Building Plan Approval (IOD)P52100017521 · 24 SBH I.pdf · uploaded 15 Feb 2020Source
  • 11 Building Plan Approval (IOD)P52100017521 · 26 WP SBH I.pdf · uploaded 15 Feb 2020Source
  • 12 Building Plan Approval (IOD)P52100017521 · 27 WP SBH I SBH II.pdf · uploaded 15 Feb 2020Source
  • 13 Building Plan Approval (IOD)P52100017521 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • 14 Building Plan Approval (IOD)P52100017521 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100017521 · CC 2724 19 dtd 05022020.pdf · uploaded 15 Feb 2020Source
  • 10 Building Plan Approval (IOD)P52100017591 · 18 SBH 2.pdf · uploaded 15 Feb 2020Source
  • 11 Building Plan Approval (IOD)P52100017591 · 19 SBH 2.pdf · uploaded 15 Feb 2020Source
  • 12 Building Plan Approval (IOD)P52100017591 · 27 WP SBH I SBH II.pdf · uploaded 15 Feb 2020Source
  • 13 Building Plan Approval (IOD)P52100017591 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100017591 · CC 2724 19 dtd 05022020.pdf · uploaded 15 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100017521 · download.pdf · uploaded 8 Jul 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100017591 · SBH 2.pdf · uploaded 8 Jul 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100017521 · SBH I.pdf · uploaded 19 Feb 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100017591 · SBH II.pdf · uploaded 19 Feb 2021Source
  • 3 Copy of Layout Approval (in case of layout)P52100017521 · 1- 38.pdf · uploaded 4 Mar 2021Source
  • 15 Building Plan Approval (IOD)P52100017521 · 2-38.pdf · uploaded 4 Mar 2021Source
  • 16 Building Plan Approval (IOD)P52100017521 · 3-38.pdf · uploaded 4 Mar 2021Source
  • 17 Building Plan Approval (IOD)P52100017521 · 4-38.pdf · uploaded 4 Mar 2021Source
  • 18 Building Plan Approval (IOD)P52100017521 · 5-38.pdf · uploaded 4 Mar 2021Source
  • 19 Building Plan Approval (IOD)P52100017521 · 6-38.pdf · uploaded 4 Mar 2021Source
  • 20 Building Plan Approval (IOD)P52100017521 · 7-38.pdf · uploaded 4 Mar 2021Source
  • 21 Building Plan Approval (IOD)P52100017521 · 8-38.pdf · uploaded 4 Mar 2021Source
  • 22 Building Plan Approval (IOD)P52100017521 · 9-38.pdf · uploaded 4 Mar 2021Source
  • 23 Building Plan Approval (IOD)P52100017521 · 10-38.pdf · uploaded 4 Mar 2021Source
  • 24 Building Plan Approval (IOD)P52100017521 · 11-38.pdf · uploaded 4 Mar 2021Source
  • 25 Building Plan Approval (IOD)P52100017521 · 11-38.pdf · uploaded 4 Mar 2021Source
  • 26 Building Plan Approval (IOD)P52100017521 · 12-38.pdf · uploaded 4 Mar 2021Source
  • 27 Building Plan Approval (IOD)P52100017521 · 13-38.pdf · uploaded 4 Mar 2021Source
  • 28 Building Plan Approval (IOD)P52100017521 · 14-38.pdf · uploaded 4 Mar 2021Source
  • 29 Building Plan Approval (IOD)P52100017521 · 15-38.pdf · uploaded 4 Mar 2021Source
  • 30 Building Plan Approval (IOD)P52100017521 · 16-38.pdf · uploaded 4 Mar 2021Source
  • 31 Building Plan Approval (IOD)P52100017521 · 17-38.pdf · uploaded 4 Mar 2021Source
  • 32 Building Plan Approval (IOD)P52100017521 · 18-38.pdf · uploaded 4 Mar 2021Source
  • 33 Building Plan Approval (IOD)P52100017521 · 19-38.pdf · uploaded 4 Mar 2021Source
  • 34 Building Plan Approval (IOD)P52100017521 · 20-38.pdf · uploaded 4 Mar 2021Source
  • 35 Building Plan Approval (IOD)P52100017521 · 21-38.pdf · uploaded 4 Mar 2021Source
  • 36 Building Plan Approval (IOD)P52100017521 · 22-38.pdf · uploaded 4 Mar 2021Source
  • 37 Building Plan Approval (IOD)P52100017521 · 23-38.pdf · uploaded 4 Mar 2021Source
  • 38 Building Plan Approval (IOD)P52100017521 · 23-38.pdf · uploaded 4 Mar 2021Source
  • 39 Building Plan Approval (IOD)P52100017521 · 24-38.pdf · uploaded 4 Mar 2021Source
  • 40 Building Plan Approval (IOD)P52100017521 · 25-38.pdf · uploaded 4 Mar 2021Source
  • 41 Building Plan Approval (IOD)P52100017521 · 26-38.pdf · uploaded 4 Mar 2021Source
  • 42 Building Plan Approval (IOD)P52100017521 · 27-38.pdf · uploaded 4 Mar 2021Source
  • 43 Building Plan Approval (IOD)P52100017521 · 28-38.pdf · uploaded 4 Mar 2021Source
  • 44 Building Plan Approval (IOD)P52100017521 · 28-38.pdf · uploaded 4 Mar 2021Source
  • 45 Building Plan Approval (IOD)P52100017521 · 29-38.pdf · uploaded 4 Mar 2021Source
  • 46 Building Plan Approval (IOD)P52100017521 · 30-38.pdf · uploaded 4 Mar 2021Source
  • 47 Building Plan Approval (IOD)P52100017521 · 31-38.pdf · uploaded 4 Mar 2021Source
  • 48 Building Plan Approval (IOD)P52100017521 · 32-38.pdf · uploaded 4 Mar 2021Source
  • 49 Building Plan Approval (IOD)P52100017521 · 33-38.pdf · uploaded 4 Mar 2021Source
  • 50 Building Plan Approval (IOD)P52100017521 · 34-38.pdf · uploaded 4 Mar 2021Source
  • 51 Building Plan Approval (IOD)P52100017521 · 35-38.pdf · uploaded 4 Mar 2021Source
  • 52 Building Plan Approval (IOD)P52100017521 · 36-38.pdf · uploaded 4 Mar 2021Source
  • 53 Building Plan Approval (IOD)P52100017521 · 37-38.pdf · uploaded 4 Mar 2021Source
  • 54 Building Plan Approval (IOD)P52100017521 · 38-38.pdf · uploaded 4 Mar 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentP52100017521 · Commencement Certificate CC 1454 20 dtd 1812 2020.pdf · uploaded 4 Mar 2021Source
  • 3 Copy of Layout Approval (in case of layout)P52100017591 · 1- 38.pdf · uploaded 4 Mar 2021Source
  • 14 Building Plan Approval (IOD)P52100017591 · 2-38.pdf · uploaded 4 Mar 2021Source
  • 15 Building Plan Approval (IOD)P52100017591 · 3-38.pdf · uploaded 4 Mar 2021Source
  • 16 Building Plan Approval (IOD)P52100017591 · 4-38.pdf · uploaded 4 Mar 2021Source
  • 17 Building Plan Approval (IOD)P52100017591 · 5-38.pdf · uploaded 4 Mar 2021Source
  • 18 Building Plan Approval (IOD)P52100017591 · 6-38.pdf · uploaded 4 Mar 2021Source
  • 19 Building Plan Approval (IOD)P52100017591 · 7-38.pdf · uploaded 4 Mar 2021Source
  • 20 Building Plan Approval (IOD)P52100017591 · 8-38.pdf · uploaded 4 Mar 2021Source
  • 21 Building Plan Approval (IOD)P52100017591 · 9-38.pdf · uploaded 4 Mar 2021Source
  • 22 Building Plan Approval (IOD)P52100017591 · 10-38.pdf · uploaded 4 Mar 2021Source
  • 23 Building Plan Approval (IOD)P52100017591 · 11-38.pdf · uploaded 4 Mar 2021Source
  • 24 Building Plan Approval (IOD)P52100017591 · 12-38.pdf · uploaded 4 Mar 2021Source
  • 25 Building Plan Approval (IOD)P52100017591 · 13-38.pdf · uploaded 4 Mar 2021Source
  • 26 Building Plan Approval (IOD)P52100017591 · 14-38.pdf · uploaded 4 Mar 2021Source
  • 27 Building Plan Approval (IOD)P52100017591 · 15-38.pdf · uploaded 4 Mar 2021Source
  • 28 Building Plan Approval (IOD)P52100017591 · 16-38.pdf · uploaded 4 Mar 2021Source
  • 29 Building Plan Approval (IOD)P52100017591 · 17-38.pdf · uploaded 4 Mar 2021Source
  • 30 Building Plan Approval (IOD)P52100017591 · 18-38.pdf · uploaded 4 Mar 2021Source
  • 31 Building Plan Approval (IOD)P52100017591 · 19-38.pdf · uploaded 4 Mar 2021Source
  • 32 Building Plan Approval (IOD)P52100017591 · 20-38.pdf · uploaded 4 Mar 2021Source
  • 33 Building Plan Approval (IOD)P52100017591 · 21-38.pdf · uploaded 4 Mar 2021Source
  • 34 Building Plan Approval (IOD)P52100017591 · 22-38.pdf · uploaded 4 Mar 2021Source
  • 35 Building Plan Approval (IOD)P52100017591 · 23-38.pdf · uploaded 4 Mar 2021Source
  • 36 Building Plan Approval (IOD)P52100017591 · 23-38.pdf · uploaded 4 Mar 2021Source
  • 37 Building Plan Approval (IOD)P52100017591 · 24-38.pdf · uploaded 4 Mar 2021Source
  • 38 Building Plan Approval (IOD)P52100017591 · 25-38.pdf · uploaded 4 Mar 2021Source
  • 39 Building Plan Approval (IOD)P52100017591 · 26-38.pdf · uploaded 4 Mar 2021Source
  • 40 Building Plan Approval (IOD)P52100017591 · 27-38.pdf · uploaded 4 Mar 2021Source
  • 41 Building Plan Approval (IOD)P52100017591 · 28-38.pdf · uploaded 4 Mar 2021Source
  • 42 Building Plan Approval (IOD)P52100017591 · 29-38.pdf · uploaded 4 Mar 2021Source
  • 43 Building Plan Approval (IOD)P52100017591 · 29-38.pdf · uploaded 4 Mar 2021Source
  • 44 Building Plan Approval (IOD)P52100017591 · 30-38.pdf · uploaded 4 Mar 2021Source
  • 45 Building Plan Approval (IOD)P52100017591 · 31-38.pdf · uploaded 4 Mar 2021Source
  • 46 Building Plan Approval (IOD)P52100017591 · 32-38.pdf · uploaded 4 Mar 2021Source
  • 47 Building Plan Approval (IOD)P52100017591 · 33-38.pdf · uploaded 4 Mar 2021Source
  • 48 Building Plan Approval (IOD)P52100017591 · 34-38.pdf · uploaded 4 Mar 2021Source
  • 49 Building Plan Approval (IOD)P52100017591 · 35-38.pdf · uploaded 4 Mar 2021Source
  • 50 Building Plan Approval (IOD)P52100017591 · 36-38.pdf · uploaded 4 Mar 2021Source
  • 51 Building Plan Approval (IOD)P52100017591 · 37-38.pdf · uploaded 4 Mar 2021Source
  • 52 Building Plan Approval (IOD)P52100017591 · 38-38.pdf · uploaded 4 Mar 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentP52100017591 · Commencement Certificate CC 1454 20 dtd 1812 2020.pdf · uploaded 4 Mar 2021Source
  • 2 Details of encumbrancesP52100017521 · SBH I Encumbrances.pdf · uploaded 24 Mar 2021Source
  • 2 Details of encumbrancesP52100017591 · SBH II Encumbrances.pdf · uploaded 24 Mar 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100017521 · SW SBH PHASE 1 Build 1.pdf · uploaded 5 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100017591 · SW SBH II Build -1.pdf · uploaded 5 Jul 2021Source
  • 2 Disclosure of sold/ booked inventoryP52100017591 · SW SBH II Build -2.pdf · uploaded 5 Jul 2021Source
  • 3 Disclosure of sold/ booked inventoryP52100017591 · SW SBH II Build 3.pdf · uploaded 5 Jul 2021Source
  • 4 Disclosure of sold/ booked inventoryP52100017591 · SW SBH II Build 4.pdf · uploaded 5 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · SW SBH 1 Form 2A May-21.pdf · uploaded 16 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · SW SBH 2 Form 2A May-21.pdf · uploaded 16 Jul 2021Source
  • 2 Disclosure of sold/ booked inventoryP52100017521 · SW SBH 1 Building -1.pdf · uploaded 13 Aug 2021Source
  • 5 Disclosure of sold/ booked inventoryP52100017591 · SW SBH 2 Building -1.pdf · uploaded 13 Aug 2021Source
  • 6 Disclosure of sold/ booked inventoryP52100017591 · SW SBH 2 Building -2.pdf · uploaded 13 Aug 2021Source
  • 7 Disclosure of sold/ booked inventoryP52100017591 · SW SBH 2 Building -3.pdf · uploaded 13 Aug 2021Source
  • 8 Disclosure of sold/ booked inventoryP52100017591 · SW SBH 2 Building -4.pdf · uploaded 13 Aug 2021Source
  • 4 Copy of Layout Approval (in case of layout)P52100017521 · 1_42 TA W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 55 Building Plan Approval (IOD)P52100017521 · 2_42 TA.pdf · uploaded 2 Sep 2021Source
  • 56 Building Plan Approval (IOD)P52100017521 · 3_42 TA.pdf · uploaded 2 Sep 2021Source
  • 57 Building Plan Approval (IOD)P52100017521 · 4_ 42 TA.pdf · uploaded 2 Sep 2021Source
  • 58 Building Plan Approval (IOD)P52100017521 · 5_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 59 Building Plan Approval (IOD)P52100017521 · 6_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 60 Building Plan Approval (IOD)P52100017521 · 7_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 61 Building Plan Approval (IOD)P52100017521 · 8_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 62 Building Plan Approval (IOD)P52100017521 · 9_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 63 Building Plan Approval (IOD)P52100017521 · 10_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 64 Building Plan Approval (IOD)P52100017521 · 11_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 65 Building Plan Approval (IOD)P52100017521 · 12_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 66 Building Plan Approval (IOD)P52100017521 · 13_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 67 Building Plan Approval (IOD)P52100017521 · 14_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 68 Building Plan Approval (IOD)P52100017521 · 15_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 69 Building Plan Approval (IOD)P52100017521 · 16_42 TA.pdf · uploaded 2 Sep 2021Source
  • 70 Building Plan Approval (IOD)P52100017521 · 17_42 TA.pdf · uploaded 2 Sep 2021Source
  • 71 Building Plan Approval (IOD)P52100017521 · 18_42 TA.pdf · uploaded 2 Sep 2021Source
  • 72 Building Plan Approval (IOD)P52100017521 · 19_42 TA.pdf · uploaded 2 Sep 2021Source
  • 73 Building Plan Approval (IOD)P52100017521 · 20_42 TA.pdf · uploaded 2 Sep 2021Source
  • 74 Building Plan Approval (IOD)P52100017521 · 21_42 TA.pdf · uploaded 2 Sep 2021Source
  • 75 Building Plan Approval (IOD)P52100017521 · 22_42 TA.pdf · uploaded 2 Sep 2021Source
  • 76 Building Plan Approval (IOD)P52100017521 · 23_42 TA.pdf · uploaded 2 Sep 2021Source
  • 77 Building Plan Approval (IOD)P52100017521 · 24_42 TA.pdf · uploaded 2 Sep 2021Source
  • 78 Building Plan Approval (IOD)P52100017521 · 25_42 TA.pdf · uploaded 2 Sep 2021Source
  • 79 Building Plan Approval (IOD)P52100017521 · 26_42 TA.pdf · uploaded 2 Sep 2021Source
  • 80 Building Plan Approval (IOD)P52100017521 · 27_42 TA.pdf · uploaded 2 Sep 2021Source
  • 81 Building Plan Approval (IOD)P52100017521 · 28_42 W1.pdf · uploaded 2 Sep 2021Source
  • 82 Building Plan Approval (IOD)P52100017521 · 29_42 W1.pdf · uploaded 2 Sep 2021Source
  • 83 Building Plan Approval (IOD)P52100017521 · 30_42 W1.pdf · uploaded 2 Sep 2021Source
  • 84 Building Plan Approval (IOD)P52100017521 · 31_42 W2.pdf · uploaded 2 Sep 2021Source
  • 85 Building Plan Approval (IOD)P52100017521 · 32_42 W2.pdf · uploaded 2 Sep 2021Source
  • 86 Building Plan Approval (IOD)P52100017521 · 33_42 W2.pdf · uploaded 2 Sep 2021Source
  • 87 Building Plan Approval (IOD)P52100017521 · 34_42 W3.pdf · uploaded 2 Sep 2021Source
  • 88 Building Plan Approval (IOD)P52100017521 · 35_42 W3.pdf · uploaded 2 Sep 2021Source
  • 89 Building Plan Approval (IOD)P52100017521 · 36_42 W3.pdf · uploaded 2 Sep 2021Source
  • 90 Building Plan Approval (IOD)P52100017521 · 37_42 W4.pdf · uploaded 2 Sep 2021Source
  • 91 Building Plan Approval (IOD)P52100017521 · 38_42 W4.pdf · uploaded 2 Sep 2021Source
  • 92 Building Plan Approval (IOD)P52100017521 · 39_42 W4.pdf · uploaded 2 Sep 2021Source
  • 93 Building Plan Approval (IOD)P52100017521 · 40_42 W4.pdf · uploaded 2 Sep 2021Source
  • 94 Building Plan Approval (IOD)P52100017521 · 41_42 W4.pdf · uploaded 2 Sep 2021Source
  • 95 Building Plan Approval (IOD)P52100017521 · 42_42 W4.pdf · uploaded 2 Sep 2021Source
  • 5 Commencement Certificates / NA Order for plotted developmentP52100017521 · CC 1364 21 dt 23082021.pdf · uploaded 2 Sep 2021Source
  • 4 Copy of Layout Approval (in case of layout)P52100017591 · 1_42 TA W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 53 Building Plan Approval (IOD)P52100017591 · 2_42 TA.pdf · uploaded 2 Sep 2021Source
  • 54 Building Plan Approval (IOD)P52100017591 · 3_42 TA.pdf · uploaded 2 Sep 2021Source
  • 55 Building Plan Approval (IOD)P52100017591 · 4_ 42 TA.pdf · uploaded 2 Sep 2021Source
  • 56 Building Plan Approval (IOD)P52100017591 · 5_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 57 Building Plan Approval (IOD)P52100017591 · 6_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 58 Building Plan Approval (IOD)P52100017591 · 7_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • 59 Building Plan Approval (IOD)P52100017591 · 8_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 60 Building Plan Approval (IOD)P52100017591 · 9_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 61 Building Plan Approval (IOD)P52100017591 · 10_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 62 Building Plan Approval (IOD)P52100017591 · 11_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 63 Building Plan Approval (IOD)P52100017591 · 12_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 64 Building Plan Approval (IOD)P52100017591 · 13_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 65 Building Plan Approval (IOD)P52100017591 · 14_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 66 Building Plan Approval (IOD)P52100017591 · 15_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • 67 Building Plan Approval (IOD)P52100017591 · 16_42 TA.pdf · uploaded 2 Sep 2021Source
  • 68 Building Plan Approval (IOD)P52100017591 · 17_42 TA.pdf · uploaded 2 Sep 2021Source
  • 69 Building Plan Approval (IOD)P52100017591 · 18_42 TA.pdf · uploaded 2 Sep 2021Source
  • 70 Building Plan Approval (IOD)P52100017591 · 19_42 TA.pdf · uploaded 2 Sep 2021Source
  • 71 Building Plan Approval (IOD)P52100017591 · 20_42 TA.pdf · uploaded 2 Sep 2021Source
  • 72 Building Plan Approval (IOD)P52100017591 · 21_42 TA.pdf · uploaded 2 Sep 2021Source
  • 73 Building Plan Approval (IOD)P52100017591 · 22_42 TA.pdf · uploaded 2 Sep 2021Source
  • 74 Building Plan Approval (IOD)P52100017591 · 23_42 TA.pdf · uploaded 2 Sep 2021Source
  • 75 Building Plan Approval (IOD)P52100017591 · 24_42 TA.pdf · uploaded 2 Sep 2021Source
  • 76 Building Plan Approval (IOD)P52100017591 · 25_42 TA.pdf · uploaded 2 Sep 2021Source
  • 77 Building Plan Approval (IOD)P52100017591 · 26_42 TA.pdf · uploaded 2 Sep 2021Source
  • 78 Building Plan Approval (IOD)P52100017591 · 27_42 TA.pdf · uploaded 2 Sep 2021Source
  • 79 Building Plan Approval (IOD)P52100017591 · 28_42 W1.pdf · uploaded 2 Sep 2021Source
  • 80 Building Plan Approval (IOD)P52100017591 · 29_42 W1.pdf · uploaded 2 Sep 2021Source
  • 81 Building Plan Approval (IOD)P52100017591 · 30_42 W1.pdf · uploaded 2 Sep 2021Source
  • 82 Building Plan Approval (IOD)P52100017591 · 31_42 W2.pdf · uploaded 2 Sep 2021Source
  • 83 Building Plan Approval (IOD)P52100017591 · 32_42 W2.pdf · uploaded 2 Sep 2021Source
  • 84 Building Plan Approval (IOD)P52100017591 · 33_42 W2.pdf · uploaded 2 Sep 2021Source
  • 85 Building Plan Approval (IOD)P52100017591 · 34_42 W3.pdf · uploaded 2 Sep 2021Source
  • 86 Building Plan Approval (IOD)P52100017591 · 35_42 W3.pdf · uploaded 2 Sep 2021Source
  • 87 Building Plan Approval (IOD)P52100017591 · 36_42 W3.pdf · uploaded 2 Sep 2021Source
  • 88 Building Plan Approval (IOD)P52100017591 · 37_42 W4.pdf · uploaded 2 Sep 2021Source
  • 89 Building Plan Approval (IOD)P52100017591 · 38_42 W4.pdf · uploaded 2 Sep 2021Source
  • 90 Building Plan Approval (IOD)P52100017591 · 39_42 W4.pdf · uploaded 2 Sep 2021Source
  • 91 Building Plan Approval (IOD)P52100017591 · 40_42 W4.pdf · uploaded 2 Sep 2021Source
  • 92 Building Plan Approval (IOD)P52100017591 · 41_42 W4.pdf · uploaded 2 Sep 2021Source
  • 93 Building Plan Approval (IOD)P52100017591 · 42_42 W4.pdf · uploaded 2 Sep 2021Source
  • 5 Commencement Certificates / NA Order for plotted developmentP52100017591 · CC 1364 21 dt 23082021.pdf · uploaded 2 Sep 2021Source
  • 1 Declaration about Commencement CertificateP52100017521 · SBH PH1 18_20.pdf · uploaded 4 Sep 2021Source
  • 2 Declaration about Commencement CertificateP52100017521 · SBH PH1 23_21.pdf · uploaded 4 Sep 2021Source
  • 1 Declaration about Commencement CertificateP52100017591 · SBH PH 2 18.pdf · uploaded 4 Sep 2021Source
  • 2 Declaration about Commencement CertificateP52100017591 · SBH PH 2 23.pdf · uploaded 4 Sep 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · SBH -I Form 2A Jun 2021.pdf · uploaded 14 Sep 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · SBH -II Form 2A Jun 2021.pdf · uploaded 14 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100017521 · Form 5 SBH Phase 1 20 - 21.pdf · uploaded 30 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100017591 · Form 5 SBH Phase 2 20 - 21.pdf · uploaded 30 Sep 2021Source
  • 3 Disclosure of sold/ booked inventoryP52100017521 · Sold Sept-21 SW SBH 1.pdf · uploaded 7 Oct 2021Source
  • 9 Disclosure of sold/ booked inventoryP52100017591 · DISCLOSURE OF SOLD SBH II B1.pdf · uploaded 8 Oct 2021Source
  • 10 Disclosure of sold/ booked inventoryP52100017591 · DISCLOSURE OF SOLD SBH II B2.pdf · uploaded 8 Oct 2021Source
  • 11 Disclosure of sold/ booked inventoryP52100017591 · DISCLOSURE OF SOLD SBH II B3.pdf · uploaded 8 Oct 2021Source
  • 12 Disclosure of sold/ booked inventoryP52100017591 · DISCLOSURE OF SOLD SBH II B4.pdf · uploaded 8 Oct 2021Source
  • 2 Copy of the legal title reportP52100017521 · Updated TRS Solitaire World 09092021.pdf · uploaded 15 Oct 2021Source
  • 2 Copy of the legal title reportP52100017591 · Updated TRS Solitaire World 09092021.pdf · uploaded 15 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · SBH II mAR 20.pdf · uploaded 5 Nov 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · SBH -II MAR 21.pdf · uploaded 5 Nov 2021Source
  • 3 Declaration about Commencement CertificateP52100017521 · 4 SW SBH PH 1 DEC 2021.pdf · uploaded 8 Jan 2022Source
  • 4 Disclosure of sold/ booked inventoryP52100017521 · SBH I Building 1 SOLD DISCLOSURE DEC 2021.pdf · uploaded 8 Jan 2022Source
  • 3 Declaration about Commencement CertificateP52100017591 · 5 SW SBH PH 2 DEC 2021.pdf · uploaded 8 Jan 2022Source
  • 13 Disclosure of sold/ booked inventoryP52100017591 · SBH II Building 1-4 Sold Disclosure Dec 2021.pdf · uploaded 8 Jan 2022Source
  • 4 Declaration about Commencement CertificateP52100017521 · SW SBH PH-1.pdf · uploaded 7 Apr 2022Source
  • 4 Declaration about Commencement CertificateP52100017591 · SW SBH PH 2.pdf · uploaded 7 Apr 2022Source
  • 14 Disclosure of sold/ booked inventoryP52100017591 · SBH PH -II - Jun 22- Bldg 1.pdf · uploaded 11 Jul 2022Source
  • 15 Disclosure of sold/ booked inventoryP52100017591 · SBH PH -II-Jun 22 - Bldg-2.pdf · uploaded 11 Jul 2022Source
  • 16 Disclosure of sold/ booked inventoryP52100017591 · SBH PH - II - Jun 22-Bldg-3.pdf · uploaded 11 Jul 2022Source
  • 17 Disclosure of sold/ booked inventoryP52100017591 · SBH PH - II - Jun 22- Bldg 4.pdf · uploaded 11 Jul 2022Source
  • 5 Disclosure of sold/ booked inventoryP52100017521 · SBH PH- I - Jun 22- Bldg 1_compressed.pdf · uploaded 12 Jul 2022Source
  • 1 CERSAI detailsP52100017521 · CERSAI_Search_Report_.pdf · uploaded 8 Aug 2022Source
  • 1 CERSAI detailsP52100017591 · CERSAI_Search_Report_.pdf · uploaded 8 Aug 2022Source
  • 2 CERSAI detailsP52100017591 · CERSAI_Search_Report.pdf · uploaded 8 Aug 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100017521 · Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) SBH PHASE 1.pdf · uploaded 30 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100017591 · Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) SBH PHASE-2.pdf · uploaded 30 Sep 2022Source
  • 5 Declaration about Commencement CertificateP52100017521 · Declaration of CC SBH PHASE 1.pdf · uploaded 12 Oct 2022Source
  • 5 Declaration about Commencement CertificateP52100017591 · Declaration of CC SBH PHASE 2.pdf · uploaded 12 Oct 2022Source
  • 6 Disclosure of sold/ booked inventoryP52100017521 · SBH_1_Buld_1_Sep_22.pdf · uploaded 21 Oct 2022Source
  • 18 Disclosure of sold/ booked inventoryP52100017591 · SBH_2.pdf · uploaded 21 Oct 2022Source
  • 5 Copy of Layout Approval (in case of layout)P52100017521 · Scan_0979-01_compressed.pdf · uploaded 10 Nov 2022Source
  • 96 Building Plan Approval (IOD)P52100017521 · Scan_0979-02_compressed.pdf · uploaded 10 Nov 2022Source
  • 97 Building Plan Approval (IOD)P52100017521 · Scan_0979-03_compressed.pdf · uploaded 10 Nov 2022Source
  • 98 Building Plan Approval (IOD)P52100017521 · Scan_0979-04_compressed.pdf · uploaded 10 Nov 2022Source
  • 99 Building Plan Approval (IOD)P52100017521 · Scan_0979-05_compressed.pdf · uploaded 10 Nov 2022Source
  • 100 Building Plan Approval (IOD)P52100017521 · Scan_0979-06_compressed.pdf · uploaded 10 Nov 2022Source
  • 101 Building Plan Approval (IOD)P52100017521 · Scan_0979-07_compressed.pdf · uploaded 10 Nov 2022Source
  • 102 Building Plan Approval (IOD)P52100017521 · Scan_0979-08_compressed.pdf · uploaded 10 Nov 2022Source
  • 103 Building Plan Approval (IOD)P52100017521 · Scan_0979-09_compressed.pdf · uploaded 10 Nov 2022Source
  • 104 Building Plan Approval (IOD)P52100017521 · Scan_0979-10.pdf · uploaded 10 Nov 2022Source
  • 105 Building Plan Approval (IOD)P52100017521 · Scan_0979-11.pdf · uploaded 10 Nov 2022Source
  • 106 Building Plan Approval (IOD)P52100017521 · Scan_0979-12.pdf · uploaded 10 Nov 2022Source
  • 107 Building Plan Approval (IOD)P52100017521 · Scan_0979-13.pdf · uploaded 10 Nov 2022Source
  • 108 Building Plan Approval (IOD)P52100017521 · Scan_0979-14.pdf · uploaded 10 Nov 2022Source
  • 109 Building Plan Approval (IOD)P52100017521 · Scan_0979-15.pdf · uploaded 10 Nov 2022Source
  • 110 Building Plan Approval (IOD)P52100017521 · Scan_0979-16_compressed.pdf · uploaded 10 Nov 2022Source
  • 111 Building Plan Approval (IOD)P52100017521 · Scan_0979-17.pdf · uploaded 10 Nov 2022Source
  • 112 Building Plan Approval (IOD)P52100017521 · Scan_0979-19_compressed.pdf · uploaded 10 Nov 2022Source
  • 113 Building Plan Approval (IOD)P52100017521 · Scan_0979-20_compressed.pdf · uploaded 10 Nov 2022Source
  • 114 Building Plan Approval (IOD)P52100017521 · Scan_0979-21_compressed.pdf · uploaded 10 Nov 2022Source
  • 115 Building Plan Approval (IOD)P52100017521 · Scan_0979-22_compressed.pdf · uploaded 10 Nov 2022Source
  • 116 Building Plan Approval (IOD)P52100017521 · Scan_0979-23_compressed.pdf · uploaded 10 Nov 2022Source
  • 117 Building Plan Approval (IOD)P52100017521 · Scan_0979-24_compressed.pdf · uploaded 10 Nov 2022Source
  • 118 Building Plan Approval (IOD)P52100017521 · Scan_0979-25_compressed.pdf · uploaded 10 Nov 2022Source
  • 119 Building Plan Approval (IOD)P52100017521 · Scan_0979-26_compressed.pdf · uploaded 10 Nov 2022Source
  • 120 Building Plan Approval (IOD)P52100017521 · Scan_0979-27_compressed.pdf · uploaded 10 Nov 2022Source
  • 121 Building Plan Approval (IOD)P52100017521 · Scan_0979-28_compressed.pdf · uploaded 10 Nov 2022Source
  • 122 Building Plan Approval (IOD)P52100017521 · Scan_0979-29_compressed.pdf · uploaded 10 Nov 2022Source
  • 123 Building Plan Approval (IOD)P52100017521 · Scan_0979-30_compressed.pdf · uploaded 10 Nov 2022Source
  • 124 Building Plan Approval (IOD)P52100017521 · Scan_0979-31_compressed.pdf · uploaded 10 Nov 2022Source
  • 125 Building Plan Approval (IOD)P52100017521 · Scan_0979-32_compressed.pdf · uploaded 10 Nov 2022Source
  • 126 Building Plan Approval (IOD)P52100017521 · Scan_0979-32_compressed.pdf · uploaded 10 Nov 2022Source
  • 127 Building Plan Approval (IOD)P52100017521 · Scan_0979-33_compressed.pdf · uploaded 10 Nov 2022Source
  • 128 Building Plan Approval (IOD)P52100017521 · Scan_0979-34_compressed.pdf · uploaded 10 Nov 2022Source
  • 129 Building Plan Approval (IOD)P52100017521 · Scan_0979-35_compressed.pdf · uploaded 10 Nov 2022Source
  • 130 Building Plan Approval (IOD)P52100017521 · Scan_0979-36_compressed.pdf · uploaded 10 Nov 2022Source
  • 131 Building Plan Approval (IOD)P52100017521 · Scan_0979-37_compressed.pdf · uploaded 10 Nov 2022Source
  • 132 Building Plan Approval (IOD)P52100017521 · Scan_0979-38_compressed.pdf · uploaded 10 Nov 2022Source
  • 133 Building Plan Approval (IOD)P52100017521 · Scan_0979-39_compressed.pdf · uploaded 10 Nov 2022Source
  • 134 Building Plan Approval (IOD)P52100017521 · Scan_0979-40_compressed.pdf · uploaded 10 Nov 2022Source
  • 135 Building Plan Approval (IOD)P52100017521 · Scan_0979-41_compressed.pdf · uploaded 10 Nov 2022Source
  • 136 Building Plan Approval (IOD)P52100017521 · Scan_0979-42_compressed.pdf · uploaded 10 Nov 2022Source
  • 137 Building Plan Approval (IOD)P52100017521 · Scan_0979-43_compressed.pdf · uploaded 10 Nov 2022Source
  • 6 Commencement Certificates / NA Order for plotted developmentP52100017521 · COMMENCEMENT CERTIFICATE.pdf · uploaded 10 Nov 2022Source
  • 6 Commencement Certificates / NA Order for plotted developmentP52100017591 · COMMENCEMENT CERTIFICATE.pdf · uploaded 10 Nov 2022Source
  • 5 Copy of Layout Approval (in case of layout)P52100017591 · Scan_0979-01_compressed.pdf · uploaded 11 Nov 2022Source
  • 94 Building Plan Approval (IOD)P52100017591 · Scan_0979-02_compressed.pdf · uploaded 11 Nov 2022Source
  • 95 Building Plan Approval (IOD)P52100017591 · Scan_0979-03_compressed.pdf · uploaded 11 Nov 2022Source
  • 96 Building Plan Approval (IOD)P52100017591 · Scan_0979-04_compressed.pdf · uploaded 11 Nov 2022Source
  • 97 Building Plan Approval (IOD)P52100017591 · Scan_0979-05_compressed.pdf · uploaded 11 Nov 2022Source
  • 98 Building Plan Approval (IOD)P52100017591 · Scan_0979-06_compressed.pdf · uploaded 11 Nov 2022Source
  • 99 Building Plan Approval (IOD)P52100017591 · Scan_0979-07_compressed.pdf · uploaded 11 Nov 2022Source
  • 100 Building Plan Approval (IOD)P52100017591 · Scan_0979-08_compressed.pdf · uploaded 11 Nov 2022Source
  • 101 Building Plan Approval (IOD)P52100017591 · Scan_0979-09_compressed.pdf · uploaded 11 Nov 2022Source
  • 102 Building Plan Approval (IOD)P52100017591 · Scan_0979-10.pdf · uploaded 11 Nov 2022Source
  • 103 Building Plan Approval (IOD)P52100017591 · Scan_0979-11.pdf · uploaded 11 Nov 2022Source
  • 104 Building Plan Approval (IOD)P52100017591 · Scan_0979-12.pdf · uploaded 11 Nov 2022Source
  • 105 Building Plan Approval (IOD)P52100017591 · Scan_0979-13.pdf · uploaded 11 Nov 2022Source
  • 106 Building Plan Approval (IOD)P52100017591 · Scan_0979-14.pdf · uploaded 11 Nov 2022Source
  • 107 Building Plan Approval (IOD)P52100017591 · Scan_0979-15.pdf · uploaded 11 Nov 2022Source
  • 108 Building Plan Approval (IOD)P52100017591 · Scan_0979-16_compressed.pdf · uploaded 11 Nov 2022Source
  • 109 Building Plan Approval (IOD)P52100017591 · Scan_0979-17.pdf · uploaded 11 Nov 2022Source
  • 110 Building Plan Approval (IOD)P52100017591 · Scan_0979-18_compressed.pdf · uploaded 11 Nov 2022Source
  • 111 Building Plan Approval (IOD)P52100017591 · Scan_0979-19_compressed.pdf · uploaded 11 Nov 2022Source
  • 112 Building Plan Approval (IOD)P52100017591 · Scan_0979-20_compressed.pdf · uploaded 11 Nov 2022Source
  • 113 Building Plan Approval (IOD)P52100017591 · Scan_0979-21_compressed.pdf · uploaded 11 Nov 2022Source
  • 114 Building Plan Approval (IOD)P52100017591 · Scan_0979-22_compressed.pdf · uploaded 11 Nov 2022Source
  • 115 Building Plan Approval (IOD)P52100017591 · Scan_0979-23_compressed.pdf · uploaded 11 Nov 2022Source
  • 116 Building Plan Approval (IOD)P52100017591 · Scan_0979-24_compressed.pdf · uploaded 11 Nov 2022Source
  • 117 Building Plan Approval (IOD)P52100017591 · Scan_0979-25_compressed.pdf · uploaded 11 Nov 2022Source
  • 118 Building Plan Approval (IOD)P52100017591 · Scan_0979-26_compressed.pdf · uploaded 11 Nov 2022Source
  • 119 Building Plan Approval (IOD)P52100017591 · Scan_0979-27_compressed.pdf · uploaded 11 Nov 2022Source
  • 120 Building Plan Approval (IOD)P52100017591 · Scan_0979-28_compressed.pdf · uploaded 11 Nov 2022Source
  • 121 Building Plan Approval (IOD)P52100017591 · Scan_0979-29_compressed.pdf · uploaded 11 Nov 2022Source
  • 122 Building Plan Approval (IOD)P52100017591 · Scan_0979-30_compressed.pdf · uploaded 11 Nov 2022Source
  • 123 Building Plan Approval (IOD)P52100017591 · Scan_0979-31_compressed.pdf · uploaded 11 Nov 2022Source
  • 124 Building Plan Approval (IOD)P52100017591 · Scan_0979-32_compressed.pdf · uploaded 11 Nov 2022Source
  • 125 Building Plan Approval (IOD)P52100017591 · Scan_0979-33_compressed.pdf · uploaded 11 Nov 2022Source
  • 126 Building Plan Approval (IOD)P52100017591 · Scan_0979-34_compressed.pdf · uploaded 11 Nov 2022Source
  • 127 Building Plan Approval (IOD)P52100017591 · Scan_0979-35_compressed.pdf · uploaded 11 Nov 2022Source
  • 128 Building Plan Approval (IOD)P52100017591 · Scan_0979-36_compressed.pdf · uploaded 11 Nov 2022Source
  • 129 Building Plan Approval (IOD)P52100017591 · Scan_0979-37_compressed.pdf · uploaded 11 Nov 2022Source
  • 130 Building Plan Approval (IOD)P52100017591 · Scan_0979-38_compressed.pdf · uploaded 11 Nov 2022Source
  • 131 Building Plan Approval (IOD)P52100017591 · Scan_0979-39_compressed.pdf · uploaded 11 Nov 2022Source
  • 132 Building Plan Approval (IOD)P52100017591 · Scan_0979-40_compressed.pdf · uploaded 11 Nov 2022Source
  • 133 Building Plan Approval (IOD)P52100017591 · Scan_0979-41_compressed.pdf · uploaded 11 Nov 2022Source
  • 134 Building Plan Approval (IOD)P52100017591 · Scan_0979-42_compressed.pdf · uploaded 11 Nov 2022Source
  • 135 Building Plan Approval (IOD)P52100017591 · Scan_0979-43_compressed.pdf · uploaded 11 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017521 · Form 2A SBH PH-1 Dec-22.pdf · uploaded 20 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017591 · Form 2A SBH PH-2 Dec-22.pdf · uploaded 20 Jan 2023Source
  • 7 Disclosure of sold/ booked inventoryP52100017521 · Sold_Disclosure_SBH_Phase I_SW_Dec_22.pdf · uploaded 27 Jan 2023Source
  • 19 Disclosure of sold/ booked inventoryP52100017591 · Sold_Disclosure_SBH_Phase II_SW_Dec_22.pdf · uploaded 27 Jan 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 OCT.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1DEC 18.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 MAR 19.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1MAY 19.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 AUG 19.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1OCT 19.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 FEB 20.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1MAY 20.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1UG 20.pdf · uploaded 20 Mar 2023Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 NOV 20.pdf · uploaded 20 Mar 2023Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH MAR 21.pdf · uploaded 20 Mar 2023Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1JUNE 21.pdf · uploaded 20 Mar 2023Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 SEP21.pdf · uploaded 20 Mar 2023Source
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · SBH 1 DEC21.pdf · uploaded 20 Mar 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · OCT 18.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 JAN 19.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 MAY 19.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 AUG 19.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 OCT 19.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 DEC 19.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 FEB 20.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 MAY 20.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 AUG 20.pdf · uploaded 20 Mar 2023Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 NOV 20.pdf · uploaded 20 Mar 2023Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 FEB 21.pdf · uploaded 20 Mar 2023Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 FEB 21.pdf · uploaded 20 Mar 2023Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 JUNE 21.pdf · uploaded 20 Mar 2023Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 SEP 21.pdf · uploaded 20 Mar 2023Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · SBH 1 DEC 21.pdf · uploaded 20 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · 2A OCT 18.pdf · uploaded 20 Mar 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · DEC 18.pdf · uploaded 20 Mar 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · MAR 19.pdf · uploaded 20 Mar 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · SBH 1 MAY 19.pdf · uploaded 20 Mar 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · AUG 19.pdf · uploaded 20 Mar 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · OCT 19.pdf · uploaded 20 Mar 2023Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017521 · FEB 20.pdf · uploaded 20 Mar 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · SBH 1 MAY 20.pdf · uploaded 20 Mar 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · AUG 20.pdf · uploaded 20 Mar 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · SBH 1 NOV 20.pdf · uploaded 20 Mar 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017521 · SBH1 FEB 21.pdf · uploaded 20 Mar 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017521 · JUNE 21.pdf · uploaded 20 Mar 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017521 · SBH 1 SEP 21.pdf · uploaded 20 Mar 2023Source
  • 2 Certificates of CA (Form 3)P52100017521 · OCT 18.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of CA (Form 3)P52100017521 · JAN 19.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of CA (Form 3)P52100017521 · MAY 19.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of CA (Form 3)P52100017521 · OCT 19.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of CA (Form 3)P52100017521 · FEB 20.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of CA (Form 3)P52100017521 · AUG 20.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of CA (Form 3)P52100017521 · NOV 20.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of CA (Form 3)P52100017521 · FEB 21_compressed.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of CA (Form 3)P52100017521 · JUNE 21.pdf · uploaded 20 Mar 2023Source
  • 11 Certificates of CA (Form 3)P52100017521 · SEP 21.pdf · uploaded 20 Mar 2023Source
  • 12 Certificates of CA (Form 3)P52100017521 · DEC 21.pdf · uploaded 20 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100017521 · DEC 21.pdf · uploaded 20 Mar 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · OCT 18.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · DEC 18.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · MAR 19.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · MAY 19.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · AUG 19.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · OCT 19.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · FEB 20.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · MAY 20.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · AUG 20.pdf · uploaded 20 Mar 2023Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · NOV 20.pdf · uploaded 20 Mar 2023Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · FEB 21.pdf · uploaded 20 Mar 2023Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · JUN 21.pdf · uploaded 20 Mar 2023Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · SEP 21.pdf · uploaded 20 Mar 2023Source
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · DEC 21.pdf · uploaded 20 Mar 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · MAR 21.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · June 21.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · sep 21.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · dec 21.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · mar 19.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · OCT 18.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · JAN 19.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · NO.pdf · uploaded 20 Mar 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · oct 18.pdf · uploaded 20 Mar 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · dec 18.pdf · uploaded 20 Mar 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · may 19.pdf · uploaded 20 Mar 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · nov 20.pdf · uploaded 20 Mar 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · aug 19.pdf · uploaded 20 Mar 2023Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100017591 · oct 19.pdf · uploaded 20 Mar 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · aug 20.pdf · uploaded 20 Mar 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · feb 20.pdf · uploaded 20 Mar 2023Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · oct 20.pdf · uploaded 20 Mar 2023Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · may 20.pdf · uploaded 20 Mar 2023Source
  • 8 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100017591 · feb 21.pdf · uploaded 20 Mar 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017591 · june 21.pdf · uploaded 20 Mar 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017591 · sep 21.pdf · uploaded 20 Mar 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017591 · dec 21.pdf · uploaded 20 Mar 2023Source
  • 2 Certificates of CA (Form 3)P52100017591 · AUG 19.pdf · uploaded 20 Mar 2023Source
  • 3 Certificates of CA (Form 3)P52100017591 · SBH JAN.pdf · uploaded 20 Mar 2023Source
  • 4 Certificates of CA (Form 3)P52100017591 · MAY 19 SBH 2.pdf · uploaded 20 Mar 2023Source
  • 5 Certificates of CA (Form 3)P52100017591 · AUG 19.pdf · uploaded 20 Mar 2023Source
  • 6 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_March 2020.pdf · uploaded 20 Mar 2023Source
  • 7 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_May 2020.pdf · uploaded 20 Mar 2023Source
  • 8 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_Aug 2020.pdf · uploaded 20 Mar 2023Source
  • 9 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_Nov 2020.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of CA (Form 3)P52100017591 · FEB 211111.pdf · uploaded 20 Mar 2023Source
  • 11 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_Jun 2021.pdf · uploaded 20 Mar 2023Source
  • 12 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_Sep 2021.pdf · uploaded 20 Mar 2023Source
  • 13 Certificates of CA (Form 3)P52100017591 · Form 3_SBH-2_Dec 2021.pdf · uploaded 20 Mar 2023Source
  • 14 Certificates of CA (Form 3)P52100017591 · MAY 19.pdf · uploaded 20 Mar 2023Source
  • 15 Certificates of CA (Form 3)P52100017591 · AUG 19.pdf · uploaded 20 Mar 2023Source
  • 16 Certificates of CA (Form 3)P52100017591 · FEB 20.pdf · uploaded 20 Mar 2023Source
  • 17 Certificates of CA (Form 3)P52100017591 · MAY 20.pdf · uploaded 20 Mar 2023Source
  • 18 Certificates of CA (Form 3)P52100017591 · AUG 20.pdf · uploaded 20 Mar 2023Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · OCT 18.pdf · uploaded 21 Mar 2023Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · JAN.pdf · uploaded 21 Mar 2023Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · may.pdf · uploaded 21 Mar 2023Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · aug.pdf · uploaded 21 Mar 2023Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · feb 20.pdf · uploaded 21 Mar 2023Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · may 20.pdf · uploaded 21 Mar 2023Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · aug 20.pdf · uploaded 21 Mar 2023Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · nov.pdf · uploaded 21 Mar 2023Source
  • 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH-1 March-2023.pdf · uploaded 5 Apr 2023Source
  • 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2 March-2023.pdf · uploaded 5 Apr 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017521 · Form 2A SW SBH I March 2023.pdf · uploaded 12 Apr 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017591 · Form 2A SW SBH II March 2023.pdf · uploaded 12 Apr 2023Source
  • 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form1 March2022.pdf · uploaded 22 Apr 2023Source
  • 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH1_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH1_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH1Dec 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH1_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 SBH1 Dec2022.pdf · uploaded 22 Apr 2023Source
  • 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 SBH1 Jun2022.pdf · uploaded 22 Apr 2023Source
  • 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 SBH1 March2022.pdf · uploaded 22 Apr 2023Source
  • 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 SBH1 Sep2022.pdf · uploaded 22 Apr 2023Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100017521 · Form 2A SBH1_March 2022.pdf · uploaded 22 Apr 2023Source
  • 13 Certificates of CA (Form 3)P52100017521 · may 20.pdf · uploaded 22 Apr 2023Source
  • 14 Certificates of CA (Form 3)P52100017521 · Form 3_SBH1_Dec 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 15 Certificates of CA (Form 3)P52100017521 · Form 3_SBH1_Dec 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 16 Certificates of CA (Form 3)P52100017521 · Form 3 SBH1_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 17 Certificates of CA (Form 3)P52100017521 · Form 3_SBH1_Sep 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1_SBH 2_March 2022.pdf · uploaded 22 Apr 2023Source
  • 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1_SBH 2_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1_SBH 2_Sep 2022.pdf · uploaded 22 Apr 2023Source
  • 20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1_SBH 2_Dec 2022.pdf · uploaded 22 Apr 2023Source
  • 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2_SBH 2_March 2022.pdf · uploaded 22 Apr 2023Source
  • 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2_SBH 2_Jun 2022.pdf · uploaded 22 Apr 2023Source
  • 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2_SBH 2_Sep 2022.pdf · uploaded 22 Apr 2023Source
  • 21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2_SBH 2_Dec 2022.pdf · uploaded 22 Apr 2023Source
  • 19 Certificates of CA (Form 3)P52100017591 · Form 3_SBH 2_March 2022.pdf · uploaded 22 Apr 2023Source
  • 20 Certificates of CA (Form 3)P52100017591 · Form 3_SBH 2_Jun 2022-compressed.pdf · uploaded 22 Apr 2023Source
  • 21 Certificates of CA (Form 3)P52100017591 · Form 3_SBH 2_Sep 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 22 Certificates of CA (Form 3)P52100017591 · Form 3_SBH 2_Dec 2022_compressed.pdf · uploaded 22 Apr 2023Source
  • 8 Disclosure of sold/ booked inventoryP52100017521 · SBH Phase_1_SW_March23.pdf · uploaded 11 May 2023Source
  • 20 Disclosure of sold/ booked inventoryP52100017591 · SBH Phase_2_SW_March23.pdf · uploaded 11 May 2023Source
  • 21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2 March-2023.pdf · uploaded 29 May 2023Source
  • 2 Declaration in FORM BP52100017591 · sharp scanner_20230607_151831.pdf · uploaded 7 Jun 2023Source
  • 22 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH -II SW.pdf · uploaded 11 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017591 · Form 2A SBH-II SW.pdf · uploaded 11 Jul 2023Source
  • 22 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 SBH PH I.pdf · uploaded 14 Sep 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017521 · Form 2A SBH-I SW.pdf · uploaded 14 Sep 2023Source
  • 9 Disclosure of sold/ booked inventoryP52100017521 · SBH PH I Jun 23 Sold Disclosure.pdf · uploaded 26 Sep 2023Source
  • 21 Disclosure of sold/ booked inventoryP52100017591 · SBH PH II - Jun 23 Bldg 1 to 4.pdf · uploaded 26 Sep 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017521 · From 2A - SBH PH I - Sept 2023.pdf · uploaded 6 Oct 2023Source
  • 23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1- SBH PH I - Sept 2023.pdf · uploaded 9 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100017521 · Form 5 - SBH PH - I FY 22-23.pdf · uploaded 13 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100017591 · Form 5 - SBH PH II FY 22-23.pdf · uploaded 13 Oct 2023Source
  • 23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1- SBH PH II - Sept 2023.pdf · uploaded 18 Oct 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017591 · Form 2A - SBH PH II - Sept 2023.pdf · uploaded 18 Oct 2023Source
  • 10 Disclosure of sold/ booked inventoryP52100017521 · SBH PH I - Sept 23 Sold Disclosure.pdf · uploaded 20 Oct 2023Source
  • 22 Disclosure of sold/ booked inventoryP52100017591 · SBH PH II - Sept 23 Sold Disclosure.pdf · uploaded 20 Oct 2023Source
  • 24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · 1 Form 1 SBH 1 Sep 2022.pdf · uploaded 15 Dec 2023Source
  • 25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · 2 Form 1 SBH PH I Sept 2023.pdf · uploaded 15 Dec 2023Source
  • 21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · 1 Form 2 SBH I June 23.pdf · uploaded 15 Dec 2023Source
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · 2 Form 2 SBH I Sept 23.pdf · uploaded 15 Dec 2023Source
  • 18 Certificates of CA (Form 3)P52100017521 · 1 Form 3 SBH Phase 1 Aug 2019.pdf · uploaded 15 Dec 2023Source
  • 19 Certificates of CA (Form 3)P52100017521 · 2 Form 3 SBH 1 May 2020.pdf · uploaded 15 Dec 2023Source
  • 20 Certificates of CA (Form 3)P52100017521 · 3 Form 3 SBH 1 March 2022.pdf · uploaded 15 Dec 2023Source
  • 21 Certificates of CA (Form 3)P52100017521 · 4 Form 3 SBH 1 Jun 2022.pdf · uploaded 15 Dec 2023Source
  • 22 Certificates of CA (Form 3)P52100017521 · 5 Form 3 SBH 1 Sep 2022.pdf · uploaded 15 Dec 2023Source
  • 23 Certificates of CA (Form 3)P52100017521 · 6 Form 3 SBH 1 Dec 2022.pdf · uploaded 15 Dec 2023Source
  • 24 Certificates of CA (Form 3)P52100017521 · 7 Form 3 SBH Phase 1 March 2023.pdf · uploaded 15 Dec 2023Source
  • 25 Certificates of CA (Form 3)P52100017521 · 8 Form 3 SBH Phase 1 June 2023.pdf · uploaded 15 Dec 2023Source
  • 26 Certificates of CA (Form 3)P52100017521 · 9 Form 3 SBH Phase 1 Sept 2023.pdf · uploaded 15 Dec 2023Source
  • 24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · 1 Form 1 SBH-2_Sep 2022.pdf · uploaded 15 Dec 2023Source
  • 25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · 2 Form 1- SBH PH II - Sept 2023.pdf · uploaded 15 Dec 2023Source
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · 1 From 2- SBH II - Jun 23.pdf · uploaded 15 Dec 2023Source
  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · 2 Form 2- SBH II - Sept 23.pdf · uploaded 15 Dec 2023Source
  • 23 Certificates of CA (Form 3)P52100017591 · 1 Form 3 SBH Phase 2 Aug 2019.pdf · uploaded 15 Dec 2023Source
  • 24 Certificates of CA (Form 3)P52100017591 · 2 Form 3 SBH 2 May 2020.pdf · uploaded 15 Dec 2023Source
  • 25 Certificates of CA (Form 3)P52100017591 · 3 Form 3 SBH 2 March 2022.pdf · uploaded 15 Dec 2023Source
  • 26 Certificates of CA (Form 3)P52100017591 · 4 Form 3 SBH 2 Jun 2022.pdf · uploaded 15 Dec 2023Source
  • 27 Certificates of CA (Form 3)P52100017591 · 5 Form 3 SBH 2 Sep 2022.pdf · uploaded 15 Dec 2023Source
  • 28 Certificates of CA (Form 3)P52100017591 · 6 Form 3 SBH 2 Dec 2022.pdf · uploaded 15 Dec 2023Source
  • 29 Certificates of CA (Form 3)P52100017591 · 7 Form 3 SBH Phase 2 March 2023.pdf · uploaded 15 Dec 2023Source
  • 30 Certificates of CA (Form 3)P52100017591 · 8 Form 3 SBH Phase 2 June 2023.pdf · uploaded 15 Dec 2023Source
  • 31 Certificates of CA (Form 3)P52100017591 · 9 Form 3 SBH Phase 2 Sept 2023.pdf · uploaded 15 Dec 2023Source
  • 26 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1- SBH PH I - Sept 2023 Signed.pdf · uploaded 23 Dec 2023Source
  • 26 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1- SBH PH II - Sept 2023 Signed.pdf · uploaded 23 Dec 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017521 · From 2A - SBH I - Dec 23.pdf · uploaded 8 Jan 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100017591 · From 2A - SBH II - Dec 23.pdf · uploaded 8 Jan 2024Source
  • 27 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1- SBH PH I - Dec 23.pdf · uploaded 17 Jan 2024Source
  • 27 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1- SBH PH II - Dec 23.pdf · uploaded 17 Jan 2024Source
  • 11 Disclosure of sold/ booked inventoryP52100017521 · SBH I Dec 23 Sold Disclosure.pdf · uploaded 20 Jan 2024Source
  • 23 Disclosure of sold/ booked inventoryP52100017591 · SBH II Dec 23 Sold Disclosure.pdf · uploaded 20 Jan 2024Source
  • 28 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form-1 - Mar 24 - SBH I.pdf · uploaded 18 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100017521 · Form-2A - Mar 24 - SBH I.pdf · uploaded 18 May 2024Source
  • 28 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form-1 - Mar 24 - SBH II.pdf · uploaded 18 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100017591 · Form-2A - Mar 24 - SBH II.pdf · uploaded 18 May 2024Source
  • 12 Disclosure of sold/ booked inventoryP52100017521 · SBH Phase 1 Solitaire World 3rd to 7th Floor.pdf · uploaded 31 Jul 2024Source
  • 24 Disclosure of sold/ booked inventoryP52100017591 · Sold Disclosure - SBH II - Mar 24.pdf · uploaded 1 Aug 2024Source
  • 25 Disclosure of sold/ booked inventoryP52100017591 · Sold Disclosure - Jun 24 - SBH II.pdf · uploaded 1 Aug 2024Source
  • 29 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1- SBH PH I - Jun 2024.pdf · uploaded 20 Aug 2024Source
  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · FORM 2 Engineer certificate-SW-SBH-1.pdf · uploaded 20 Aug 2024Source
  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2-SBH I- Mar 24.pdf · uploaded 20 Aug 2024Source
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2- SBH PH I - June24.pdf · uploaded 20 Aug 2024Source
  • 27 Certificates of CA (Form 3)P52100017521 · SBH I_Form 3 dec23.pdf · uploaded 20 Aug 2024Source
  • 28 Certificates of CA (Form 3)P52100017521 · Form 3- SBH PH - I - Mar 24.pdf · uploaded 20 Aug 2024Source
  • 29 Certificates of CA (Form 3)P52100017521 · Form 3- SBH PH I - Jun 24.pdf · uploaded 20 Aug 2024Source
  • 2 Disclosure of sold/ booked inventoryP52100017521 · Sold Discloure - SBH I SW - Sept 2024.pdf · uploaded 19 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryP52100017591 · Sold Discloure - SBH PH II - SW Sept 2024.pdf · uploaded 19 Oct 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 - SBH PH I - Sept 2024.pdf · uploaded 21 Oct 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form -1 - SBH PH -II - Sept 2024.pdf · uploaded 21 Oct 2024Source
  • 2 Certificates of CA (Form 3)P52100017521 · SBH PH I Form 3.pdf · uploaded 10 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100017521 · SBH PH I - SW - FY 23-24 - Form 5.pdf · uploaded 13 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100017591 · SBH PH II - Form 5 - FY 23-24.pdf · uploaded 24 Dec 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 - SBH PH I - Dec 24.pdf · uploaded 18 Jan 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 - SBH PH II - Dec 24.pdf · uploaded 18 Jan 2025Source
  • 1 Certificates of CA (Form 3)P52100017521 · Form 3 - SBH PH I - Dec 24.pdf · uploaded 20 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 - SBH PH I - Dec 24.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100017521 · SOld Disclsoure - SBH PH I - Bldg - 1 - Dec 24.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100017591 · Sold Disclosure - SBH PH II - Dec 24.pdf · uploaded 20 Jan 2025Source
  • 1 Certificates of CA (Form 3)P52100017591 · SBH II_Form 3 Dec 23 Signed Copy.pdf · uploaded 22 Jan 2025Source
  • 2 Certificates of CA (Form 3)P52100017591 · Form-3 - SBH PH II - Mar 24.pdf · uploaded 22 Jan 2025Source
  • 3 Certificates of CA (Form 3)P52100017591 · Form 3_ CA SBH2-Jun-24 signed.pdf · uploaded 22 Jan 2025Source
  • 4 Certificates of CA (Form 3)P52100017591 · Form -3 - SBH PH -II - Sept 2024.pdf · uploaded 22 Jan 2025Source
  • 5 Certificates of CA (Form 3)P52100017591 · Form 3 - SBH PH II - Dec 24.pdf · uploaded 22 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · FORM 2 Engineer certificate-SW-SBH-2.pdf · uploaded 22 Jan 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2_SBH 2 _Mar 24.pdf · uploaded 22 Jan 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form - 2- SBH Ph II - Jun 24.pdf · uploaded 22 Jan 2025Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · FORM 2 - SBH PH II -SW-Sept 24.pdf · uploaded 22 Jan 2025Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2 - SBH PH II - Dec 24.pdf · uploaded 22 Jan 2025Source
  • 1 Details of encumbrancesP52100017521 · SBH I Encumbrances-14-2-25 Capri.pdf · uploaded 15 Feb 2025Source
  • 1 Details of encumbrancesP52100017591 · SBH II Encumbrances - 14-02-25 Capri.pdf · uploaded 15 Feb 2025Source
  • 1 Declaration in FORM BP52100017521 · SBH PH I - Revised form B.pdf · uploaded 29 Mar 2025Source
  • 1 Other – TechnicalP52100017521 · 1 SBH PH I - BAR Chart RERA Timeline as on date.pdf · uploaded 29 Mar 2025Source
  • 2 Other – TechnicalP52100017521 · 1SBH PH I - BAR Chart.pdf · uploaded 29 Mar 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017521 · Form 1 - SBH PH I - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Certificates of CA (Form 3)P52100017521 · Form 3 - SBH PH I - Mar 25_compressed.pdf · uploaded 26 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017521 · Form 2 - SBH PH I - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100017521 · Sold Disclosure - SBH I - Mar 24.pdf · uploaded 26 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryP52100017521 · Sold Disclosure - SBH PH I - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100017521 · Form 2A - SBH PH I - SW - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 - SBH-2.pdf · uploaded 26 Apr 2025Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2_March 2022.pdf · uploaded 26 Apr 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2_Jun 2022.pdf · uploaded 26 Apr 2025Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2_Sep 2022.pdf · uploaded 26 Apr 2025Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2_Dec 2022.pdf · uploaded 26 Apr 2025Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 SBH-2 March-2023.pdf · uploaded 26 Apr 2025Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1- SBH PH II - Jun 2024.pdf · uploaded 26 Apr 2025Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017591 · Form 1 - SBH PH II - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Certificates of CA (Form 3)P52100017591 · Form 3 - SBH PH II - Mar 25_compressed.pdf · uploaded 26 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017591 · Form 2 - SBH PH II - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100017591 · Sold Disclosure - SBH PH II - Mar 25.pdf · uploaded 26 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100017591 · Form 2A - SBH PH II - SW - Mar 25.pdf · uploaded 26 Apr 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH PH I - Mar 25.pdf · uploaded 8 Jul 2025Source
  • Withdrawal Update Form 2P52100017521 · Form 2 - SBH PH I - Mar 25.pdf · uploaded 8 Jul 2025Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH I - Mar 25.pdf · uploaded 8 Jul 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH PH I - Mar 25.pdf · uploaded 10 Jul 2025Source
  • Withdrawal Update Form 2P52100017521 · Form 2 - SBH PH I - Mar 25.pdf · uploaded 10 Jul 2025Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH I - Mar 25.pdf · uploaded 10 Jul 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 SBH PH 1 Jun-25.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 2P52100017521 · Form 2 SBH PH I- Jun-25.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH I - Jun 25.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 SBH PH 1 Jun-25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 2P52100017521 · Form 2 SBH PH I- Jun-25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH I - Jun 25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 1P52100017591 · Form 1 SBH PH II- Jun-25.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 2P52100017591 · SBH-ll Form-2.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 3P52100017591 · Form 3_SBH 2_June 2025.pdf · uploaded 24 Jul 2025Source
  • Form 5 (FY 2024-2025)P52100017591 · SBH PH II -Form 5-FY 24-25.pdf · uploaded 4 Sep 2025Source
  • Form 5 (FY 2024-2025)P52100017521 · SBH PH I -Form 5-FY 24-25.pdf · uploaded 30 Sep 2025Source
  • Form 2A (FY 2024-2025)P52100017591 · Form 2A - SBH PH II - SW - Mar 25.pdf · uploaded 1 Oct 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH PH I - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2P52100017521 · Form 2 - SBH PH I - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3P52100017521 · Form 3- SBH PH I - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1P52100017591 · Form 1 - SBH PH II - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2P52100017591 · Form 2 - SBH PH II - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3P52100017591 · Form 3 - SBH PH II - Sept 2025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH PH - I - Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P52100017521 · Form 2 - SBH PH I - Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH I - Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P52100017591 · Form 1 - SBH PH - II - Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P52100017591 · Form 1 - SBH PH - II - Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P52100017591 · Form 2 - SBH PH II- Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P52100017591 · Form 2 - SBH PH II- Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P52100017591 · Form 3 - SBH PH II - Sept 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P52100017591 · Form 3 - SBH PH - II- Dec 2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH PH - I - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P52100017521 · Form 2 SBH PH I - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P52100017521 · Form 3 SBH PH I - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1P52100017591 · Form 1 - SBH PH - II - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P52100017591 · Form 2 -SBH PH - II - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P52100017591 · Form-3_SBH Ph2_Mar26.pdf · uploaded 20 Apr 2026Source
  • Form 2A (FY 2025-2026)P52100017521 · Form 2A SBH PH I - Mar 26.pdf · uploaded 21 Apr 2026Source
  • Form 2A (FY 2025-2026)P52100017591 · Form 2A -SBH PH - II - Mar 26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1P52100017521 · Form 1 - SBH -PH - I-SW- Jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2P52100017521 · Form 2 - SBH PH - I - Jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3P52100017521 · Form 3 - SBH PH - I - Jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1P52100017591 · Form 1 - SBH PH-II-SW Jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2P52100017591 · Form 2 - SBH PH - II - Jun 26.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3P52100017591 · Form 3 - SBH PH - II - Jun 26.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)P52100017521 · Form 5 - SBH PH - I - FY 25-26.pdf · uploaded 9 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100017591 · Form 5 - SBH PH - II - FY 25-26.pdf · uploaded 10 Sep 2026Source

Technical

  • DocumentP52100017521 · 1_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017521 · 8_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017521 · 9_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017591 · 1_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017591 · 8_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017591 · 9_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017591 · 10_17.pdf · uploaded 14 Apr 2018Source
  • DocumentP52100017521 · Buiulding Layout.pdf · uploaded 31 Jul 2018Source
  • DocumentP52100017591 · SBH Ph2 Floor plan.pdf · uploaded 3 Aug 2018Source
  • DocumentP52100017521 · 1-39_layout.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017521 · 16-39_SBH1.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017521 · 17-39_SBH1n2.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017521 · 25-39_SBH1.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017591 · 1-39_layout.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017591 · 17-39_SBH1n2.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017591 · 18-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017591 · 19-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017591 · 20-39_SBH2.pdf · uploaded 25 Jun 2019Source
  • DocumentP52100017521 · 1.pdf · uploaded 15 Oct 2019Source
  • DocumentP52100017591 · 1.pdf · uploaded 15 Oct 2019Source
  • DocumentP52100017521 · 26 WP SBH I.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 27 WP SBH I SBH II.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 16 SBH 1.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 17 SBH 1.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 24 SBH I.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017591 · 18 SBH 2.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017591 · 19 SBH 2.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017591 · 25 Tower A.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017591 · 27 WP SBH I SBH II.pdf · uploaded 15 Feb 2020Source
  • DocumentP52100017521 · 1- 38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 2-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 3-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 4-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 5-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 6-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 7-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 8-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 9-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 10-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 11-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 11-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 12-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 13-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 14-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 15-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 16-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 17-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 18-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 19-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 20-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 21-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 22-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 23-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 23-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 24-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 25-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 26-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 27-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 28-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 28-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 29-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 30-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 31-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 32-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 33-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 34-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 35-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 36-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 37-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 38-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 1- 38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 2-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 3-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 4-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 5-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 6-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 7-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 8-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 9-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 10-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 11-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 12-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 13-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 14-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 15-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 16-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 17-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 18-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 19-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 20-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 21-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 22-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 23-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 23-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 24-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 25-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 26-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 27-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 28-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 29-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 29-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 30-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 31-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 32-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 33-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 34-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 35-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 36-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 37-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017591 · 38-38.pdf · uploaded 4 Mar 2021Source
  • DocumentP52100017521 · 1_42 TA W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 2_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 3_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 4_ 42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 5_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 6_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 17_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 18_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 19_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 20_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 21_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 22_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 23_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 24_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 25_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 26_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 27_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 28_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 29_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 30_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 31_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 32_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 33_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 34_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 7_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 8_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 9_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 10_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 11_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 12_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 13_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 14_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 15_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 35_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 36_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 37_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 38_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 39_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 40_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 41_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 42_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · 16_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 1_42 TA W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 2_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 3_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 4_ 42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 5_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 6_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 7_42 W1 W2 W3 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 8_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 9_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 10_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 11_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 12_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 13_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 14_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 15_42 TA WORLD PLAZA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 16_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 17_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 18_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 19_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 20_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 21_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 22_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 23_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 24_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 25_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 26_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 27_42 TA.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 28_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 29_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 30_42 W1.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 31_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 32_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 33_42 W2.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 34_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 35_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 36_42 W3.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 37_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 38_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 39_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 40_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 41_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017591 · 42_42 W4.pdf · uploaded 2 Sep 2021Source
  • DocumentP52100017521 · Scan_0979-01_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-02_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-03_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-04_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-05_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-06_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-07_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-08_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-09_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-10.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-11.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-12.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-13.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-14.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-15.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-16_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-17.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-19_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-20_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-21_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-22_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-23_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-24_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-25_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-26_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-27_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-28_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-29_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-30_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-31_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-32_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-32_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-33_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-34_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-35_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-36_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-37_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-38_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-39_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-40_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-41_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-42_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017521 · Scan_0979-43_compressed.pdf · uploaded 10 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-07_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-08_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-09_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-10.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-11.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-12.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-13.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-14.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-15.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-16_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-17.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-18_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-19_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-20_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-21_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-22_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-23_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-24_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-25_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-26_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-27_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-28_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-29_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-30_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-31_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-32_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-33_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-34_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-35_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-36_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-37_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-38_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-39_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-40_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-41_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-42_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-43_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-01_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-02_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-03_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-04_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-05_compressed.pdf · uploaded 11 Nov 2022Source
  • DocumentP52100017591 · Scan_0979-06_compressed.pdf · uploaded 11 Nov 2022Source
  • Other – TechnicalP52100017521 · 1 SBH PH I - BAR Chart RERA Timeline as on date.pdf · uploaded 29 Mar 2025Source
  • Other – TechnicalP52100017521 · 1SBH PH I - BAR Chart.pdf · uploaded 29 Mar 2025Source

Technical (Architect)

  • DocumentP52100017521 · Form 1 - SBH PH I - Sept 2024.pdf · uploaded 21 Oct 2024Source
  • DocumentP52100017591 · Form -1 - SBH PH -II - Sept 2024.pdf · uploaded 21 Oct 2024Source
  • DocumentP52100017521 · Form 1 - SBH PH I - Dec 24.pdf · uploaded 18 Jan 2025Source
  • DocumentP52100017591 · Form 1 - SBH PH II - Dec 24.pdf · uploaded 18 Jan 2025Source
  • DocumentP52100017521 · Form 1 - SBH PH I - Mar 25.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 - SBH-2.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 SBH-2_March 2022.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 SBH-2_Jun 2022.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 SBH-2_Sep 2022.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 SBH-2_Dec 2022.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 SBH-2 March-2023.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1- SBH PH II - Jun 2024.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 1 - SBH PH II - Mar 25.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017521 · Form 1 - SBH -PH - I-SW- Jun 26.pdf · uploaded 20 Jul 2026Source
  • DocumentP52100017591 · Form 1 - SBH PH-II-SW Jun 26.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentP52100017521 · Form 2 - SBH PH I - Dec 24.pdf · uploaded 20 Jan 2025Source
  • DocumentP52100017591 · FORM 2 Engineer certificate-SW-SBH-2.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100017591 · Form 2_SBH 2 _Mar 24.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100017591 · Form - 2- SBH Ph II - Jun 24.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100017591 · FORM 2 - SBH PH II -SW-Sept 24.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100017591 · Form 2 - SBH PH II - Dec 24.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100017521 · Form 2 - SBH PH I - Mar 25.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017591 · Form 2 - SBH PH II - Mar 25.pdf · uploaded 26 Apr 2025Source
  • DocumentP52100017521 · Form 2 - SBH PH - I - Jun 26.pdf · uploaded 20 Jul 2026Source
  • DocumentP52100017591 · Form 2 - SBH PH - II - Jun 26.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 578/1/2, 578/1/3

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
Office space, Restaurant, Office 3550 units in all
Address
578/1/2 and 578/1/3, Bibwewadi, 578/1/2+578/1/3 BIBWEWADI, BIBWEWADIPIN 411037
Village
Pune (M Corp.), Pune City taluka
Land area for this project
4,058 sq m (43,682 sq ft)
Permissible built-up area
16,787 sq m (1,80,698 sq ft)
Sanctioned built-up area
16,787 sq m (1,80,698 sq ft)
Recreational open space
406 sq m (4,368 sq ft)
Designated bank account
76
Developed in phases
No
Also registered as
Solitaire Business Hub Phase I, Solitaire World, Solitaire Business Hub Phase II, Solitaire World

Survey, CTS, gat or plot numbers

578/1/2578/1/3

Land as published on MahaRERA's project page

578/1/2 and 578/1/3, Bibwewadi

Boundaries

North
30 Mtr Wide Dp Road
South
S No 578-2
East
24 Mtr Dp Road
West
S No 579 Bibvewadi

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking550 units

226 of 550 units booked (41%), as the promoter reported to MahaRERA

Office space · 549 unitsRestaurant · 1 unitOffice 3 · 0 units
RERABuildingTypeCarpet areaUnitsBooked
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space32.14 sq m · 346 sq ft52
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space33.54 sq m · 361 sq ft50
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space33.72 sq m · 363 sq ft21
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space33.82 sq m · 364 sq ft22
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space34.65 sq m · 373 sq ft40
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space34.75 sq m · 374 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space34.84 sq m · 375 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space35.67 sq m · 384 sq ft11
Show all 127 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space36.51 sq m · 393 sq ft40
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space36.7 sq m · 395 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space37.81 sq m · 407 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space37.9 sq m · 408 sq ft44
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space38.46 sq m · 414 sq ft33
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space38.55 sq m · 415 sq ft66
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space38.83 sq m · 418 sq ft20
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space38.93 sq m · 419 sq ft180
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space39.11 sq m · 421 sq ft77
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space39.76 sq m · 428 sq ft21
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space39.86 sq m · 429 sq ft22
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space40.78 sq m · 439 sq ft30
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space40.88 sq m · 440 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space40.97 sq m · 441 sq ft2020
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space41.06 sq m · 442 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space41.43 sq m · 446 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space41.71 sq m · 449 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space42.36 sq m · 456 sq ft80
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space43.11 sq m · 464 sq ft22
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space43.76 sq m · 471 sq ft42
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space43.85 sq m · 472 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space43.94 sq m · 473 sq ft20
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space44.04 sq m · 474 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space44.22 sq m · 476 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space44.31 sq m · 477 sq ft33
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space44.59 sq m · 480 sq ft1515
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space45.15 sq m · 486 sq ft180
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space45.24 sq m · 487 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space45.43 sq m · 489 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space46.54 sq m · 501 sq ft33
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space47.29 sq m · 509 sq ft20
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space52.12 sq m · 561 sq ft32
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space52.3 sq m · 563 sq ft53
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space52.49 sq m · 565 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space52.68 sq m · 567 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space53.6 sq m · 577 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space53.79 sq m · 579 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space56.86 sq m · 612 sq ft163
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space57.13 sq m · 615 sq ft3535
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space57.6 sq m · 620 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space60.2 sq m · 648 sq ft22
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space70.98 sq m · 764 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space72.46 sq m · 780 sq ft40
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space72.56 sq m · 781 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space75.25 sq m · 810 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space85.01 sq m · 915 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space87.33 sq m · 940 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space89.19 sq m · 960 sq ft40
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space122.63 sq m · 1,320 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space124.4 sq m · 1,339 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space125.88 sq m · 1,355 sq ft11
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space127.74 sq m · 1,375 sq ft22
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space150.5 sq m · 1,620 sq ft20
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space150.59 sq m · 1,621 sq ft20
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space154.68 sq m · 1,665 sq ft10
P52100017521BUILDING 1 - 3rd Floor to 7th FloorOffice space170.1 sq m · 1,831 sq ft50
P52100017591Building 1 - 8th to 15th FloorOffice space33.54 sq m · 361 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space34.65 sq m · 373 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space37.81 sq m · 407 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space38.93 sq m · 419 sq ft50
P52100017591Building 1 - 8th to 15th FloorOffice space39.67 sq m · 427 sq ft51
P52100017591Building 1 - 8th to 15th FloorOffice space39.76 sq m · 428 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space40.78 sq m · 439 sq ft66
P52100017591Building 1 - 8th to 15th FloorOffice space42.83 sq m · 461 sq ft484
P52100017591Building 1 - 8th to 15th FloorOffice space43.01 sq m · 463 sq ft22
P52100017591Building 1 - 8th to 15th FloorOffice space43.11 sq m · 464 sq ft22
P52100017591Building 1 - 8th to 15th FloorOffice space43.2 sq m · 465 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space44.22 sq m · 476 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space72.46 sq m · 780 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space73.49 sq m · 791 sq ft30
P52100017591Building 1 - 8th to 15th FloorOffice space73.67 sq m · 793 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space73.76 sq m · 794 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space79.8 sq m · 859 sq ft30
P52100017591Building 1 - 8th to 15th FloorOffice space86.31 sq m · 929 sq ft21
P52100017591Building 1 - 8th to 15th FloorOffice space110.93 sq m · 1,194 sq ft41
P52100017591Building 1 - 8th to 15th FloorOffice space111.02 sq m · 1,195 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space143.16 sq m · 1,541 sq ft40
P52100017591Building 1 - 8th to 15th FloorOffice space143.26 sq m · 1,542 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space170.1 sq m · 1,831 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space599.41 sq m · 6,452 sq ft10
P52100017591Building 1 - 8th to 15th FloorOffice space767.47 sq m · 8,261 sq ft11
P52100017591Building 1 - 8th to 15th FloorOffice space1,123.28 sq m · 12,091 sq ft10
P52100017591Building 1 - 8th to 15th FloorRestaurant380.25 sq m · 4,093 sq ft10
P52100017591Building 2 - 16th FloorOffice space39.67 sq m · 427 sq ft10
P52100017591Building 2 - 16th FloorOffice space42.83 sq m · 461 sq ft92
P52100017591Building 2 - 16th FloorOffice space43.01 sq m · 463 sq ft11
P52100017591Building 2 - 16th FloorOffice space43.11 sq m · 464 sq ft11
P52100017591Building 2 - 16th FloorOffice space73.49 sq m · 791 sq ft10
P52100017591Building 2 - 16th FloorOffice space79.8 sq m · 859 sq ft10
P52100017591Building 2 - 16th FloorOffice space111.02 sq m · 1,195 sq ft11
P52100017591Building 2 - 16th FloorOffice space143.26 sq m · 1,542 sq ft10
P52100017591Building 3 - 17th Floor to 25th FloorOffice space39.67 sq m · 427 sq ft60
P52100017591Building 3 - 17th Floor to 25th FloorOffice space39.76 sq m · 428 sq ft11
P52100017591Building 3 - 17th Floor to 25th FloorOffice space39.95 sq m · 430 sq ft22
P52100017591Building 3 - 17th Floor to 25th FloorOffice space42.83 sq m · 461 sq ft7712
P52100017591Building 3 - 17th Floor to 25th FloorOffice space43.01 sq m · 463 sq ft1817
P52100017591Building 3 - 17th Floor to 25th FloorOffice space43.11 sq m · 464 sq ft20
P52100017591Building 3 - 17th Floor to 25th FloorOffice space73.49 sq m · 791 sq ft81
P52100017591Building 3 - 17th Floor to 25th FloorOffice space73.67 sq m · 793 sq ft11
P52100017591Building 3 - 17th Floor to 25th FloorOffice space79.8 sq m · 859 sq ft70
P52100017591Building 3 - 17th Floor to 25th FloorOffice space86.21 sq m · 928 sq ft21
P52100017591Building 3 - 17th Floor to 25th FloorOffice space110.93 sq m · 1,194 sq ft80
P52100017591Building 3 - 17th Floor to 25th FloorOffice space111.02 sq m · 1,195 sq ft11
P52100017591Building 3 - 17th Floor to 25th FloorOffice space143.16 sq m · 1,541 sq ft71
P52100017591Building 3 - 17th Floor to 25th FloorOffice space143.26 sq m · 1,542 sq ft11
P52100017591Building 3 - 17th Floor to 25th FloorOffice space143.44 sq m · 1,544 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space39.8 sq m · 428 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space39.95 sq m · 430 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space42.83 sq m · 461 sq ft155
P52100017591Building 4 - 26th Floor to 28th FloorOffice space43.01 sq m · 463 sq ft99
P52100017591Building 4 - 26th Floor to 28th FloorOffice space43.05 sq m · 463 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space43.11 sq m · 464 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space73.67 sq m · 793 sq ft22
P52100017591Building 4 - 26th Floor to 28th FloorOffice space79.8 sq m · 859 sq ft21
P52100017591Building 4 - 26th Floor to 28th FloorOffice space86.21 sq m · 928 sq ft10
P52100017591Building 4 - 26th Floor to 28th FloorOffice space110.93 sq m · 1,194 sq ft20
P52100017591Building 4 - 26th Floor to 28th FloorOffice space111.02 sq m · 1,195 sq ft11
P52100017591Building 4 - 26th Floor to 28th FloorOffice space143.35 sq m · 1,543 sq ft22
P52100017591Building 5Office 31 sq m · 11 sq ft00

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals28

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectVenkataramanan Associates—P52100017591
ArchitectVenkataramanan Associates—P52100017521
Chartered accountantSPAK & Co—P52100017521
Chartered accountantSPAK & Co—P52100017591
EngineerAnant Kulkarni—P52100017591
EngineerAnant Kulkarni—P52100017521
EngineerDevanand Amale—P52100017521
EngineerIshwar Ghodke—P52100017591
Show all 28 professionalsShow fewer professionals
RoleNameRegistration no.RERA
EngineerMr. Umesh Joshi—P52100017591
EngineerMr. Umesh Joshi—P52100017521
EngineerPranav Patil—P52100017521
EngineerShivprasad Kale—P52100017521
EngineerShivprasad Kale—P52100017591
EngineerSushil Bhoi—P52100017521
EngineerSushil Bhoi—P52100017591
EngineerSwapnil Sonawane—P52100017521
EngineerSwapnil Sonawane—P52100017591
Registered real estate agentANAROCK Property Consultants Pvt. Ltd.—P52100017521
Registered real estate agentAnshul Ajay Gupta—P52100017521
Registered real estate agentDhaval Pradeep Badani—P52100017521
Registered real estate agentHrishikesh Vinod Shah—P52100017521
Registered real estate agentLalitkumar Chhaganlal Jain—P52100017521
Registered real estate agentManoj Chainsukhlal Gandhi—P52100017521
Registered real estate agentNilesh Prakashchandra Joshi—P52100017521
Registered real estate agentRamesh P Toshniwal—P52100017521
Registered real estate agentRavindra Keshavrao Yadav—P52100017521
Registered real estate agentSandhya Vinod Katariya—P52100017521
Registered real estate agentSunita Ramesh Toshniwal—P52100017521

Source: MahaRERA project page. Contact details are not shown.

Other projects in Pune (M Corp.)

All 750 projects in Pune (M Corp.) · Compare Solitaire Business Hub with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Report a problemMethodology