Classic Promoters And Builders Pvt. Ltd

Company or firm · 15 projects · 16 MahaRERA registrations

Also appears as CLASSIC PROMOTERS & BUILDERS PVT LTD · Classic Promoters And Builders Private Limited · Classic Promoters And Builders Pvt. Ltd.

15Projects16 RERA registrations
0Completedas reported on MahaRERA project pages
13%Kept RERA date1 of 8 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 9 extended
11Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Avalon City C-3P52100003105Pimpri Chinchawad (M Corp.)2017Certificate Signed31 Dec 201930 Dec 2021+24 months
MudraP52100003715Pune (M Corp.)2017Certificate Signed30 Jun 202129 Dec 2022+18 months
World One Solitaire WorldP52100004877Pune (M Corp.)2017Certificate Signed31 Dec 202631 Dec 2026On date
Solitaire Business Hub Viman Nagar Phase 1P52100006995Lohgaon2017Certificate Signed31 Dec 202730 Apr 2028+4 months
SBH Wakad C-3 1st and 2nd FloorP52100007034Wakad2017Certificate Signed31 Mar 201830 Sep 2018+6 months
Premier Tower - Solitaire WorldP52100013951Pune (M Corp.)2017Certificate Signed30 Dec 202129 Jun 2023+18 months
Avalon City - C2P52100014311Pimpri Chinchawad (M Corp.)2017Certificate Signed30 Sep 202131 Jul 2027+70 months
Solitaire Business Hub KalyaninagarP52100014846Haveli2018Certificate Signed30 Dec 202329 Dec 2024+12 months
World Plaza Solitaire WorldP52100017361Pune (M Corp.)2018Certificate Signed30 Jun 202231 Dec 2026+54 months
Solitaire Business HubP52100017521Pune (M Corp.)2018Certificate Signed31 Dec 202631 Dec 2026On date
Solitaire Business HubP52100017591Pune (M Corp.)2018Certificate Signed31 Mar 202731 Jul 2027+4 months
World Three - Solitaire WorldP52100018407Pune (M Corp.)2018Certificate Signed30 Jun 202730 Jun 2027On date
World Two - Solitaire WorldP52100027723Pune (M Corp.)2021Certificate Signed31 Dec 202631 Dec 2026On date
World Four - Solitaire WorldP52100030319Pune (M Corp.)2021Certificate Signed30 Sep 202730 Sep 2027On date
AVALON CITY - C5 and C6P52100033855Dapodi2022Certificate Signed31 Mar 202731 Mar 2027On date
Avalon City - Wing AP52100033953Pimpri Chinchawad (M Corp.)2022Certificate Signed31 Mar 202531 Mar 2025On date
Show all 16 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Avalon City C-3+24 mo
  • Mudra+18 mo
  • World One Solitaire WorldOn date
  • Solitaire Business Hub Viman Nagar Phase 1+4 mo
  • SBH Wakad C-3 1st and 2nd Floor+6 mo
  • Premier Tower - Solitaire World+18 mo
  • Avalon City - C2+70 mo
  • Solitaire Business Hub Kalyaninagar+12 mo
  • World Plaza Solitaire World+54 mo
  • Solitaire Business HubOn date
Show all 16 registrations
  • Solitaire Business Hub+4 mo
  • World Three - Solitaire WorldOn date
  • World Two - Solitaire WorldOn date
  • World Four - Solitaire WorldOn date
  • AVALON CITY - C5 and C6On date
  • Avalon City - Wing AOn date

Track record notes

  • 1 of 8 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 70 months, for Avalon City - C2 (P52100014311).
  • MahaRERA records spell this promoter's name 4 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

Show all 11 cases
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology