Skip to content
Others · 1 building · 14 unitsRERA P52100066474

Buttepatil Capital

Deedo IDDP-PUN-6N54

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Pune (M Corp.), Pune 411005 · by Buttepatil Properties · 43% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 11 Jun 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100066474
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210006647411 Jun 202431 Dec 202630 Apr 2027Buttepatil PropertiesProject page
Documents70

1 document held by Deedo, 69 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardButtepatil Properties PAN.pdf · uploaded 7 Mar 2024Source

Legal

  • Declaration Form BDeclaration Form B Developer.pdf · uploaded 7 Mar 2024Source
  • Legal Title reportLatest Search Title Report Tembe 24524.pdf · uploaded 24 May 2024Source

Migrated

  • 1 PAN CardButtepatil Properties PAN.pdf · uploaded 7 Mar 2024Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration Towards Concern Finance.pdf · uploaded 7 Mar 2024Source
  • 1 b Details of encumbrances concerned to LegalDeclaration Towards Concern Finance.pdf · uploaded 7 Mar 2024Source
  • 1 Copy of Layout Approval (in case of layout)Declaration Copy of Layout.pdf · uploaded 7 Mar 2024Source
Show all 70 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentButtepatil Capital Plan.pdf · uploaded 7 Mar 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentButtepatil Capital CC.pdf · uploaded 7 Mar 2024Source
  • 1 Declaration about Commencement CertificateDeclaration About CC.pdf · uploaded 7 Mar 2024Source
  • 1 Declaration in FORM BDeclaration Form B Developer.pdf · uploaded 7 Mar 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest In Other Real Estate GVBP.pdf · uploaded 7 Mar 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest In Other Real Estate RGBP.pdf · uploaded 7 Mar 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest In Other Real Estate SGBP.pdf · uploaded 7 Mar 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest In Other Real Estate Shantanu BP.pdf · uploaded 7 Mar 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest In Other Real Estate SRBP.pdf · uploaded 7 Mar 2024Source
  • 1 Proforma of Allotment letterModel Form Of Allotment Letter Annexure 1.pdf · uploaded 7 Mar 2024Source
  • 1 Deviation Report with respect to Allotment letterDiviation Report With Respect To allotment Letter.pdf · uploaded 7 Mar 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report With Respect To Model Copy Of Agreement.pdf · uploaded 7 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)BP CAPITAL ARCHI CERTI.pdf · uploaded 8 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTI.pdf · uploaded 29 Mar 2024Source
  • 1 Other – TechnicaluNDERTAKING cUM dECLARATION oTHER tECHNICAL.pdf · uploaded 30 Mar 2024Source
  • 1 CERSAI detailsCERSAI REPORT UNDERTAKING.pdf · uploaded 4 Apr 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK ACCOUNT BP CAPITAL.pdf · uploaded 4 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 REVISED BP CAPITAL.pdf · uploaded 5 Apr 2024Source
  • 2 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCE .pdf · uploaded 26 Apr 2024Source
  • 2 b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE .pdf · uploaded 26 Apr 2024Source
  • 1 Copy of the legal title reportLatest Search Title Report Tembe 24524.pdf · uploaded 24 May 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SALE 24 5 24.pdf · uploaded 24 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA BP Capital 31 Mar 2024 (1).pdf · uploaded 21 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA BP Capital 30 June 2024.pdf · uploaded 21 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 BP CAPITAL mar 24.pdf · uploaded 21 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)BP Capital Ar CERTI JUNE 24.pdf · uploaded 24 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)BP Capital Ar CERTI JUNE 24.pdf · uploaded 24 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Buttepatil Capital CA 30 Sep 2024.pdf · uploaded 26 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Buttepatil Capital ArC 30 Sept 2024.pdf · uploaded 7 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EC BP Capital 30 SEP 24.pdf · uploaded 23 Nov 2024Source
  • Form 1Buttepatil Capital Form 1 Arch Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Form 2Buttepatil Capital Form 2 Eng Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Form 3BUTTEPATIL CAPITAL Form 3 CA Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Form 1BUTTEPATIL CAPITAL Form 1 Arch DEC 24 Q3.pdf · uploaded 27 May 2025Source
  • Form 2Buttepatil Capital Form 2 Eng Dec 24 Q3.pdf · uploaded 27 May 2025Source
  • Form 3BUTTEPATIL CAPITAL Form 3 CA Dec 24 Q3.pdf · uploaded 27 May 2025Source
  • Withdrawal Update Form 1AC BP CAPITAL 30625.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 2EC BP CAPITAL 30625.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 3CA BP CAPITAL 30625.pdf · uploaded 27 Oct 2025Source
  • Withdrawal Update Form 1ARC 15102025.pdf · uploaded 31 Oct 2025Source
  • Withdrawal Update Form 2ENG 05102025.pdf · uploaded 31 Oct 2025Source
  • Withdrawal Update Form 3CA 30092025.pdf · uploaded 31 Oct 2025Source
  • Withdrawal Update Form 1ARC Q3 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1ARC Q4 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2EC Q3 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2EC Q4 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3CA Q3 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3CA Q4 CAPITAL.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1BP Capital ArC Q1.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2BP Capital EC From 2.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3BP Capital CA From 3.pdf · uploaded 4 Aug 2026Source

Technical

  • DocumentDeclaration Copy of Layout.pdf · uploaded 7 Mar 2024Source
  • DocumentButtepatil Capital Plan.pdf · uploaded 7 Mar 2024Source
  • Other – TechnicaluNDERTAKING cUM dECLARATION oTHER tECHNICAL.pdf · uploaded 30 Mar 2024Source
  • DocumentButtepatil Capital 2nd Sanction 1.pdf · uploaded 30 Oct 2025Source
  • DocumentButtepatil Capital 2nd Sanction 2.pdf · uploaded 30 Oct 2025Source
  • DocumentButtepatil Capital 2nd Sanction 1.pdf · uploaded 31 Oct 2025Source
  • DocumentButtepatil Capital 2nd Sanction 2.pdf · uploaded 31 Oct 2025Source

Technical (Architect)

  • DocumentButtepatil Capital ArC 30 Sept 2024.pdf · uploaded 7 Nov 2024Source
  • DocumentBP Capital ArC Q1.pdf · uploaded 4 Aug 2026Source

Technical (Engineer)

  • DocumentEC BP Capital 30 SEP 24.pdf · uploaded 23 Nov 2024Source
  • DocumentBP Capital EC From 2.pdf · uploaded 4 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS 1321/2 FInal Plot No 707/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Landowner14 units in all
Address
CTS 1321/2 FInal Plot No 707/2, Khandekar Path, ShivajinagarPIN 411005
Village
Pune (M Corp.), Pune City taluka
Land area for this project
490 sq m (5,274 sq ft)
Permissible built-up area
2,153 sq m (23,175 sq ft)
Sanctioned built-up area
836 sq m (9,002 sq ft)
Designated bank account
154
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS 1321/2 FInal Plot No 707/2

Land as published on MahaRERA's project page

CTS 1321/2 FInal Plot No 707/2

Boundaries

North
Govt Road
South
Adj Gaothan
East
Adj Plot No 708
West
Adj Plot No 707

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

0 of 14 units booked (0%), as the promoter reported to MahaRERA

1BHK · 2 units1RK · 1 unitLandowner · 11 units
TypeCarpet areaUnitsBooked
1BHK66.4 sq m · 715 sq ft20
1RK41.54 sq m · 447 sq ft10
Landowner41.54 sq m · 447 sq ft10
Landowner41.88 sq m · 451 sq ft80
Landowner66.4 sq m · 715 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjay Amle—
Chartered accountantAmber Naik—
Chartered accountantAmber Naik & Associates—
Chartered accountantNitin Inamdar—
EngineerKalpesh Manani—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Pune (M Corp.)

All 750 projects in Pune (M Corp.) · Compare Buttepatil Capital with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology