MahaRERA shows it completed; no MahaRERA orders on record; 100% of its units are booked.

Erandwana, Pune 411004 · by Five Facet Realtors Llp

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked26 of 26 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 24 May 2022, completion promised 31 Jan 2025.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100045570
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004557024 May 202231 Jan 202531 Jan 2025Five Facet Realtors LLPProject page
Documents90

2 documents held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardFive Facet Realtors LLP Pan Card.PDF · uploaded 12 May 2022Source

Legal

  • Declaration Form BVIHANG- PROMOTER FORM- B_compressed.pdf · uploaded 12 May 2022Source
  • Legal Title reportRera Title - Five Facet_compressed-1.pdf · uploaded 13 May 2022Source
  • Legal Title reportRera Title - Five Facet_compressed-2.pdf · uploaded 13 May 2022Source
  • Legal Title reportRera Title - Five Facet_compressed-3.pdf · uploaded 13 May 2022Source

Migrated

  • 1 PAN CardFive Facet Realtors LLP Pan Card.PDF · uploaded 12 May 2022Source
Show all 90 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BVIHANG- PROMOTER FORM- B_compressed.pdf · uploaded 12 May 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 12 May 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA Certificate_Vihang_Awaited_Signed.pdf · uploaded 12 May 2022Source
  • 1 Proforma of Allotment letterALLOTMENT VIHANG- LETTER.pdf · uploaded 12 May 2022Source
  • 1 Copy of the legal title reportRera Title - Five Facet_compressed-1.pdf · uploaded 13 May 2022Source
  • 2 Copy of the legal title reportRera Title - Five Facet_compressed-2.pdf · uploaded 13 May 2022Source
  • 3 Copy of the legal title reportRera Title - Five Facet_compressed-3.pdf · uploaded 13 May 2022Source
  • 1 Details of encumbrancesVIHANG -NO ENCOUMBRANCE LETTER.pdf · uploaded 13 May 2022Source
  • 1 Copy of Layout Approval (in case of layout)1_compressed (1).pdf · uploaded 13 May 2022Source
  • 1 Building Plan Approval / NA Order for plotted development2_compressed (1).pdf · uploaded 13 May 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 May 2022Source
  • 1 Declaration about Commencement CertificateVIHANG - FORMAT - D (2).pdf · uploaded 13 May 2022Source
  • 2 Proforma of Allotment letterAgreement for Sale - Vihang - For RERA PDF.pdf · uploaded 13 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VIHANG.pdf · uploaded 16 May 2022Source
  • 1 Disclosure of sold/ booked inventoryVIHANG SOLD INVENTORY.pdf · uploaded 22 Nov 2022Source
  • 1 Proforma of Agreement for saleAgreement of sale.pdf · uploaded 22 Nov 2022Source
  • 2 Proforma of Agreement for saleAgreement of sale.pdf · uploaded 22 Nov 2022Source
  • 2 Disclosure of sold/ booked inventoryVIHANG.pdf · uploaded 21 Jan 2023Source
  • 2 Copy of Layout Approval (in case of layout)1-3.pdf · uploaded 4 Apr 2023Source
  • 2 Building Plan Approval / NA Order for plotted development2-3.pdf · uploaded 4 Apr 2023Source
  • 3 Building Plan Approval / NA Order for plotted development3-3.pdf · uploaded 4 Apr 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentVihang cc date 11-10-2022.pdf · uploaded 4 Apr 2023Source
  • 2 Declaration about Commencement CertificateVIHANG FORMAT.pdf · uploaded 4 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VIHANG.pdf · uploaded 8 Jun 2023Source
  • 3 Disclosure of sold/ booked inventoryVihang Sales Declaration.PDF · uploaded 8 Jun 2023Source
  • 4 Disclosure of sold/ booked inventoryVihang Sales Disclosure.PDF · uploaded 12 Jun 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VIHANG.pdf · uploaded 10 Jul 2023Source
  • 5 Disclosure of sold/ booked inventoryVIHANG SOLD INVENTORY.pdf · uploaded 31 Aug 2023Source
  • 6 Disclosure of sold/ booked inventoryVihang - Sold Inventory.pdf · uploaded 10 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Vihang.pdf · uploaded 12 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Form 2.pdf · uploaded 17 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3.pdf · uploaded 17 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Vihang.PDF · uploaded 19 Oct 2023Source
  • 3 Copy of Layout Approval (in case of layout)1-3_compressed.pdf · uploaded 21 Nov 2023Source
  • 4 Building Plan Approval / NA Order for plotted development2-3_compressed.pdf · uploaded 21 Nov 2023Source
  • 5 Building Plan Approval / NA Order for plotted development3-3_compressed.pdf · uploaded 21 Nov 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentVihang cc date 11-10-2022.pdf · uploaded 21 Nov 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VIHANG JUNE22.pdf · uploaded 28 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VIHANG SEP 22.pdf · uploaded 28 Dec 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VIHANG DEC 22.pdf · uploaded 28 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Engineers Certificate JUNE 22.pdf · uploaded 28 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Engineers Certificate SEP 22.pdf · uploaded 28 Dec 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Engineers Certificate DEC 22.pdf · uploaded 28 Dec 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Engineers Certificate MARCH 23.PDF · uploaded 28 Dec 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Engineers Certificate JUNE 23.PDF · uploaded 28 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Vihang 2022-23.PDF · uploaded 28 Dec 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 CA Certificate JUNE 22.pdf · uploaded 28 Dec 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 CA Certificate SEP 22.pdf · uploaded 28 Dec 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 CA Certificate DEC 22.pdf · uploaded 28 Dec 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 CA Certificate MARCH23.PDF · uploaded 28 Dec 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 JUNE 23.pdf · uploaded 28 Dec 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Form 2 31-12-23_compressed.pdf · uploaded 12 Jan 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 31-12-2023_compressed.pdf · uploaded 12 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vihang Form 1.PDF · uploaded 16 Jan 2024Source
  • 7 Disclosure of sold/ booked inventoryVihang Disclosure.PDF · uploaded 16 Jan 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (2).pdf · uploaded 22 Jan 2024Source
  • 8 Disclosure of sold/ booked inventoryVihang.PDF · uploaded 29 Jan 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vihang Form 1 31-03-2024.PDF · uploaded 18 Apr 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Form 2 31-03-2024_compressed.pdf · uploaded 18 Apr 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Vihang Form 2A 31-03-2024.PDF · uploaded 18 Apr 2024Source
  • 9 Disclosure of sold/ booked inventoryVihang Sales Diclosure.PDF · uploaded 18 Apr 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 31-03-2024_compressed.pdf · uploaded 18 Apr 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vihang Form 1 30-06-2024.PDF · uploaded 26 Jul 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Vihang Form 2 30-06-2024.PDF · uploaded 26 Jul 2024Source
  • 10 Disclosure of sold/ booked inventoryVihang Sales disclosure 30-06-2024.PDF · uploaded 26 Jul 2024View
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vihang Form 3 30-06-2024_compressed.pdf · uploaded 26 Jul 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Vihang Form 1 01-08-2024.PDF · uploaded 14 Aug 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentVIHANG-FULL COMPLETION.pdf · uploaded 14 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Vihang Form 2A.PDF · uploaded 22 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Vihang 31-03-2024.PDF · uploaded 22 Oct 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Vihang Form 4 07-08-2024.PDF · uploaded 7 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentVIHANG FULL COMPLETION- MAIL TO RERA.pdf · uploaded 7 Nov 2024Source

Technical

  • Document1_compressed (1).pdf · uploaded 13 May 2022Source
  • Document2_compressed (1).pdf · uploaded 13 May 2022Source
  • Document1-3.pdf · uploaded 4 Apr 2023Source
  • Document2-3.pdf · uploaded 4 Apr 2023Source
  • Document3-3.pdf · uploaded 4 Apr 2023Source
  • Document1-3_compressed.pdf · uploaded 21 Nov 2023Source
  • Document2-3_compressed.pdf · uploaded 21 Nov 2023Source
  • Document3-3_compressed.pdf · uploaded 21 Nov 2023Source

Technical (Architect)

  • DocumentVihang Form 1 01-08-2024.PDF · uploaded 14 Aug 2024Source

Technical (Engineer)

  • DocumentVihang Form 2 30-06-2024.PDF · uploaded 26 Jul 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 7, Final Plot no 106

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, 3BHK26 units in all
Address
Final Plot no 106, Sub plot no 6 and 7, CTS no 65, Erandwane, Erandwane, ErandwanePIN 411004
Land area for this project
1,015 sq m (10,923 sq ft)
Permissible built-up area
1,776 sq m (19,114 sq ft)
Sanctioned built-up area
1,776 sq m (19,114 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

7Final Plot no 106Sub plot no 6

Land as published on MahaRERA's project page

Final Plot no 106, Sub plot no 6 and 7,CTS no 65, Erandwane

Boundaries

North
30 ft wide road
South
20 ft wide road
East
30 ft wide road
West
sub plot 8 and 9

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking26 units

26 of 26 units booked (100%), as the promoter reported to MahaRERA

1BHK · 2 units1RK · 1 unit2BHK · 1 unit3BHK · 22 units
TypeCarpet areaUnitsBooked
1BHK53.21 sq m · 573 sq ft11
1BHK56.68 sq m · 610 sq ft11
1RK24.1 sq m · 259 sq ft11
2BHK86.8 sq m · 934 sq ft11
3BHK100.51 sq m · 1,082 sq ft1212
3BHK102.83 sq m · 1,107 sq ft33
3BHK108.91 sq m · 1,172 sq ft77

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMangesh Gotal—
Chartered accountantJayesh Dhudediya—
EngineerRahul Chinchore—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology