Others · 1 building · 41 unitsRERA P52100053670

King Tower

Deedo IDDP-PUN-XDKE

Completion was pushed back 4 months to Sep 2026, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Punawale, Pune 411033 · Property rates in Punawale · by Shree Morya Developers

Delivery6 mo latePromised May 2026 · revised Sep 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 41 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Sep 2026, and that date has passed too

  • This projectRegistered 21 Nov 2023, completion promised 30 May 2026, revised to 30 Sep 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100053670
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005367021 Nov 202330 May 202630 Sep 2026Shree Morya DevelopersProject page
Documents97

1 document held by Deedo, 96 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN SHREE MORYA DEV.pdf · uploaded 2 Feb 2023Source

Legal

  • Other – LegalScan20230812183626.pdf · uploaded 27 Oct 2023Source
  • Other – LegalScan20230812184100.pdf · uploaded 27 Oct 2023Source
  • Other – LegalScan20230812184405.pdf · uploaded 27 Oct 2023Source
  • Other – LegalScan20230812184546.pdf · uploaded 27 Oct 2023Source
  • Other – LegalScan20230812184715.pdf · uploaded 27 Oct 2023Source
  • Other – LegalScan20230812184835.pdf · uploaded 27 Oct 2023Source
Show all 97 documentsShow fewer documents

Legal

  • Legal Title reportLegal Title Report_compressed.pdf · uploaded 27 Oct 2023Source
  • Legal Title reportSHRIKANT BABASAHEB SATHE.pdf · uploaded 27 Oct 2023Source
  • Declaration Form BAdobe Scan 7 Nov 2023.pdf · uploaded 7 Nov 2023Source

Migrated

  • 1 PAN CardPAN SHREE MORYA DEV.pdf · uploaded 2 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceFinance and Legal.pdf · uploaded 6 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalFinance and Legal.pdf · uploaded 6 Feb 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200259414187_For_Asset_Based_Search_03_02_2023_15_03_38_848.pdf · uploaded 6 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture Certificate.pdf · uploaded 27 Feb 2023Source
  • 1 Copy of Layout Approval (in case of layout)1-1.pdf · uploaded 4 Jun 2023Source
  • 2 Copy of Layout Approval (in case of layout)1.pdf · uploaded 4 Jun 2023Source
  • 1 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 4 Jun 2023Source
  • 2 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 4 Jun 2023Source
  • 3 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 4 Jun 2023Source
  • 4 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 4 Jun 2023Source
  • 5 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 4 Jun 2023Source
  • 6 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 4 Jun 2023Source
  • 2 CERSAI detailsCersai Undertaking.pdf · uploaded 4 Jun 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 4 Jun 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsSharad Namdev Gawade.pdf · uploaded 4 Jun 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account.pdf · uploaded 4 Jun 2023Source
  • 1 Copy of the legal title reportLegal Title Report_compressed.pdf · uploaded 27 Oct 2023Source
  • 2 Copy of the legal title reportSHRIKANT BABASAHEB SATHE.pdf · uploaded 27 Oct 2023Source
  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCES CONCERED TO LEGAL.pdf · uploaded 27 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCES CONCERED TO LEGAL.pdf · uploaded 27 Oct 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C_11zon.pdf · uploaded 27 Oct 2023Source
  • 1 Proforma of Agreement for saleKING TOWER - HARSHAL GAWADE - 26102023.pdf · uploaded 27 Oct 2023Source
  • 1 Proforma of Allotment letterANNEXURE 1.pdf · uploaded 27 Oct 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT FOR ALLOTMENT LETTER.pdf · uploaded 27 Oct 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT FOR AGREEMENT TO SALE.pdf · uploaded 27 Oct 2023Source
  • 1 Other – LegalScan20230812183626.pdf · uploaded 27 Oct 2023Source
  • 2 Other – LegalScan20230812184100.pdf · uploaded 27 Oct 2023Source
  • 3 Other – LegalScan20230812184405.pdf · uploaded 27 Oct 2023Source
  • 4 Other – LegalScan20230812184546.pdf · uploaded 27 Oct 2023Source
  • 5 Other – LegalScan20230812184715.pdf · uploaded 27 Oct 2023Source
  • 6 Other – LegalScan20230812184835.pdf · uploaded 27 Oct 2023Source
  • 1 Other – Technicalorganized 7-1.pdf · uploaded 27 Oct 2023Source
  • 2 Other – Technicalorganized 7-2.pdf · uploaded 27 Oct 2023Source
  • 3 Other – Technicalorganized 7-3.pdf · uploaded 27 Oct 2023Source
  • 4 Other – Technicalorganized 7-4.pdf · uploaded 27 Oct 2023Source
  • 5 Other – Technicalorganized 7-5.pdf · uploaded 27 Oct 2023Source
  • 6 Other – Technicalorganized 7-6.pdf · uploaded 27 Oct 2023Source
  • 7 Other – Technicalorganized 7-7.pdf · uploaded 27 Oct 2023Source
  • 1 Declaration in FORM BAdobe Scan 7 Nov 2023.pdf · uploaded 7 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencment Certificate 13-10-2021.pdf · uploaded 8 Nov 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentSelf Declaration CC Scan.pdf · uploaded 8 Nov 2023Source
  • 8 Other – TechnicalSelf Declaration CC Scan.pdf · uploaded 8 Nov 2023Source
  • 1 Declaration about Commencement CertificateC C deceleration 6:11:23.pdf · uploaded 9 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 18 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 17 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 24 Jul 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate (June-24) - King Tower (DSC).pdf · uploaded 24 Jul 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 8 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate -King Tower(Sep-24) DSC.pdf · uploaded 8 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 8 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 8 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 7 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 7 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 May 2025Source

Technical

  • Document1-1.pdf · uploaded 4 Jun 2023Source
  • Document1.pdf · uploaded 4 Jun 2023Source
  • Document2.pdf · uploaded 4 Jun 2023Source
  • Document3.pdf · uploaded 4 Jun 2023Source
  • Document4.pdf · uploaded 4 Jun 2023Source
  • Document5.pdf · uploaded 4 Jun 2023Source
  • Document6.pdf · uploaded 4 Jun 2023Source
  • Document7.pdf · uploaded 4 Jun 2023Source
  • Other – Technicalorganized 7-1.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-2.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-3.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-4.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-5.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-6.pdf · uploaded 27 Oct 2023Source
  • Other – Technicalorganized 7-7.pdf · uploaded 27 Oct 2023Source
  • Other – TechnicalSelf Declaration CC Scan.pdf · uploaded 8 Nov 2023Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 26 Jul 2024Source
  • DocumentForm-1.pdf · uploaded 8 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 8 Feb 2025Source
  • DocumentFORM 1.pdf · uploaded 7 May 2025Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 24 Jul 2024Source
  • DocumentForm-2.pdf · uploaded 8 Feb 2025Source
  • DocumentForm 2.pdf · uploaded 8 Feb 2025Source
  • DocumentFORM 2.pdf · uploaded 7 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 47/3/6, 47/3/7

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Office space41 units in all
Address
SR NO 47/3/5, 47/3/6, 47/3/7, 47/3/8, 47/3/9 AND 48/2/1, Pune - Bangalore Highway, PunawalePIN 411033
Village
Punawale, Mulshi taluka
Land area for this project
1,584 sq m (17,053 sq ft)
Permissible built-up area
18,961 sq m (2,04,092 sq ft)
Sanctioned built-up area
4,961 sq m (53,398 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

47/3/647/3/747/3/847/3/948/2/1SR NO 47/3/5

Land as published on MahaRERA's project page

SR NO 47/3/5, 47/3/6, 47/3/7, 47/3/8, 47/3/9 AND 48/2/1

Boundaries

North
12 Meter Wide Road
South
Part Survey No 47
East
Part Of Survey No 47
West
18 METER WIDE D PWide D P ROAD

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking41 units

0 of 41 units booked (0%), as the promoter reported to MahaRERA

2BHK · 39 unitsOffice space · 2 units
TypeCarpet areaUnitsBooked
2BHK76.78 sq m · 826 sq ft90
2BHK78.09 sq m · 841 sq ft100
2BHK80.58 sq m · 867 sq ft50
2BHK85.19 sq m · 917 sq ft100
2BHK97.44 sq m · 1,049 sq ft50
Office space138.43 sq m · 1,490 sq ft10
Office space234.21 sq m · 2,521 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr. Paras Subhash Netragaonkar—
Chartered accountantSavalsure And Company—
EngineerRohit Narayan Barane—

Source: MahaRERA project page. Contact details are not shown.