Deedo IDDP-PUN-E79JIts promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 54% of its units are booked.
Pisoli, Pune 411060 · Property rates in Pisoli · by Nirman Trimurti Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 22 Mar 2021, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Rental · Oct 2026
- Rental · Sep 2026
- Other · Aug 2026
- Rental · 22 mo · Aug 2026
- Rental · Aug 2026
- Other · Aug 2026
- Rental · Aug 2026
- Rental · 22 mo · Aug 2026
- Rental · 24 mo · Jul 2026
- Rental · Jul 2026
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Oct 2026 | Wing- A2 · 709 | Rental | — | View Rental, Oct 2026 | |
| Sep 2026 | Wing- A2 · 608 | Rental | — | View Rental, Sep 2026 | |
| Aug 2026 | Wing- A2 · 507 | Other | 532 sq ft | View Other, Aug 2026 | |
| Aug 2026 | Wing- A2 · 205 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | Wing- A2 · 302 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | Wing- A2 · 1109 | Other | 573 sq ft | View Other, Aug 2026 | |
| Aug 2026 | Unit A-1 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | Wing- A2 · 103 | Rental | — | View Rental, Aug 2026 | |
| Jul 2026 | Wing- A2 · 1107 | Rental | — | View Rental, Jul 2026 | |
| Jul 2026 | Wing- A2 · 605 | Rental | — | View Rental, Jul 2026 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100028570
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100028570 | 22 Mar 2021 | 30 Jun 2025 | 30 Jun 2025 | Nirman Trimurti Developers | Project page |
Documents115
1 document held by Deedo, 114 filings listed on MahaRERA's project page
Finance
- PAN Cardpan trimurti.pdf · uploaded 25 Jan 2021Source
Legal
- Legal Title reportSupplymentary Search And Title Report.pdf · uploaded 28 Jan 2021Source
- Declaration Form Bform b_compressed (2).pdf · uploaded 3 Feb 2021Source
- Declaration Form BForm B ajay vasvani new_compressed.pdf · uploaded 3 Mar 2021Source
- OtherREVALIDATION OF CC LETTER.pdf · uploaded 9 Mar 2021Source
- Othermarketing declaration a2.pdf · uploaded 9 Mar 2021Source
- Legal Title reportlegal title report.pdf · uploaded 20 Mar 2021Source
Show all 115 documentsShow fewer documents
Legal
- Legal Title reportlegal title report -flow of title.pdf · uploaded 20 Mar 2021Source
Migrated
- 1 PAN Cardpan trimurti.pdf · uploaded 25 Jan 2021Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 25 Jan 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentHPSC6548_compressed.pdf · uploaded 25 Jan 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentHPSC6549_compressed.pdf · uploaded 25 Jan 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentHPSC6550_compressed.pdf · uploaded 25 Jan 2021Source
- 4 Building Plan Approval / NA Order for plotted developmentHPSC6551_compressed.pdf · uploaded 25 Jan 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 25 Jan 2021Source
- 1 Copy of the legal title reportSupplymentary Search And Title Report.pdf · uploaded 28 Jan 2021Source
- 1 Proforma of Allotment letteragreement for sale.pdf · uploaded 1 Feb 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 2 Feb 2021Source
- 1 Declaration in FORM Bform b_compressed (2).pdf · uploaded 3 Feb 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_compressed.pdf · uploaded 3 Feb 2021Source
- 2 Declaration in FORM BForm B ajay vasvani new_compressed.pdf · uploaded 3 Mar 2021Source
- 1 Details of encumbrancesself declration.pdf · uploaded 9 Mar 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentREVALIDATION OF CC LETTER.pdf · uploaded 9 Mar 2021Source
- 1 OtherREVALIDATION OF CC LETTER.pdf · uploaded 9 Mar 2021Source
- 2 Othermarketing declaration a2.pdf · uploaded 9 Mar 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 10 Mar 2021Source
- 2 Copy of the legal title reportlegal title report.pdf · uploaded 20 Mar 2021Source
- 3 Copy of the legal title reportlegal title report -flow of title.pdf · uploaded 20 Mar 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form No 3.pdf · uploaded 14 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 - Nirman Trimurti Developers.pdf · uploaded 29 Sep 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A-2021.pdf · uploaded 9 Oct 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A-2022.pdf · uploaded 10 Jan 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 A2 2022_compressed (1).pdf · uploaded 13 Jan 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pisoli A2.pdf · uploaded 25 Jan 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 pisoli_compressed.pdf · uploaded 9 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Nirman Rera-Annual Reports Final.pdf · uploaded 4 Oct 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 30 JUN 2021.pdf · uploaded 22 Feb 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 30 SEPT 2021.pdf · uploaded 22 Feb 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 31 DEC 2021.pdf · uploaded 22 Feb 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 31 MAR 2022.pdf · uploaded 22 Feb 2023Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 30 JUN 2022.pdf · uploaded 22 Feb 2023Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 30 SEPT 2022.pdf · uploaded 22 Feb 2023Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 31 DEC 2022.pdf · uploaded 22 Feb 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 JUN 21.pdf · uploaded 22 Feb 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 SEPT 21.pdf · uploaded 22 Feb 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31 DEC 21.pdf · uploaded 22 Feb 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31 MAR 22.pdf · uploaded 22 Feb 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 JUN 22.pdf · uploaded 22 Feb 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 SEPT 22.pdf · uploaded 22 Feb 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31DEC 22.pdf · uploaded 22 Feb 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 30 jun 2021.pdf · uploaded 25 Feb 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 30 sept 2021.pdf · uploaded 25 Feb 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31 mar 2022.pdf · uploaded 25 Feb 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 30 sept 2022.pdf · uploaded 25 Feb 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 31 dec 2022.pdf · uploaded 25 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 june 21_compressed.pdf · uploaded 28 Feb 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 sept 21_compressed.pdf · uploaded 28 Feb 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31 dec 21_compressed.pdf · uploaded 28 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31 march 22_compressed.pdf · uploaded 28 Feb 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 june 22_compressed.pdf · uploaded 28 Feb 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 sept 22_compressed.pdf · uploaded 28 Feb 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31 dec 22_compressed.pdf · uploaded 28 Feb 2023Source
- 1 Proforma of Agreement for saleagreement for sale.pdf · uploaded 10 Jun 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 PISOLI (2).pdf · uploaded 15 Jun 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 ntd (2).pdf · uploaded 4 Jul 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 pisoli 31-3-23_compressed.pdf · uploaded 4 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2a 31 mar 2023.pdf · uploaded 4 Jul 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 NTD.pdf · uploaded 4 Jul 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 pisoli 30 june 2023.pdf · uploaded 25 Aug 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 pisoli 30 june 2023.pdf · uploaded 25 Aug 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FROM 3 30 June 2023_compressed.pdf · uploaded 25 Aug 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A Pisoli.pdf · uploaded 29 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Nirman Rera-Annual Reports Final.pdf · uploaded 26 Sep 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 pisoli 30 sept 2023_compressed.pdf · uploaded 18 Oct 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 -30 sept 2023.pdf · uploaded 13 Dec 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30-09-2023.pdf · uploaded 14 Dec 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 30-09-2023.pdf · uploaded 14 Dec 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)pisoli Form 2A 31 dec 2023.pdf · uploaded 8 Jan 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 pisoli 30-12-23.pdf · uploaded 27 Jan 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Pisoli-31-12-2023_compressed.pdf · uploaded 13 Feb 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 29 Feb 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 31 March 2024.pdf · uploaded 11 Apr 2024Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 9 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 17 May 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 May 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q1.pdf · uploaded 21 Jun 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q2.pdf · uploaded 21 Jun 2024Source
- 3 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q3.pdf · uploaded 21 Jun 2024Source
- 4 Disclosure of sold/ booked inventoryDisclosure of sold or unsold Inventory Q4.pdf · uploaded 21 Jun 2024Source
- 5 Disclosure of sold/ booked inventoryNirman Disclosure of sold or unsold Inventory Q1.pdf · uploaded 19 Jul 2024Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 1 Aug 2024Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Aug 2024Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3_compressed.pdf · uploaded 1 Aug 2024Source
- 2 Disclosure of sold/ booked inventoryNirman Disclosure of sold or unsold Inventory Q2.pdf · uploaded 25 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Nirman Rera-Annual Reports statement.pdf · uploaded 29 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)pisolin 30 sept 2024.pdf · uploaded 25 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3.pdf · uploaded 27 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 5 Dec 2024Source
- 1 Disclosure of sold/ booked inventoryNirman Disclosure of sold or unsold Inventory Q3.pdf · uploaded 10 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 24 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryNirman Disclosure of sold or unsold Inventory Q4.pdf · uploaded 3 May 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 6/1/14, 6/1/15
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK108 units in all
- Address
- 6/1/14, 6/1/15, 6/1/18, 6/2/1, 6/2/2 Pisoli, Pisoli Fursungi Road, PisoliPIN 411060
- Village
- Pisoli, Haveli taluka
- Location
- 19.38750, 75.16320
- Land area for this project
- 1,842 sq m (19,831 sq ft)
- Permissible built-up area
- 10,393 sq m (1,11,871 sq ft)
- Sanctioned built-up area
- 6,285 sq m (67,653 sq ft)
- Recreational open space
- 922 sq m (9,923 sq ft)
- Designated bank account
- 230
- Developed in phases
- No
- Also registered as
- Brookfield Viloes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
6/1/14,6/1/15,6/1/18,6/2/1,6/2/2 PISOLI
Boundaries
- North
- A1 Building Of Same Layout
- South
- Driveway A3 Building Of Same Layout
- East
- Drive Way
- West
- Open Space
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking108 units
58 of 108 units booked (54%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 46.22 sq m · 498 sq ft | 6 | 5 |
| 2BHK | 46.25 sq m · 498 sq ft | 1 | 0 |
| 2BHK | 46.35 sq m · 499 sq ft | 4 | 1 |
| 2BHK | 46.47 sq m · 500 sq ft | 12 | 5 |
| 2BHK | 49.46 sq m · 532 sq ft | 15 | 6 |
| 2BHK | 49.48 sq m · 533 sq ft | 4 | 4 |
| 2BHK | 50.13 sq m · 540 sq ft | 1 | 0 |
| 2BHK | 52.2 sq m · 562 sq ft | 6 | 4 |
Show all 20 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 52.41 sq m · 564 sq ft | 5 | 5 |
| 2BHK | 52.44 sq m · 564 sq ft | 4 | 4 |
| 2BHK | 52.96 sq m · 570 sq ft | 11 | 10 |
| 2BHK | 53.28 sq m · 574 sq ft | 6 | 5 |
| 2BHK | 55.41 sq m · 596 sq ft | 5 | 3 |
| 2BHK | 56.46 sq m · 608 sq ft | 6 | 4 |
| 3BHK | 61.41 sq m · 661 sq ft | 4 | 1 |
| 3BHK | 61.71 sq m · 664 sq ft | 1 | 0 |
| 3BHK | 63.2 sq m · 680 sq ft | 4 | 1 |
| 3BHK | 63.5 sq m · 684 sq ft | 1 | 0 |
| 3BHK | 64.09 sq m · 690 sq ft | 6 | 0 |
| 3BHK | 65.49 sq m · 705 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Prakash Kulkarni | — |
| Chartered accountant | CA Vinay Chordiya CA Vinay Chordiya | — |
| Engineer | G A bhilare Consultants pvt ltd | — |
Source: MahaRERA project page. Contact details are not shown.
Brookefield Willows- A2 in numbers
Registered deals, summarised
Deedo has 466 registered documents at Brookefield Willows- A2, from Feb 2015 to Oct 2026: 100 sales, 121 leave and licence agreements, 136 mortgages. The median registered sale since Feb 2015 works out to about ₹7,900 per sq ft, at a median of ₹43 L a deal; 0% of sales were resales.
- What is the price per sq ft at Brookefield Willows- A2?
- The median registered sale since Feb 2015 works out to about ₹7,900 per sq ft, at a median of ₹43 L a deal; 0% of sales were resales.
- How many properties have been sold at Brookefield Willows- A2?
- 100 sales are registered at Brookefield Willows- A2.
- Are properties at Brookefield Willows- A2 rented out?
- Yes: 121 leave and licence agreements are registered at Brookefield Willows- A2, at a median rent since Feb 2015 of about ₹11,000 a month with a deposit of about ₹25,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Brookefield Willows- A2 by Deedo, last updated with deals registered in Oct 2026.
Latest deal · Rental · Oct 2026