Destination El Progreso
Deedo IDDP-PUN-9C0SMahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 36% of its units are booked.
Moshi, Pune 412105 · Property rates in Moshi · by El Progreso Ventures
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year
- This projectRegistered 22 Oct 2020, completion promised 30 Jun 2024, revised to 30 Jun 2025.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- 6sSize not on record100% booked
- A Building16 floors · 112 units36% booked
- Building (P52100026761)Size not on record100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100026761
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100026761 | 22 Oct 2020 | 30 Jun 2024 | 30 Jun 2025 | El Progreso Ventures | Project page |
Documents115
3 documents held by Deedo, 112 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Show all 115 documentsShow fewer documents
Legal
- Legal Title reportAOP OF EL PROGRESO VENTURES compressed.pdf · uploaded 21 Sep 2020Source
- Legal Title reportDA GATKAL_compressed-1-10.pdf · uploaded 21 Sep 2020Source
- Legal Title reportDA GATKAL_compressed-11-20.pdf · uploaded 21 Sep 2020Source
- Legal Title reportDA GATKAL_compressed-21-35.pdf · uploaded 21 Sep 2020Source
- Legal Title reportGATKAL POA_compressed.pdf · uploaded 21 Sep 2020Source
- Declaration Form B1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (1).pdf · uploaded 20 Oct 2023Source
Migrated
- 1 PAN Cardcompany pan card.pdf · uploaded 21 Sep 2020Source
- 1 Copy of the legal title reportSEARCH REPORT 28 5 R compressed.pdf · uploaded 21 Sep 2020Source
- 2 Copy of the legal title reportAOP OF EL PROGRESO VENTURES compressed.pdf · uploaded 21 Sep 2020Source
- 3 Copy of the legal title reportDA GATKAL_compressed-1-10.pdf · uploaded 21 Sep 2020Source
- 4 Copy of the legal title reportDA GATKAL_compressed-11-20.pdf · uploaded 21 Sep 2020Source
- 5 Copy of the legal title reportDA GATKAL_compressed-21-35.pdf · uploaded 21 Sep 2020Source
- 6 Copy of the legal title reportGATKAL POA_compressed.pdf · uploaded 21 Sep 2020Source
- 1 Details of encumbrancesNO ENCUMBARANCE CERTIFICATE.pdf · uploaded 21 Sep 2020Source
- 1 Copy of Layout Approval (in case of layout)layout compressed.pdf · uploaded 21 Sep 2020Source
- 2 Copy of Layout Approval (in case of layout)IOD ARCHITECT LETTER.pdf · uploaded 21 Sep 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentNA ORDER compressed.pdf · uploaded 21 Sep 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE 12 09 2020.pdf · uploaded 21 Sep 2020Source
- 1 Declaration in FORM BB Form Amit Gavhane compressed.pdf · uploaded 21 Sep 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Cert 25 0 R.pdf · uploaded 21 Sep 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A 17 09 2020 compressed.pdf · uploaded 21 Sep 2020Source
- 1 Proforma of Allotment letterALLOTMENT LETTER EL PROGESSO.pdf · uploaded 21 Sep 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)REVISED FORM 3 CA_compressed.pdf · uploaded 7 Oct 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Revised compressed.pdf · uploaded 9 Oct 2020Source
- 2 Proforma of Allotment letterAgreement Draft Final EL PROGRESO.pdf · uploaded 12 Oct 2020Source
- 2 PAN CardEL PROGRESO VENTURES PAN CARD NEW.pdf · uploaded 21 Apr 2021Source
- 3 Copy of Layout Approval (in case of layout)1-4_compressed.pdf · uploaded 27 Apr 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentBP-CC Borhadewadi-10-2021_compressed.pdf · uploaded 27 Apr 2021Source
- 3 PAN CardEL Progresso Partneship DEED.pdf · uploaded 30 Apr 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 12 May 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 12 May 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 28 May 2021Source
- 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 5 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form EL Progreso.pdf · uploaded 5 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 17 09 2020 compressed.pdf · uploaded 6 Jul 2021Source
- 1 Disclosure of sold/ booked inventoryDiscolsure Sold Unsold.pdf · uploaded 21 Jul 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)EL progresso June 21.pdf · uploaded 18 Sep 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Destination EL progreso -- Form 2.pdf · uploaded 18 Apr 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MARCH 22 EL PROGRESSO.pdf · uploaded 18 Apr 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Apr 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)NEW Form 1 EL RRO (Pravin More.pdf · uploaded 30 Jun 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- El progreso_compressed.pdf · uploaded 30 Jun 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certtificate El Progresso 'A' RERA for 20 June 2022.pdf · uploaded 30 Jun 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 30-09-2022 EL-Progreso.pdf · uploaded 20 Oct 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)E L Progresso A 25 Sept 2022.pdf · uploaded 20 Oct 2022Source
- 4 Copy of Layout Approval (in case of layout)1 (2) (1)_compressed.pdf · uploaded 16 Dec 2022Source
- 2 Building Plan Approval / NA Order for plotted development2 (2) (1)_compressed.pdf · uploaded 16 Dec 2022Source
- 3 Building Plan Approval / NA Order for plotted development2 (4)_compressed.pdf · uploaded 16 Dec 2022Source
- 4 Building Plan Approval / NA Order for plotted development3 (2)_compressed.pdf · uploaded 16 Dec 2022Source
- 5 Building Plan Approval / NA Order for plotted development4 (1)_compressed.pdf · uploaded 16 Dec 2022Source
- 2 Declaration about Commencement CertificateDeclaration (Format - D) EL-Progreso.pdf · uploaded 16 Dec 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 08-12-22 EL Progreso (1).pdf · uploaded 16 Jan 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Destination EL PROGRESO.pdf · uploaded 16 Jan 2023Source
- 2 Disclosure of sold/ booked inventoryEL Progreso A Bldg Sold-Unsold.pdf · uploaded 16 Jan 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)El Progreso A Bldg F3_compressed.pdf · uploaded 16 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form -5 El Progreso Ventures -2021-22.pdf · uploaded 25 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)EL Progresso Ventures-Form-5.pdf · uploaded 1 Feb 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 El Progresso A Bldg (1).pdf · uploaded 4 Apr 2023Source
- 3 Disclosure of sold/ booked inventorySold Unsold EL Progreso.pdf · uploaded 4 Apr 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Destination El progresso form 2.pdf · uploaded 7 Apr 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 EL progresso A Bldg.pdf · uploaded 27 Apr 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 EL-Progreso A Bldg.pdf · uploaded 27 Jun 2023Source
- 4 Disclosure of sold/ booked inventorySold Unsold EL Progreso A Bldg.pdf · uploaded 27 Jun 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)EL progressive Ventures.pdf · uploaded 28 Jun 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)EL Progresso A Bldg_compressed.pdf · uploaded 19 Jul 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 El Progreso A Bldg.pdf · uploaded 27 Sep 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)qu f2 destination EL sep 23.pdf · uploaded 27 Sep 2023Source
- 5 Disclosure of sold/ booked inventorySold Unsold El Progreso A building.pdf · uploaded 27 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A, EL Progreso A Bldg.pdf · uploaded 11 Oct 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentSold Dec 2020_rotated (3) (1).pdf · uploaded 17 Oct 2023Source
- 6 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 17 Oct 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Dec 2022 (1).pdf · uploaded 17 Oct 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)EL Progresso Ventures A BLDG_11zon.pdf · uploaded 19 Oct 2023Source
- 2 Declaration in FORM B1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (1).pdf · uploaded 20 Oct 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (1).pdf · uploaded 20 Oct 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (2).pdf · uploaded 20 Oct 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)GetUserDocumentFileContent (14) (1).pdf · uploaded 20 Oct 2023Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)GetUserDocumentFileContent (14) (1) (1).pdf · uploaded 20 Oct 2023Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)GetUserDocumentFileContent (15) (1).pdf · uploaded 20 Oct 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)El Progresso A Bldg 3.pdf · uploaded 20 Oct 2023Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)EL PRogresso A bldg.pdf · uploaded 20 Oct 2023Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)E L Progresso A 25 Sept 2022.pdf · uploaded 20 Oct 2023Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)El Progresso 'A' RERA for 20 June 2022.pdf · uploaded 20 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)EL Progresso Ventures (1).pdf · uploaded 1 Nov 2023Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1 El Progreso A Bldg.pdf · uploaded 23 Dec 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)el progresso A.pdf · uploaded 23 Dec 2023Source
- 7 Disclosure of sold/ booked inventorySold Unsold A Bldg EL Progreso.pdf · uploaded 26 Dec 2023View
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3 El Progress A Build.pdf · uploaded 6 Jan 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBorhadewadi Gat No 75 Plot No B Building A hello hello completion.pdf · uploaded 21 Mar 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form - 4 09-07-2024 (2).pdf · uploaded 18 Jan 2025Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Destination EL Progreso A Bldg Society Certificate (3).pdf · uploaded 18 Jan 2025Source
- 1 CERSAI detailsCERSAI_Search_Report_200335998847_For_Asset_Based_Search_18_01_2025_18_07_19_990.pdf · uploaded 18 Jan 2025Source
- 2 CERSAI detailsCERSAI decalaration.pdf · uploaded 21 Jan 2025Source
- 3 CERSAI detailsdeclaration for change in Address (1) FINAL.pdf · uploaded 21 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)ELPV Form 5 FY 23-24.pdf · uploaded 3 Feb 2025Source
Technical
- Documentlayout compressed.pdf · uploaded 21 Sep 2020Source
- DocumentNA ORDER compressed.pdf · uploaded 21 Sep 2020Source
- DocumentIOD ARCHITECT LETTER.pdf · uploaded 21 Sep 2020Source
- Document1-4_compressed.pdf · uploaded 27 Apr 2021Source
- Document1 (2) (1)_compressed.pdf · uploaded 16 Dec 2022Source
- Document2 (2) (1)_compressed.pdf · uploaded 16 Dec 2022Source
- Document2 (4)_compressed.pdf · uploaded 16 Dec 2022Source
- Document3 (2)_compressed.pdf · uploaded 16 Dec 2022Source
- Document4 (1)_compressed.pdf · uploaded 16 Dec 2022Source
- DocumentSold Dec 2020_rotated (3) (1).pdf · uploaded 17 Oct 2023Source
Technical (Architect)
- DocumentForm -1 El Progreso A Bldg.pdf · uploaded 23 Dec 2023Source
Technical (Engineer)
- Documentel progresso A.pdf · uploaded 23 Dec 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Gat No 75 Borhadewadi
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Shop112 units in all
- Address
- Gat No 75 Borhadewadi, BORHADEWADI, MOSHI PRADHIKARANPIN 412105
- Village
- Pimpri Chinchawad (M Corp.), Haveli taluka
- Location
- 18.66428, 73.83189
- Land area for this project
- 2,850 sq m (30,677 sq ft)
- Permissible built-up area
- 4,273 sq m (45,990 sq ft)
- Sanctioned built-up area
- 2,592 sq m (27,898 sq ft)
- Recreational open space
- 287 sq m (3,090 sq ft)
- Designated bank account
- 103
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gat No 75 Borhadewadi
Boundaries
- North
- Gat No 74 P And 75 P New
- South
- Remaining Land Of Gat No 75 P New
- East
- 12 M Wide Road
- West
- Gat No 79 P New
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking112 units
40 of 112 units booked (36%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 52.47 sq m · 565 sq ft | 2 | 0 |
| 2BHK | 54.32 sq m · 585 sq ft | 13 | 4 |
| 2BHK | 55.77 sq m · 600 sq ft | 13 | 13 |
| 2BHK | 56.62 sq m · 609 sq ft | 13 | 5 |
| 2BHK | 56.9 sq m · 612 sq ft | 13 | 4 |
| 2BHK | 57.52 sq m · 619 sq ft | 13 | 0 |
| 2BHK | 57.77 sq m · 622 sq ft | 13 | 0 |
| 3BHK | 66.18 sq m · 712 sq ft | 11 | 7 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 66.87 sq m · 720 sq ft | 13 | 7 |
| Shop | 12.49 sq m · 134 sq ft | 2 | 0 |
| Shop | 13.87 sq m · 149 sq ft | 5 | 0 |
| Shop | 22.08 sq m · 238 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Patil & Bugade Associates | — |
| Chartered accountant | Hary Kurup & Associates | — |
| Engineer | Pravin More | — |
| Other | Shree Ganesh Construction | — |
Source: MahaRERA project page. Contact details are not shown.