Residential / Group Housing · 5 buildings · 108 unitsRERA P52100004088

Playtor Paud C- Phase 1

Deedo IDDP-PUN-JAD1

MahaRERA shows it completed, after its date was pushed back 4 years; no MahaRERA orders on record; 39% of its units are booked.

Paud, Pune 412108 · by Sangam Realty · 0% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 4 yrs extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales39% booked42 of 108 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 4 years

  • This projectRegistered 7 Aug 2017, completion promised 31 Mar 2019, revised to 29 Mar 2023.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100004088
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000040887 Aug 201731 Mar 201929 Mar 2023Sangam RealtyProject page
Documents44

3 documents held by Deedo, 41 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPan -Sangam Realty.pdf · uploaded 8 Jul 2017Source

Legal

  • Legal Title reportGat No-266_Title Report.pdf · uploaded 8 Jul 2017Source
  • Declaration Form BForm B_Promoter_Paud C ph 1.pdf · uploaded 29 Jul 2017Source

Migrated

  • 1 PAN CardPan -Sangam Realty.pdf · uploaded 8 Jul 2017Source
  • 1 Copy of the legal title reportGat No-266_Title Report.pdf · uploaded 8 Jul 2017Source
Show all 44 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)scan976_2.pdf · uploaded 8 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommisment Certificate_Paud C_Revised.pdf · uploaded 8 Jul 2017Source
  • 1 Details of encumbrancesEncum Index 1137-17_Paud C.pdf · uploaded 15 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cer_Form 1_Paud C1.pdf · uploaded 19 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cer_Form 1_Paud C3.pdf · uploaded 19 Jul 2017Source
  • 1 Building Plan Approval (IOD)IOD_Paud C ph 1.pdf · uploaded 26 Jul 2017Source
  • 1 Declaration in FORM BForm B_Promoter_Paud C ph 1.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Engineer Cert_Paud C Ph 1.PDF · uploaded 29 Jul 2017Source
  • 1 Proforma of Allotment letter6_Sale Agreement_Paud C_Ph 1.pdf · uploaded 29 Jul 2017Source
  • 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)FORM 3_Paud C ph 1.pdf · uploaded 31 Jul 2017Source
  • 3 Proforma of Allotment letterRevised Allotment (Booking) letter_RERA.pdf · uploaded 14 Nov 2017Source
  • 2 Details of encumbrancesIndex 2 Mortgage Deed Fullerton.pdf · uploaded 19 Dec 2018Source
  • 3 Details of encumbrancesIndex 2 Release Edelweiss.pdf · uploaded 20 Dec 2018Source
  • 1 Certificates of CA (Form 5)Form 5_CA-Paud C Ph 1.pdf · uploaded 9 Jan 2019Source
  • 2 Certificates of CA (Form 5)Form 5_CA- Paud C Ph 1 - 09-01-2020.pdf · uploaded 22 Jan 2020Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sangam Phase 1 C1 Building.pdf · uploaded 24 Jan 2020Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sangam Phase 1 C3 Building.pdf · uploaded 24 Jan 2020Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineering Certificate Paud C Ph 1.pdf · uploaded 24 Jan 2020Source
  • 2 Certificates of CA (Form 3)Form 3_CA Cartificate_Paud C Ph 1.pdf · uploaded 24 Jan 2020Source
  • 3 Certificates of CA (Form 3)Form 3 Sangam 2019 Paud C Ph 1 Signed_compressed.pdf · uploaded 24 Jan 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 (Architect Completion Certificate) - Paud C3 Bldg .pdf · uploaded 9 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Paud C Phase 1.pdf · uploaded 19 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Qulity Assurance Certificate FY 19-20.pdf · uploaded 5 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate FY 20-21.pdf · uploaded 5 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 FY 20-21.pdf · uploaded 5 Apr 2022Source
  • 1 Declaration about Commencement CertificateDeclaration Regarding Commencement.pdf · uploaded 6 Apr 2022Source
  • 1 Disclosure of sold/ booked inventoryinventory.pdf · uploaded 6 Apr 2022View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 FY 18-19.pdf · uploaded 8 Apr 2022Source
  • 4 Certificates of CA (Form 3)FORM 3__22-23_Paud C_11zon.pdf · uploaded 26 Jul 2023Source
  • 5 Certificates of CA (Form 3)Form 3_11zon.pdf · uploaded 3 Aug 2023Source
  • 3 Certificates of CA (Form 5)Form 5_11zon.pdf · uploaded 3 Aug 2023Source

Technical

  • Documentscan976_2.pdf · uploaded 8 Jul 2017Source
  • DocumentIOD_Paud C ph 1.pdf · uploaded 26 Jul 2017Source

Technical (Architect)

  • DocumentSangam Phase 1 C3 Building.pdf · uploaded 24 Jan 2020Source

Technical (Engineer)

  • DocumentEngineering Certificate Paud C Ph 1.pdf · uploaded 24 Jan 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 266, Gat no 245

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1.5BHK, 1BHK, 1RK108 units in all
Address
Gat no 245, 266, Paud-Mulshi Road, Next to Tehsil OfficePIN 412108
Village
Paud, Mulshi taluka
Land area for this project
2,052 sq m (22,090 sq ft)
Permissible built-up area
3,361 sq m (36,182 sq ft)
Sanctioned built-up area
3,263 sq m (35,125 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

266Gat no 245

Land as published on MahaRERA's project page

Gat no 245, 266

Boundaries

North
Op Space 2 and 12 mts Road
South
Adj Forest Property
East
Gat No 221
West
Internal 12 mts Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking108 units

42 of 108 units booked (39%), as the promoter reported to MahaRERA

1.5BHK · 32 units1BHK · 37 units1RK · 39 units
BuildingTypeCarpet areaUnitsBooked
C11.5BHK32 sq m · 344 sq ft126
C11.5BHK32.06 sq m · 345 sq ft84
C11.5BHK32.2 sq m · 347 sq ft80
C11.5BHK36.76 sq m · 396 sq ft40
C11BHK22.01 sq m · 237 sq ft20
C11BHK22.96 sq m · 247 sq ft1616
C11BHK22.99 sq m · 247 sq ft120
C11BHK26.27 sq m · 283 sq ft22
Show all 16 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
C31BHK21.61 sq m · 233 sq ft33
C31BHK22.01 sq m · 237 sq ft11
C31BHK24 sq m · 258 sq ft10
C31RK13.16 sq m · 142 sq ft44
C31RK13.29 sq m · 143 sq ft43
C31RK15.79 sq m · 170 sq ft180
C31RK16.25 sq m · 175 sq ft90
C31RK16.48 sq m · 177 sq ft43

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals10

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash Nawathe—
EngineerSspa—
OtherBics—
OtherChandrasekara—
OtherS N Joshi Consultants Pvt. Ltd.—
OtherTricon Infra Buildtech Pvt Ltd—
OtherVishwas Electric Services—
Registered real estate agentPhalcomm Infra Solutions Private Limited—
Registered real estate agentPulin Goradia—
Registered real estate agentSuresh Malku Kirtikar—

Source: MahaRERA project page. Contact details are not shown.