Sangam Realty
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+36 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Chakan AnnexP52100002851 | Pimpalgaon Tarf Khed | 2017 | Not reported | 29 Jun 2020 | 30 Jun 2023 | +36 months |
| Playtor Paud C- Phase 1P52100004088 | Paud | 2017 | Not reported | 31 Mar 2019 | 29 Mar 2023 | +48 months |
| Playtor Paud D- Phase 2P52100018651 | Paud | 2018 | Not reported | 25 Sep 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 48 months, for Playtor Paud C- Phase 1 (P52100004088).
Regulatory cases across projects
- DeregisteredDeregistered: Playtor Paud D- Phase 2 · Playtor Paud D- Phase 2 · P52100018651
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology