Company or firm · first RERA registration 2017

Sangam Realty

Deedo IDDD-0K2V

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay48 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredPlaytor Paud D- Phase 2Deregistered: Playtor Paud D- Phase 2Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Chakan AnnexP52100002851Pimpalgaon Tarf KhedCertificate Signed29 Jun 202030 Jun 2023+77 mo*
Playtor Paud C- Phase 1P52100004088PaudCertificate Signed31 Mar 201929 Mar 2023+48 mo
Playtor Paud D- Phase 2P52100018651PaudCertificate Signed25 Sep 202625 Sep 2026+2 mo*

Sangam Realty, in questions

Does Sangam Realty finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sangam Realty registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Sangam Realty have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology