Sangam Realty
Deedo IDDD-0K2VOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay48 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Playtor Paud D- Phase 2Deregistered: Playtor Paud D- Phase 2 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Chakan AnnexP52100002851 | Pimpalgaon Tarf Khed | Certificate Signed | 29 Jun 2020 | 30 Jun 2023 | +77 mo* |
| Playtor Paud C- Phase 1P52100004088 | Paud | Certificate Signed | 31 Mar 2019 | 29 Mar 2023 | +48 mo |
| Playtor Paud D- Phase 2P52100018651 | Paud | Certificate Signed | 25 Sep 2026 | 25 Sep 2026 | +2 mo* |
Sangam Realty, in questions
Does Sangam Realty finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sangam Realty registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Sangam Realty have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology