RERA projects in Nigade

1 project under 1 MahaRERA registration, registered 2017–2017. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
12 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171

Projects in Nigade

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Ntlf IstaNew Town Leasing And Finance Pvt LtdP5210000686316 Aug 201731 Jan 201931 Jan 2020Extended 12 mo0

Other localities in Mawal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. New Town Leasing And Finance Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology