Extended 12 mo3 floorsRERA P52100001638
M, Kuber Aangan
Deedo IDDP-PUN-JN8B-MMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked100%4 of 4 · MahaRERA
Completion28 Apr 202328 Apr 2022 · revised
Units & parking in M
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 55.9 m² (602 sq.ft) | 2 | 2 |
| 3 BHK | 90 m² (969 sq.ft) | 2 | 2 |
As registered with MahaRERA
- RERA registration
- P52100001638 · registered 29 Jul 2017
- Promised completion
- 28 Apr 2022
- Revised completion
- 28 Apr 2023
- Sanctioned habitable floors
- 3
- Sanctioned floors (incl. basement, stilt, podium)
- 3
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-JN8B-M
Questions about M
When is M due for completion?
The MahaRERA registration promises 28 Apr 2022, revised to 28 Apr 2023.
How many floors does M have?
3 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology