Kuber Aangan
Deedo IDDP-PUN-JN8BCompletion was pushed back 1 year to Apr 2023, and that date has passed too; no MahaRERA orders on record; 69% of its units are booked.
Narayangaon, Pune 410504 · by Kuber Builders
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Apr 2023, and that date has passed too
- This projectRegistered 29 Jul 2017, completion promised 28 Apr 2022, revised to 28 Apr 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
16 buildings
Open a building to see every flat, floor by floor.
- 03 floors · 4 units75% booked
- A6 floors · 16 units38% booked
- B6 floors · 16 units38% booked
- C6 floors · 16 units6% booked
- D6 floors · 16 units50% booked
- E6 floors · 16 units94% booked
- F6 floors · 16 units100% booked
- G6 floors · 16 units94% booked
- H6 floors · 16 units94% booked
- I6 floors
- J1 floor · 4 units100% booked
- K3 floors · 4 units100% booked
Show all 16 buildingsShow fewer buildings
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100001638
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100001638 | 29 Jul 2017 | 28 Apr 2022 | 28 Apr 2023 | Kuber Builders | Project page |
Documents46
2 documents held by Deedo, 44 filings listed on MahaRERA's project page
Finance
Legal
- Legal Title reportLegal-Report part 1.pdf · uploaded 25 Jul 2017Source
- Legal Title reportLegal-Report part 2.pdf · uploaded 25 Jul 2017Source
- Legal Title reportLegal-Report part 3.pdf · uploaded 25 Jul 2017Source
- Declaration Form BForm - B Affidavit Cum Declaration - Compressed.pdf · uploaded 25 Jul 2017Source
Show all 46 documentsShow fewer documents
Migrated
- 1 PAN CardPAN - KUBER BUILDERS.pdf · uploaded 14 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)A4 - Reduction Plans COMPRESSED.pdf · uploaded 14 Jul 2017Source
- 1 Copy of the legal title reportLegal-Report part 1.pdf · uploaded 25 Jul 2017Source
- 2 Copy of the legal title reportLegal-Report part 2.pdf · uploaded 25 Jul 2017Source
- 3 Copy of the legal title reportLegal-Report part 3.pdf · uploaded 25 Jul 2017Source
- 1 Details of encumbrancesKuber Builders - Non Incumbereances.pdf · uploaded 25 Jul 2017Source
- 1 Building Plan Approval (IOD)A4 - Reduction Plans COMPRESSED.pdf · uploaded 25 Jul 2017Source
- 1 Declaration in FORM BForm - B Affidavit Cum Declaration - Compressed.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect-Certificate part 1.pdf · uploaded 25 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect-Certificate part 2.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate Kuber Aang.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of CA (Form 3)CA - Certificate Kuber Aangan Compressod.pdf · uploaded 25 Jul 2017Source
- 1 Proforma of Allotment letterAGREEMENT.pdf · uploaded 25 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentNA - Order Aangan.pdf · uploaded 9 Apr 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLATION ghi and Row house.pdf · uploaded 1 Jan 2021Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Reg Certificate.pdf · uploaded 21 Sep 2021Source
- 1 Declaration about Commencement CertificateRERA OPTIMIZED.pdf · uploaded 14 Mar 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)COMBIN qUTY 20 COM.pdf · uploaded 14 Mar 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)qUALITY CERTIFICATE1.pdf · uploaded 14 Mar 2022Source
- 1 Disclosure of sold/ booked inventoryAANGAN COSTOMER LIST (1)pdf.pdf · uploaded 14 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)ITR - 17-18.pdf · uploaded 14 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)KUBER BUILDERS - ITR AY 2018-19 (2).pdf · uploaded 14 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)KUBER BUILDERS - ITR AY 2019-20.pdf · uploaded 14 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Kuber Builders - ITR FY 2020-2021 Compress.pdf · uploaded 14 Mar 2022Source
- 1 CERSAI detailsCERSAI_Sear ANGAN 1.pdf · uploaded 8 Apr 2022Source
- 2 CERSAI detailsCersai search report of lala.pdf · uploaded 16 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM 5 - FY 2017 - 18.pdf · uploaded 16 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 - FY 2018 - 19.pdf · uploaded 16 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 - FY 2019 - 20.pdf · uploaded 16 Apr 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 - FY 2020 - 21.pdf · uploaded 16 Apr 2022Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentABC DEF COMPLATION CERTIFICATE.pdf · uploaded 26 Jun 2023Source
- 2 Disclosure of sold/ booked inventorybooked flats.pdf · uploaded 22 Jul 2023Source
- 1 Other – FinanceAccount Closer.pdf · uploaded 13 Mar 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 (1).pdf · uploaded 5 Nov 2024Source
Technical
Technical (Architect)
- DocumentArchitect-Certificate part 2.pdf · uploaded 25 Jul 2017Source
Technical (Engineer)
- DocumentEngg Certificate Kuber Aang.pdf · uploaded 25 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SR NO 217/5/7/8/9/10/11/17/18
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, 3BHK, 1.5 BHK, 2BHK, 1.5bhk, 1.5BHK, 1BHK, Shop, 3 BHK156 units in all
- Address
- SR NO 217/5/7/8/9/10/11/17/18, Ozer Road, KolhemalaPIN 410504
- Village
- Narayangaon, Junnar taluka
- Location
- 19.05211, 72.90067
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Hissa No 1 Part
- South
- Ozar Road Kolhemala
- East
- Sr No 260
- West
- Internal Road Hissa No 10 And 11
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking156 units
108 of 156 units booked (69%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| 0 | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| 0 | 3BHK | 90.02 sq m · 969 sq ft | 2 | 1 |
| A | 1.5 BHK | 48.49 sq m · 522 sq ft | 8 | 1 |
| A | 2BHK | 56.95 sq m · 613 sq ft | 8 | 5 |
| B | 1.5bhk | 48.77 sq m · 525 sq ft | 16 | 6 |
| C | 1.5BHK | 48.49 sq m · 522 sq ft | 8 | 1 |
| C | 2BHK | 56.95 sq m · 613 sq ft | 8 | 0 |
| D | 1.5BHK | 50 sq m · 538 sq ft | 8 | 4 |
Show all 26 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| D | 2BHK | 57.15 sq m · 615 sq ft | 8 | 4 |
| E | 1BHK | 38.83 sq m · 418 sq ft | 16 | 15 |
| F | 1.5BHK | 49.98 sq m · 538 sq ft | 8 | 8 |
| F | 2 BHK | 57.13 sq m · 615 sq ft | 8 | 8 |
| G | 1BHK | 35.3 sq m · 380 sq ft | 8 | 7 |
| G | 2 BHK | 53.42 sq m · 575 sq ft | 8 | 8 |
| H | 1BHK | 35.3 sq m · 380 sq ft | 16 | 15 |
| J | Shop | 19.6 sq m · 211 sq ft | 4 | 4 |
| K | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| K | 3 BHK | 90.02 sq m · 969 sq ft | 2 | 2 |
| L | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| L | 3 BHK | 90.02 sq m · 969 sq ft | 2 | 2 |
| M | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| M | 3 BHK | 90.02 sq m · 969 sq ft | 2 | 2 |
| N | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| N | 3BHK | 90.02 sq m · 969 sq ft | 2 | 1 |
| P | 2 BHK | 55.93 sq m · 602 sq ft | 2 | 2 |
| P | 3BHK | 90.02 sq m · 969 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Cubix Architects | — |
| Engineer | G A Bhilare Consultants Pvt Ltd | — |
| Other | Kuber Properties | — |
| Other | Swanand Dhondse | — |
Source: MahaRERA project page. Contact details are not shown.